Professional Documents
Culture Documents
Superstructure Construction: ©ramaiah University of Applied Sciences Faculty of Engineering & Technology
Superstructure Construction: ©ramaiah University of Applied Sciences Faculty of Engineering & Technology
1
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Vacuum De-watered Concrete Floor
2
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Vacuum De-watered Concrete Floor
• VDF floors are known to provide a good concrete floor and is known
to achieve strength earlier than a control concrete
4
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Vacuum De-watered Concrete Floor – contd..
Advantages
• It is the most cost-effective solution as the cost of laying M35
concrete is cheaper than other options
• Durable
• Fairly maintenance-free
5
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Vacuum De-watered Concrete Floor – contd..
Disadvantages
• The inherent porosity of the concrete allows water, oil and grease
to seep through, consequently weakening the concrete
Disadvantages – contd..
• Cleanability becomes a problem due to the presence of
imperfections, surface roughness and porosity
7
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Launching Techniques
8
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Equipments used
• Main girder
• Series of rail-beams
• Sliding rollers
• Hoisting winches
9
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Construction Methodology
10
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Advantages
o Structurally efficient and aesthetic
Disadvantages
o Casting yard setup and transportation
11
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Slipform Techniques
12
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Vertical Slipform:
• The concrete form and
working platform are raised
by means of hydraulic jacks
13
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Horizontal Slipform:
• Concrete is laid down,
vibrated, worked, and settled
in place while the form itself
slowly moves ahead
14
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Advantages
• Accuracy, strength and speed
• Continual casting, creating a monolithic structure
• No joints (unless a halt occurs)
15
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Disadvantages
• Good coordination and site organization required
• Large quantities of equipment (e.g. generators, lighting systems,
and hoists) needed
• Operation cannot easily be halted so that work must continue 24
hours a day through all weather
• Skilled labor force
• High initial expense
• Need 24-hour service facilities (e.g. canteen, material supply,
maintenance crews)
16
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Suspended Formwork
17
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
18
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Large Span Structures
• Shell structures
• Folded plate
• Steel space frame
• Coffered slab
• North light roof
• Patent glazing
19
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont...
20
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Shell Structures
• Is a curved surface structure
• Transmits load without bending or twisting
• Thickness is small compared to its other dimension
Application: Roof structures
21
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
22
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Dome
•Hemispherical in shape
•Constructed of stone , concrete & brick
•Have certain height & diameter ratio
23
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Application: Roof structures
26
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Folded Plate Structures
27
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Steel Space Frame Structures
28
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Steel Space Frame Structures
29
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Different Types Of Space Frame
Structures
31
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
North light structure
32
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
North light structure
33
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Patent Glazing
34
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Patent Glazing
35
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Post Tensioning of Slab
36
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Post Tensioning of Slab
37
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
• Prestressing tendons
• Grouting
38
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Advantages
• Fire resistance
• Cost
• Speed
• Reduced material use
• Sound control
Post Tensioning of Slab
• Robustness
Post Tensioning of Beam
39
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Support structures for heavy equipment and machinery in heavy
industries
• Building, bridges & metro projects-Pile caps
• Turbine, power plant & wind farm- Raft foundation over piles
40
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Support structures for heavy equipment and machinery
in heavy industries
41
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Erecting Light Weight Components On Tall Structures
42
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Erecting Light Weight Components On Tall
Structures
• Besides high raise buildings the usage of steel element is also
popular with construction of hospital and commercial complexes
• Light weight blocks are used for patricians to reduce the dead load
building
44
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Construction of Special Structures
45
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Erection of lattice towers
46
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Erection of lattice towers – contd..
47
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Erection of lattice towers – contd..
Tower Erection
• The towers shall be erected on the foundations not less than 14
days after concreting or till such time that the concrete has
acquired sufficient strength.
48
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Erection of lattice towers – contd..
Tower Erection
49
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tower Erection
50
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tower Erection – contd..
b) Section method
c) Ground assembly method
51
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tower Erection – contd..
Advantages
52
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Built Up Method
• This method consists of erecting the towers member by member
• The tower members are first set out and kept on the ground serially
according to erection sequence to avoid time loss due to searching
for them as and when required
• The four main corner leg members of the first section of the tower
are first erected and kept in position by fixing temporary rope guys.
53
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Built Up Method – contd..
• The cross bracings of the first section, which may be assembled on
the ground, are raised one by one as a unit and bolted to the
already erected corner leg angles
• For assembling the second section of the tower, the derrick / gin
pole is placed on the top of one corner leg. First, the leg members
of the second section are hoisted and assembled
54
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Built Up Method – contd..
55
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Built Up Method – contd..
56
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Helicopter Method
• The tower is erected in sections
• Bottom section is first lifted on to the stub and then the upper
section is lifted and bolted to first section and the process is
repeated till the tower is erected
57
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
58
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
General Steps To Be Followed For Tower Erection
• No tower shall be erected on foundation within 10 days after
concreting
• Reason can be
– Defective fabrication
– Defective foundation
– Defective erection method
60
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
General Steps To Be Followed For Tower Erection –
contd..
• Transport complete tower or complete section
61
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tower Erection
62
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Safety of Tower Erection
• While loading and unloading the tower parts, care should be taken
for stacking systematically
• All lifting tools and tackles should be load tested as per standard
63
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Safety of Tower Erection – contd..
• Ensure the derrick used before tower erection has been checked for
adequate strength / size
• After 5 operations check the condition of the rope. If worn out then
replace
64
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Safety of Tower Erection – contd..
65
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Rigging
66
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cooling tower
67
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cooling tower – contd..
68
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
PRESTRESSING
69
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Prestressing
70
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Prestressing – Classification and Types
• Pre-tensioning
– Tendons are tensioned before the concrete is placed, tendons
are temporarily anchored and tensioned and the prestress is
transferred to the concrete after it is hardened
• Post-tensioning
– Tendon is tensioned after concrete has hardened
– Tendons are placed in sheathing at suitable places in the
member before casting and later after hardening of concrete
71
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tensioning Devices
• Mechanical Devices
– The mechanical devices generally used include weights with or
without lever transmission, geared transmission in conjunction
with pulley blocks, screw jacks with or without gear devices and
wire-winding machines
72
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tensioning Devices – contd..
• Hydraulic Devices
– These are simplest means for producing large prestressing force,
extensively used as tensioning devices
• Electrical devices
– The wires are electrically heated and anchored before placing
concrete in the mould
– This method is often referred to as thermo-prestressing and
used for tensioning of steel wires and deformed bars
73
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tensioning Devices – contd..
• Chemical Devices
– Expanding cements are used and the degree of expansion is
controlled by varying the curing condition
74
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Prestressing System
• Pre-tensioning System
– Tendons are first tensioned between rigid anchor-blocks cast on
the ground or in a column or unit –mould types pre-tensioning
bed, prior to the casting of concrete in the mould
– With the forms in place, the concrete is cast around the stressed
tendon
75
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Prestressing System – contd..
76
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Prestressing System
• Post-tensioned System
– The concrete unit are first cast by incorporating ducts or grooves
to house the tendons
– When the concrete attains sufficient strength, the high-tensile
wires are tensioned by means of jack bearing on the end of the
face of the member and anchored by wedge or nuts
– The forces are transmitted to the concrete by means of end
anchorage and, when the cable is curved, through the radial
pressure between the cable and the duct
– The space between the tendons and the duct is generally
grouted after the tensioning operation
77
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Summary
78
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Summary – contd..
79
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Summary – contd..
• Pre-stressing
• Method of applying pre-compression to control the stresses
resulting due to external loads below the neutral axis of the beam
tension developed due to external load which is more than the
permissible limits of the plain concrete
81
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Summary – contd..
• Pre-tensioning
– Tendons are tensioned before the concrete is placed, tendons
are temporarily anchored and tensioned and the prestress is
transferred to the concrete after it is hardened
• Post-tensioning
– Tendon is tensioned after concrete has hardened
– Tendons are placed in sheathing at suitable places in the
member before casting and later after hardening of concrete
82
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences