Andres LNG Terminal Expansion Project

Weekly Progress Report


Report Period: 06/Sept/2021(Monday) ~ 12/Sept/2021(Sunday)

12th September 2021


7. Quality Status
7.1 Accomplishment of this week
7.1.1 Common
 Rebar Receiving from San Cristobal Inspection (Continue)
 Sector 9 #1: GPR Test
 ELT-01-CQ-PC-0101 ITP for Concrete Works RC Submittal
 ELT-01-CQ-PC-0102 ITP for Topography RB Submittal
 ELT-01-MQ-PC-0009 Welder Qualification procedure submittal
 ELT-05-CT-PC-0001 Inspection and Test Plan for LNG Tank Installation submittal
7.1.2 Mechanical
 Sector 2. Pedestal Anchor bolts/boxes installation inspection
 Sector 2. Pedestal Anchor bolts Location and Verification inspection
 Sector 3. Pedestal Anchor bolts installation inspection
: Partial inspection
7.1.3 Electrical
 Sector 2. Pedestal Tank Slab Heating System installation inspection
 Sector 3. Pedestal Tank Slab Heating System installation inspection
: Partial inspection (conduits installation)
 Medium voltage Electric Works Installation Overlap with Andres I Temporary Power (Continue)
 Medium voltage Electrical Disconnector and Cut out Installation Inspection in Temporary Power
(Continue)
7.1.4 Civil
 Sector 2. Pedestal Rebar Work, Inclinometer, Anchor boxes and Tank Slab Heating System
inspection
 Sector 2: Pedestal MOPC Inspection for LNG Tank
: Pedestal 2 covers 34m
7. Quality Status
7.1 Accomplishment of this week (Continue)
7.1.4 Civil (Continue)
 Sector 3. Pedestal Rebar Work, Inclinometer, Anchor bolts and Tank Slab Heating System inspection
: Partial inspection (Rebar, formworks, conduits installation)
 Sector 6. Foundation Rebar Work Inspection
 Sector 6: MOPC Inspection for LNG Tank Foundation
 Sector 6: Foundation Concrete Pouring
 Sector 6: Foundation Post Pouring Inspection
 Sector 7. Foundation Rebar Work Inspection
 Sector 7: MOPC Inspection for LNG Tank Foundation
 Sector 8. Foundation Rebar Work Inspection
 Sector 8: MOPC Inspection for LNG Tank Foundation
 Sector 8: Foundation Concrete Pouring
 Sector 8: Foundation Post Pouring Inspection
 Sector 7 & 8: Lean Concrete Pouring

7.2 Forecast to be completed next week


7.2.1 Common
 Rebar Receiving from San Cristobal Inspection (Continue)
 Revised ELT-05-CT-PC-0001 Inspection and Test Plan for LNG Tank Installation submittal

7.2.2 Mechanical
 Sector 2. Pedestal Anchor bolts Location and Verification inspection (Continue)
 Sector 3. Pedestal Anchor bolts/boxes Installation inspection
 Sector 4. Pedestal Anchor bolts/boxes installation inspection
7.2 Forecast to be completed next week (Continue)
7.2.2 Electrical
 Sector 3. Pedestal Tank Slab Heating System inspection
 Sector 4. Pedestal Tank Slab Heating System installation inspection
: Partial inspection (conduits installation)
 Medium voltage Electric Works Installation Overlap with Andres I Temporary Power (Continue)
 Medium voltage Electrical Disconnector and Cut out Installation Inspection in Temporary Power
(Continue)
7.2.4 Civil
 Sector 3. Pedestal Rebar Work & Inclinometer inspection
 Sector 3: Pedestal MOPC Inspection for LNG Tank
: Pedestal 2 covers 34m
 Sector 3: Pedestal Concrete Pouring
 Sector 3: Pedestal Post pouring Inspection
 Sector 4. Pedestal Rebar Work & Inclinometer inspection
: Partial inspection (Rebar, formworks)
 Sector 7: Foundation Concrete Pouring
 Sector 7: Foundation Post Pouring Inspection
 Sector 8: Foundation Concrete Pouring
 Sector 8: Foundation Post Pouring Inspection