Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 82

SUPERSTRUCTURE CONSTRUCTION

1
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Vacuum De-watered Concrete Floor

2
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Vacuum De-watered Concrete Floor

• Invariable known as VDF or Tremix floor continues to be the most


preferred and cost available floors for various industries for many
years

• Concrete of the required grade such as M20, M25 etc (basically


means having a compressive strength of 200Kg/cm2, 250Kg/cm2
etc) are poured over the PCC and reinforcement bars as per design

• Excess water is removed in a controlled fashion by applying vacuum

• The concrete is then power-trowelled to obtain a smooth and


dense concrete
3
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Vacuum De-watered Concrete Floor – contd..

• VDF floors are known to provide a good concrete floor and is known
to achieve strength earlier than a control concrete

• However, contrary to the popular belief, for a specified design mix,


the compressive strength cannot be more than the targeted
strength

• Due to controlled water-removal as well as power-trowelling, the


surface is quite dense and levelled and hence is expected to
provide a better abrasion resistance than a non-VDF concrete floor

4
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Vacuum De-watered Concrete Floor – contd..

Advantages
• It is the most cost-effective solution as the cost of laying M35
concrete is cheaper than other options

• It can be laid by any quality flooring contractors

• Durable

• Fairly maintenance-free

5
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Vacuum De-watered Concrete Floor – contd..

Disadvantages
• The inherent porosity of the concrete allows water, oil and grease
to seep through, consequently weakening the concrete

• Joints are a necessity for concrete floors (to accommodate


shrinkage, thermal movements etc) which can lead to joint-
breakage as well as seepage of the above contaminants

• Concrete floors generate dust due to abrasive movement of


vehicles commonly found in industrial plants which can cause
tangible and intangible damage to plant and machinery, sub-
assemblies etc.
6
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Vacuum De-watered Concrete Floor – contd..

Disadvantages – contd..
• Cleanability becomes a problem due to the presence of
imperfections, surface roughness and porosity

• The best-laid floor (Tremix) can have undulations of above 5mm


(not normally visible to naked eye). While it is typically accepted in
various engineering industries, it must be kept in mind that heavy
movement of vehicles can wear out the surface faster

7
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Launching Techniques

• Full span launching technique


• Segmental launching technique

8
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Equipments used

• Main girder

• Series of rail-beams
• Sliding rollers
• Hoisting winches

9
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Construction Methodology

• Segments are cast in the casting


yard
• launching girder is used for
erection of precast segments
• The launching girder provided
with hangers to hold the
segments during erection
• Each segments is joined to the
other using epoxy glue
• Post-tensioned to form the final
span

10
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Advantages
o Structurally efficient and aesthetic

o It is economical for large project


o Rapid & safe
o Cast during substructure works – overlap of activities

Disadvantages
o Casting yard setup and transportation

11
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Slipform Techniques

Its continuous pouring of concrete into walls of a structure and


only stops when the full required height or length of the structure
has been reached.

The formwork is erected only once and remains intact until


the entire structure is completed.

12
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..

Vertical Slipform:
• The concrete form and
working platform are raised
by means of hydraulic jacks

Ex: Silos, chimneys, tall


buildings and bridges

13
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Horizontal Slipform:
• Concrete is laid down,
vibrated, worked, and settled
in place while the form itself
slowly moves ahead

• Ex: Pavement and traffic


separation wall, canals, and
tunneling

14
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Advantages
• Accuracy, strength and speed
• Continual casting, creating a monolithic structure
• No joints (unless a halt occurs)

• Lends itself to almost any shape in plan


• Labor saving in the long run

• Saves form-work material


• Economical for structures above a certain size

15
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Disadvantages
• Good coordination and site organization required
• Large quantities of equipment (e.g. generators, lighting systems,
and hoists) needed
• Operation cannot easily be halted so that work must continue 24
hours a day through all weather
• Skilled labor force
• High initial expense
• Need 24-hour service facilities (e.g. canteen, material supply,
maintenance crews)

16
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Suspended Formwork

17
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
18
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Large Span Structures

• Shell structures
• Folded plate
• Steel space frame
• Coffered slab
• North light roof
• Patent glazing

19
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont...

• Steel space frame


• Coffered slab
• North light roof
• Patent glazing

20
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Shell Structures
• Is a curved surface structure
• Transmits load without bending or twisting
• Thickness is small compared to its other dimension
Application: Roof structures

21
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..

Depending upon the geometry of middle surface the shells can be


classified as :
1.Domes
2.Shell Barrel Arch / Vault
3.Translation shells
4.Ruled Surfaces shell

22
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Dome
•Hemispherical in shape
•Constructed of stone , concrete & brick
•Have certain height & diameter ratio

Application: Roof structures

Ribbed shell domes

23
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Application: Roof structures

Smooth shell domes, Abudhabi 24


Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Different Types Of Dome

Spherical dome Triangular dome

Cylindrical dome Rectangular dome 25


Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Folded Plate Structures
• Flat plates are connected to one another along their edges
• Used in long span especially for roofs
• Give mutual support to each other
• Plates may be continuous over their supports longitudinally
• These plates carry the load from slab longitudinally to the support
Application: Roof structures

26
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Folded Plate Structures

27
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Steel Space Frame Structures

• Are used in the form of grids of rectangular, diagonal , triangular or


hexagon pattern, arches domes &other large column free areas
• Deflection of the truss is transmitted to the adjoining trusses & the
entire roof works act more or less monolithically
• Are stiffer than system of parallel trusses
• Shallower in depth

28
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Steel Space Frame Structures

29
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Different Types Of Space Frame
Structures

Braced barrel vault structure Hipped end structure

Geodesic dome structure 30


Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Coffered slab Structures

• Coffered/Ribbed/waffle slabs provide a


lighter and stiffer slab than an equivalent flat
slab, reducing the extend of foundations

• They provide a very good form where slab


vibration is an issue, such as laboratories and
hospitals

31
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
North light structure

Is a structure used to take natural day light from north side


•Consists of a series of trusses fixed to girders
•The short vertical side of the truss is glazed so that when the roof is
used in the Northern Hemisphere, the glazed portion faces North for
the best light
•Saves energy
•It can be used for spans from 20-30m
Application: Used for industrial buildings, drawing rooms ,
laboratories, etc

32
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
North light structure

33
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Patent Glazing

• Non-load bearing framing system


• Used in overhead glazing system
• Economic alternative to four edge support curtain walling
• Slim profiles allow the full use of natural light in the building
Application: Railway stations, shopping malls, atria, schools, canopies,
roofs & north light glazing

34
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Patent Glazing

35
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Post Tensioning of Slab

Post-tensioned slabs use high


strength tensioned steel cables
to compress the slabs, keeping
the majority of the concrete in
compression.
Ex: Flat slabs, ribbed slabs etc

36
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Post Tensioning of Slab

37
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..

Step by step procedure:


• Placing of tendons before pouring concrete
• Concreting of slab

• Prestressing tendons
• Grouting

38
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..

Advantages
• Fire resistance

• Cost
• Speed
• Reduced material use

• Sound control
Post Tensioning of Slab
• Robustness
Post Tensioning of Beam

39
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Support structures for heavy equipment and machinery in heavy
industries
• Building, bridges & metro projects-Pile caps

• Turbine, power plant & wind farm- Raft foundation over piles

40
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cont..
Support structures for heavy equipment and machinery
in heavy industries

41
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Erecting Light Weight Components On Tall Structures

42
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Erecting Light Weight Components On Tall
Structures
• Besides high raise buildings the usage of steel element is also
popular with construction of hospital and commercial complexes

• Instead of concrete beams and columns more than 6100 tons of


steel have been used to build the main frames

• Light weight blocks are used for patricians to reduce the dead load
building

• The usage of permanent concrete form works and structural steel


elements will be the main constituter for erecting light weight
components on tall structures results rapid speed of constructions
43
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Erecting Light Weight Components On Tall
Structures – contd..
• Hence the erection of steel beams and columns as well as the
installation of concrete form work consumes only less time

• Self drilling tapping screws are the most prevalent fasteners

• Steel to steel connections can be carried out to connect struts or


joist and track together

• Entire can be erected manually with out the use of heavy


equipment

44
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Construction of Special Structures

45
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Erection of lattice towers

• A lattice tower or truss tower is a freestanding frame work tower

• They can be used as electricity transmission towers especially for


voltages above 100 kilovolts, as a radio tower(a self-radiating tower
or as a carrier for aerials) or as an observation tower

46
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Erection of lattice towers – contd..

47
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Erection of lattice towers – contd..

Tower Erection
• The towers shall be erected on the foundations not less than 14
days after concreting or till such time that the concrete has
acquired sufficient strength.

48
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Erection of lattice towers – contd..

Tower Erection

49
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tower Erection

• The towers are erected as per the


erection drawings furnished by the
manufacturers to facilitate erection

• No member shall be subjected to


any undue over stress during
erection

50
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tower Erection – contd..

There are three main methods of erection of steel transmission


towers

a)Built up method or Piecemeal method

b) Section method
c) Ground assembly method

51
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tower Erection – contd..
Advantages

a)Tower materials can be supplied to site in knocked down condition,


i.e., in pieces which facilitates easier and cheaper transportation

b) It does not require any heavy machinery such as cranes, etc.

c) Tower erection activity can be done in any kind of terrain and


throughout most of the year

d) Availability of workmen at cheaper rates

52
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Built Up Method
• This method consists of erecting the towers member by member

• The tower members are first set out and kept on the ground serially
according to erection sequence to avoid time loss due to searching
for them as and when required

• The erection progresses from the bottom upwards

• The four main corner leg members of the first section of the tower
are first erected and kept in position by fixing temporary rope guys.

53
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Built Up Method – contd..
• The cross bracings of the first section, which may be assembled on
the ground, are raised one by one as a unit and bolted to the
already erected corner leg angles

• For smaller base towers / vertical configuration towers, one


derrick / gin pole is used

• For assembling the second section of the tower, the derrick / gin
pole is placed on the top of one corner leg. First, the leg members
of the second section are hoisted and assembled

54
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Built Up Method – contd..

• The derrick is then shifted to the


corner leg member on the top of the
second section to raise the parts of
third section of the tower in position
for assembly

55
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Built Up Method – contd..

• For heavier towers, a small


boom is rigged on one of the
tower legs for hoisting purposes

• The members / sections can be


hoisted either manually or by
pulling with a tractor or by
winch machines operated from
the ground

56
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Helicopter Method
• The tower is erected in sections

• Bottom section is first lifted on to the stub and then the upper
section is lifted and bolted to first section and the process is
repeated till the tower is erected

• Some times complete assembled tower is raised with the help of


helicopter

• Adopted with the approach is impossible

57
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
58
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
General Steps To Be Followed For Tower Erection
• No tower shall be erected on foundation within 10 days after
concreting

• Check the correctness of diagonal and level of the stub of the


foundation

• Towers are to be erected as per erection drawing

• Assembly of tower parts shall be made as per the assigned number


in the erection drawing

• Special care shall be taken in selection of marking for transverse


and longitudinal face of the square base tower
59
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
General Steps To Be Followed For Tower Erection –
contd..
• Any buckling, damage to steel member, damage to galvanizing shall
be avoided

• No member shall be subjected to undue stress

• Reason can be
– Defective fabrication
– Defective foundation
– Defective erection method

• Collect material from store tallying with Bill of Materials (BOM)

60
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
General Steps To Be Followed For Tower Erection –
contd..
• Transport complete tower or complete section

• The tower member at location shall be kept on ground serially


according to the need for following up erection sequence

61
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tower Erection

62
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Safety of Tower Erection

• While loading and unloading the tower parts, care should be taken
for stacking systematically

• Handle the tower parts carefully – suitable gloves

• Establish clear signal / communication between the persons


working on the top and the workmen supplying tower parts –
special care shall be taken for RC tower

• All lifting tools and tackles should be load tested as per standard

63
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Safety of Tower Erection – contd..

• Ensure the derrick used before tower erection has been checked for
adequate strength / size

• Keep watch on all workmen used during erection – slippage /


failure

• Polypropylene rope from 20mm to 25mm size should be used for


guying and lifting

• After 5 operations check the condition of the rope. If worn out then
replace

64
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Safety of Tower Erection – contd..

• All tower members to be fitted with appropriate size of nuts and


bolts of the section erected before the erection is taken up for the
next section

• Avoid any tower erection during rain / cloudy day

• Stop all tower erection in case of heavy wind or approaching storm

• PPE like helmet, safety belt of proper quality is used

65
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Rigging

• The system of equipment used to secure cargo for carriage, e.g.


straps, cables, clevises, shackles, spreader bars, hooks, etc.

66
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cooling tower

• A cooling tower is a heat rejection device which extracts waste heat


to the atmosphere through the cooling of a water stream to a lower
temperature

67
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Cooling tower – contd..

68
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
PRESTRESSING

69
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Prestressing

• Method of applying pre-compression to control the stresses


resulting due to external loads below the neutral axis of the beam
tension developed due to external load which is more than the
permissible limits of the plain concrete

• The precompression applied (may be axial or eccentric) will induce


the compressive stress below the neutral axis or as a whole of the
beam c/s

• Resulting either no tension or compression

70
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Prestressing – Classification and Types

• Pre-tensioning
– Tendons are tensioned before the concrete is placed, tendons
are temporarily anchored and tensioned and the prestress is
transferred to the concrete after it is hardened

• Post-tensioning
– Tendon is tensioned after concrete has hardened
– Tendons are placed in sheathing at suitable places in the
member before casting and later after hardening of concrete

71
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tensioning Devices

• Mechanical Devices
– The mechanical devices generally used include weights with or
without lever transmission, geared transmission in conjunction
with pulley blocks, screw jacks with or without gear devices and
wire-winding machines

– These devices are employed mainly for prestressing structural


concrete components produced on a mass scale in factory

72
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tensioning Devices – contd..

• Hydraulic Devices
– These are simplest means for producing large prestressing force,
extensively used as tensioning devices

• Electrical devices
– The wires are electrically heated and anchored before placing
concrete in the mould
– This method is often referred to as thermo-prestressing and
used for tensioning of steel wires and deformed bars

73
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Tensioning Devices – contd..

• Chemical Devices
– Expanding cements are used and the degree of expansion is
controlled by varying the curing condition

– Since the expansive action of cement while setting is restrained,


it induces tensile forces in tendons and compressive stresses in
concrete

74
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Prestressing System

• Pre-tensioning System
– Tendons are first tensioned between rigid anchor-blocks cast on
the ground or in a column or unit –mould types pre-tensioning
bed, prior to the casting of concrete in the mould

– The tendons comprising individual wires or strands are stretched


with constant eccentricity or a variable eccentricity with tendon
anchorage at one end and jacks at the other

– With the forms in place, the concrete is cast around the stressed
tendon
75
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Prestressing System – contd..

• Pre-tensioning System – contd..

76
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Prestressing System

• Post-tensioned System
– The concrete unit are first cast by incorporating ducts or grooves
to house the tendons
– When the concrete attains sufficient strength, the high-tensile
wires are tensioned by means of jack bearing on the end of the
face of the member and anchored by wedge or nuts
– The forces are transmitted to the concrete by means of end
anchorage and, when the cable is curved, through the radial
pressure between the cable and the duct
– The space between the tendons and the duct is generally
grouted after the tensioning operation

77
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Summary

• Vertical slipform - The concrete form and working


platform are raised by means of hydraulic jacks

• Horizontal slipform - Concrete is laid down, vibrated,


worked, and settled in place while the form itself slowly
moves ahead

• Folded plate structures - Flat plates are connected to one


another along their edges

78
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Summary – contd..

• Folded plate structures - Used in long span especially for


roofs Give mutual support to each other

• Plates may be continuous over their supports


longitudinally

• There are three main methods of erection of steel


transmission towers - Built up method or Piecemeal
method, Section method and Ground assembly method

79
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Summary – contd..

• All tower members to be fitted with appropriate size of


nuts and bolts of the section erected before the erection
is taken up for the next section

• Avoid any tower erection during rain / cloudy day

• Stop all tower erection in case of heavy wind or


approaching storm

• PPE like helmet, safety belt of proper quality is used


80
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Summary – contd..

• Pre-stressing
• Method of applying pre-compression to control the stresses
resulting due to external loads below the neutral axis of the beam
tension developed due to external load which is more than the
permissible limits of the plain concrete

• The pre-compression applied (may be axial or eccentric) will induce


the compressive stress below the neutral axis or as a whole of the
beam c/s

• Resulting either no tension or compression

81
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences
Summary – contd..

• Pre-tensioning
– Tendons are tensioned before the concrete is placed, tendons
are temporarily anchored and tensioned and the prestress is
transferred to the concrete after it is hardened

• Post-tensioning
– Tendon is tensioned after concrete has hardened
– Tendons are placed in sheathing at suitable places in the
member before casting and later after hardening of concrete

82
Faculty of Engineering & Technology ©Ramaiah University of Applied Sciences

You might also like