Professional Documents
Culture Documents
CE155P-2 - Measurement & Quantification (Part 1)
CE155P-2 - Measurement & Quantification (Part 1)
SURVEYING
CE155-2P
Engr. Timothy Daniel Felicia
MEASURING
QUANTITIES
AND ITEM OF
Q
S WORKS IN
BUILDING
MEASURING QUANTITIES AND ITEM OF WORKS IN
BUILDINGS
FORMWORK
3
TYPES OF
Q
S ESTIMATES
DETAILED ESTIMATES
S QUANTITIES
QUANTITY TAKE-OFF
S EARTHWORKS
SITE CLEARANCE/PREPARATION
RULE OF MEASUREMENT:
•Site preparation is measured in terms of area, m2.
SITE
CLEARANCE/
PREPARATIO
N
SITE
CLEARANCE/
PREPARATIO
N
SITE
CLEARANCE/
PREPARATIO
N
EXCAVATION
RULE OF MEASUREMENT:
•All excavation is measured net with no allowance for
increasing in bulk after excavation or for the extra space
required for working space or to accommodate earthwork
support.
EXCAVATION
EXCAVATION
EXCAVATION
EXCAVATION
RULE OF MEASUREMENT:
•Disposal is based on all excavated material off site
and measured in terms of volume, m3.
DISPOSAL
DISPOSAL
DISPOSAL
DISPOSAL
FILLING
RULE OF MEASUREMENT:
•Filling is obtained from excavated material which includes
topsoil and any other material arising from the excavations that
have been specified to remain on site and measured in terms of
volume, m3.
•Consider additional 25% as allowance for compaction of the
loose volume of soil.
FILLING
FILLING
SAMPLE
Q
S PROBLEM
SAMPLE PROBLEM NO. 1
Compute for the total volume of
excavation, disposal and backfill
based on the following structural
elements:
1. Footings:
F5 at GL B/1 and F6 at GL D/1
2. Footing Tie Beam:
FTB2 at GL B-D/1
3. Columns
C1C at GL B/1 and C1A at GL D/1
Annual Review 34
SAMPLE PROBLEM NO. 1
Annual Review 35
SAMPLE PROBLEM NO. 1
Annual Review 36
IN SITU
CONCRETE
Q
S WORKS
IN SITU CONCRETE
RULE OF MEASUREMENT:
Concrete volume is measured net.
Deductions are not made for the following:
Reinforcement
Steel Sections
Voids < 0.05m3 in volume (except voids in
troughed and coffered slabs)
MATERIALS IN CONCRETE
Annual Review 40
PROPORTION CLASS AA (1 : 1.5 : 3) Concrete Mix:
TCV x 10.46 = No. of bags Cement
S OF
TCV x 0.42 = No. of cubic meters Sand
TCV x 0.84 = No. of cubic meters Gravel
RULE OF MEASUREMENT:
It is measured to the faces of all cast in place
concrete which requires to be supported while the
concrete sets.
No deductions shall be made for voids < 5.00 m2
WOOD FORMWORK:
PHENOLIC BOARDS
Annual Review
STEEL
FORMWOR
K
SAMPLE
Q
PROBLEM
S
SAMPLE PROBLEM NO. 2
Compute for the total volume of concrete and total
area of formworks on the following structural
elements:
1. Footing:
F8 at GL B/4
2. Footing Tie Beam:
FTB1 at GL B-D/4
3. Column
C1B at GL B/4
4. Girders
G1 at GL D-F/1 and G6 at GL D-F/2
5. Suspended Slab
S-1 at GL D-F/1-2
6. Stair
Annual Review 47
SAMPLE PROBLEM NO. 2
Annual Review 48
SAMPLE PROBLEM NO. 2
Annual Review 49
SAMPLE PROBLEM NO. 2
Annual Review 50
SAMPLE PROBLEM NO. 2
Annual Review 51
SAMPLE PROBLEM NO. 2
Annual Review 52
SAMPLE PROBLEM NO. 2
Annual Review 53
SAMPLE PROBLEM NO. 2
Annual Review 54
SAMPLE PROBLEM NO. 2
Annual Review 55
Thank you