Proposal of Construction Plan For La Verna Drainage Project: Nittoc Construction Co., Ltd. 07/13/2020
Proposal of Construction Plan For La Verna Drainage Project: Nittoc Construction Co., Ltd. 07/13/2020
for
La Verna Drainage Project
Downstream
0+915
Upstream
0+600
3
Profile for Original Design
HDPE Pipe
Φ3.0m
No. 0+600
EL=9.559m 0.87%
315.00m No. 0+915
EL=6.804m
4
Problems of Original Design
1. It is quite difficult for the construction works to install the new drainage pipe
at the same location of the original drainage pipe.
2. It is required to divert the water of the original drainage pipe by another
route during the construction works.
3. It is required to consider the construction method to install the new drainage
pipe by removing the existing drainage pipe.
4. The HDPE Pipe shall be installed by the crane after excavating the ground.
However, it is impossible to excavate the ground since the existing drainage
pipe was installed under the residential area.
Solution
a. Accordingly, the New Drainage Pipe shall be installed at the Different Bypass
Route.
b. The New Drainage Pipe shall be installed by the Tunneling Construction
Method.
5
Outline of Our Proposal
Temporary
Vertical Shaft Downstream
0+915
Connection Box
Upstream
0+600 Bypass
t
en
c em
la
ep
R
Existing Underdrain
Existing creek
Existing Underdrain
Width ?
Tunneling
Opened excavation Proposal 1 - 2
Connection
Box
Opened Excavation
Connection Box
HDPE Pipe
Plan at Upstream 7
Existing Underdrain
Existing Creek
Existing Underdrain
HDPE
Pipe
Tunneling
Temporary
Proposal 1-2
Opened excavation Vertical
Shaft
Bottom Elevation ?
New pipe
Temporary
Depth of
Vertical
Overburden?
Shaft Bottom of Pipe
Existing
Proposal 1 - 2 Creek
φ3000
HDPE Pipe
Comparison Table for Construction Method 8
Item Proposal 1 Proposal 2
Method Construction of Tunnel by Liner Plate. Installation Cutting Edge Type Pipe Jacking Method
of HDPE by Pulling-In. Filling Air-Mortar.
Outline Tunnel shall be constructed by use of Liner Plate Tunnel Face shall be excavated by Man-Power.
as its Support. After Pulling-In HDPE Pipe into the The drainage shall be constructed by Hume Pipe
Tunnel, Air-Mortar shall be filled the space pushing by the Jack from Temporary Vertical Shaft.
between Liner Plate and HDPE Pipe.
Remarks : The construction period and cost estimate are approximately assumed since it is quite difficult to prepare the
Concrete Cost Estimate due to so many uncertain factors at this moment.
Proposal 1 - Cross Section 9
Installation of Railway
Grouting - Type B (Air
Mortar)
Installation of HDPE Pipe
s
li
al
W
r y se.
o ra llap
p o
e m eC
T th
of id
n
t io a vo
r u c to
t
s red
n i
Co equ
r
Jacking Pressure
Approximate 3,000 ton
4. Set of Cutting Edge and Hume Pipe 5. Cutting of Sheet-Pile 6. Carrying of Surplus Soil
1. It is required for the area to be installed the new drainage pipe to allow the
permanent land use. ⇒ It shall be required for the land Acquisition.
2. It is necessary to secure the temporary working yard at the upstream of the
construction site for the installation of HDPE of 3.0m diameter.
( According to the given photo of the site, it seems that the existing creek
width is less than 3.0m.)
3. It is required for the ground works during the construction to be provided
a proper space for the works temporarily.
4. It shall be required to conduct the Fore-Piling Support for the Tunnel
Works to avoid the Cave-In during the construction, if the Overburden
above the Tunnel is less, after considering the Soil Boring Test Result it may
be necessary for the whole stretch of the Tunnel for securing the Safety.
5. It is definitely required to carry out the geological survey works such as in-
site boring test along the proposed tunnel route since the past obtained
geological data is at the different place.
Plan of Existing Underdrainage 16
Are there any houses on the line of existing underdrainage?
Alternative Construction Method 17
Depending on the soil condition of the tunnel route, it may be applicable for the Mud
Density Slurry Balance Type Pipe Jacking Method. This construction method is quite safe
for the adjacent ground and structures since the cutter face is a closed type and no
intrusion of the excavated soils into the Hume Pipe is expected. The Project is required
definitely to secure the safety by minimizing the displacement of the ground as the
installation of the Hume Pipe is planned under the residential area
If the above method can be applicable for this Project, it is most recommendable from the
viewpoint of Safety and Cost Effectiveness since the Construction Period and Cost could be
almost equal to the previously presented the Two construction methods