EBR (Toyo Setal) KoM 27 June 2013 FPSO P-74 Rev1
EBR (Toyo Setal) KoM 27 June 2013 FPSO P-74 Rev1
J. P. Pontes, R. Souza
27.06.2013
Outline
Classification principles
- Scope & Interfaces
- Rules & Regulations
- Notations
Project organization
Plan (Design) Approval
Yard work (focus areas and how we do the work)
- Fabrication
- Mechanical Completion, Testing and Commissioning
Certification of Materials and Components
General remarks
Immediate tasks related to the project
SHE
MOiO
CMC
Industries
(Vendors/Suppliers)
requirements
Requirements
Work
WorkScope
Scope
Client Drawing No. Rev Title Corr. J. No. D DNV Reg. date Approval date Lay St.atus Resp. unit Resp.
No. No. days
October/2004
FSTP Brasil I-DE-3010.63-1320-140-TKP-901 0 GENERAL NOTES - DECK BOX 643 H 566 2004-10-14 2004-10-27 9 AP TNCNO723 GJE
S/A
FSTP Brasil I-DE-3010.63-1320-140-TKP-903 0 STANDARD WELDING AND TAPER 643 H 568 2004-10-14 2004-10-27 9 AP TNCNO723 GJE
S/A DETAILS - DECK BOX STRUCTURE
FSTP Brasil I-DE-3010.63-1320-140-TKP-904 0 TYPICAL WELDING - DECK BOX 643 H 569 2004-10-14 2004-10-27 9 AP TNCNO723 GJE
S/A STRUCTURE
DNV Exchange:
-E-mail approval letter to Builder Engineering
- DNV-OSS-102 Rules for Classification of Floating Production, Storage and Loading Units
- DNV-OS-A101 Safety Principles and Arrangements
- DNV-OS-B101 Metallic Materials
- DNV-OS-C101 Design of Offshore Steel Structures. General (LRFD method)
- DNV-OS-C201 Structural Design of Offshore Units (WSD method)
- DNV-OS-C301 Stability and Watertight Integrity
- DNV-OS-C401 Fabrication and Testing of Offshore Structures
- DNV-OS-D101 Marine and Machinery Systems and Equipment
- DNV-OS-D201 Electrical Installations
- DNV-OS-D202 Instrumentation and Telecommunication Systems
- DNV-OS-D301 Fire Protection
- DNV-OS-E201 Oil and Gas Processing Systems
- DNV-OS-E301 Position Mooring
FPSO P-74 KoM
27.06.2013
© Det Norske Veritas AS. All rights reserved. 15
Yard Work - Risk based verification (1)
Contemplate Annual Yard & Project specific reviews
Quality evaluation of key yard production activities
The surveys conducted during a new
building/conversion project categorized as follows:
- Survey Cat1 - Statutory & Essential / Primary Systems for Safety
- Survey Cat2 - Main Systems / Functionally Important/ Special (For Main
& Additional Class Notations). Based on yard capability/experience.
- Survey Cat3 – Minimum attendance required by surveyor (i.e. Secondary
structures, some Cat 2 drill systems, commissioning of some systems
where integration testing is also carried out)
Objective is to contribute positively so that the project and all parties can succeed
While mindful of our obligation to be an independent third party
Main focus areas are related
- Main structures
- Life Saving (Equipment and Communication)
- Main & Emergency Power
- Stability (Structural Integrity and Water & Weather tight)
- Fire & Explosion (Pressurized Equipment/ Systems, Hydrocarbon Systems and ESD)
- Environmental.
FPSO P-74 KoM
27.06.2013
© Det Norske Veritas AS. All rights reserved. 17
Yard Work - Modus Operandi: Main tasks (3)
Evaluation of yard´s QC system
Welders and WPS verification and certification
NDT (procedures & operators verification)
Verify traceability of materials
Verify Certificates of equipment's and materials received at the construction site
Witnessing of some Production Tests
Carry out visual inspections of welding on critical joints.
Carry out Scheduled & Unscheduled Surveys
Provide list on findings through NPS (Nauticus Construction)
Approval of minors design alterations due to fabrication needs
Approval of “As-built” drawings
Attend Quality Meetings
First contact for answer queries from Yard & PNBV
General Information
Periodic Tripartite Quality Meetings
DNV to deliver List of Findings – “DNV Pendings”
Periodic Tripartite Pending Meetings
Yard to submit all required Quality Procedures for PMF’s verification
Yard to inform list and SoW of all subcontractors for DNV appraisal. Sub-contractors shall be
approved by DNV if not under the same QA/QC System of the Contractor (main site)
Milestone dates of project to be previously informed to DNV
- Attend essential meetings for Follow-up of DNV Comments & CMC Coordination
- This regular project meetings as agreed must be in a reasonable intervals; not every production/review
meeting
- DNV has launched a corporate program to reduce CO2 emissions through a policy of incentives for
videoconferencing, where possible, in place of physical meetings where flights are needed.
- Project Report that shows the project progress (Plan Approval; Site Survey & CMC to be
issued in a monthly basis)
FPSO P-74 KoM
27.06.2013
© Det Norske Veritas AS. All rights reserved. 22
Project Report
DNV will deliver monthly a managerial project report of easy understanding to EBR & PNBV describing the
DNV project progress
- Plan Approval Status
- DNV Comment Status (Plan Approval & Site Survey)
- Charts, photos & pictures showing the progress of Plan Approval and the survey development.
- Areas of Concern
The contractor shall provide all adequate safety measures to ensure a working
environment that is safe and in accordance with all relevant legislation whenever DNV
undertakes work at the contractor´s or sub-contractor´s sites.
It is the surveyor’s right and duty to evaluate the safety preparations before engaging in
any survey.
He may refuse the working condition proposed to him when considered by him to be
unsafe.
www.dnv.com