Professional Documents
Culture Documents
Bheri Babai Multipurpose Project
Bheri Babai Multipurpose Project
Bheri Babai Multipurpose Project
Benefit/year(based on 2011)
Kohalpur
Harre Danda
Toli Khola
820m
Bheri
river
Babai 220m
river
Tunnel Slope 1:335
IBWT Projects - Overall Perspective
Sunkoshi-Marin DMP
820m
220m
Tunnel Length = 12 Km
Discharge=40m3/s Diameter (Finished) = 4.2 m
Tunnel Slope 1:335
Bheri river
TBM
Platform
Employer’s
Camp
弃土场
Segment
Contractor’s Plant
Camp
Dumping
Site
Crushing Quarry
Plant Site
TBM Platform, Employer’s Camp & Contractor’s Camp
TBM
Platform
TBM
Platform
Employer’s
Camp
Employer’s
Contractor’s Camp
Camp
Contractor’s
Camp
Segment
Plant
Google Map
(28o21’30”N,81o43’10”E)
Employer’s Camp
Office
Quarter
Segment Plant
Segment Plant Cement Store
General Store
Curing
Diesel Tank
Seg
Generator Labor Camp1
m
Ts
ent
ank
Sto
rag
e
Yar
Segment Labor Camp2
d
Plant
Cotractor’s
Camp
Tunnel Excavation by DBM vs TBM
DBM TBM
Shotcrete, Shotcrete with wiremesh, Precast Segment erection with pea-gravel &
Rockbolt, Lattice girder, RCC etc grouting for extra excavation, Probe drilling.
Construction Period-Long Construction Period-Short
Tunnel Excavation by TBM costs about double of DBM, but is about 3 times fast in
construction (average 28.65m/working day in BBDMP along with RCC Segment)
Entry Portal - Plan
49m
130m
25m
Tunnel Excavation by DBM & TBM
Starting Point of TBM Tunnel
Surge Tank
Heading
Benching
Tunnel Excavation by DBM Method (150.7m)
Started on Jan 1, 2017 & Completed on June 2, 2017
49m
15m TBM Front Covered Part out of 274m
Transport of TBM
Arrival at Kolkata Aug 5,2017
Vehicles (total 53) arrived at
Nepal Customs on Aug 26, 2017
5900m 6300m
400m
TBM Stucked at Ch 8+588
Harre Danda
Pond Level
Toli Khola (Bheri river)
= 461 m
Tailrace Level 820m
(Babai river)
= 309 m 220m
Tunnel Length = 12 Km
Discharge=40m3/s Diameter (Finished) = 4.2 m
1st time TBM Stuck at Ch. 8+588 on 2018 Oct 15 due to unequal rock at face
along with little water ingress & Strike nearly parallel to tunnel alignment.
Resumed excavation after 8 day later by making bypass tunnel
Bypass Tunnel
Bypass Tunnel
2nd time TBM Stuck at Ch. 8+606 on 2018 Oct 24 by top slab collapse due to
loose cement and water inflow & Resumed on the same day after 3m pre-
grouting with polyurethane chemical injection on top slab. Excavation
continued but deviate alignment towards right side soft rock up to 90cm.
Polyurethane
chemical & grout
foam
40
30
Av./day=23.52m
20
10
51
11
21 61 71 81 91
31 41
0
15-Oct-17
25-Oct-17
4-Nov-17
14-Nov-17
24-Nov-17
4-Dec-17
14-Dec-17
13-Jan-18
23-Jan-18
2-Feb-18
12-Feb-18
22-Feb-18
4-Mar-18
14-Mar-18
24-Mar-18
13-Apr-18
23-Apr-18
13-May-18
2-Jun-18
22-Jun-18
2-Jul-18
12-Jul-18
22-Jul-18
11-Aug-18
21-Aug-18
10-Sep-18
20-Sep-18
30-Sep-18
30-Oct-18
19-Nov-18
29-Nov-18
9-Dec-18
19-Dec-18
29-Dec-18
8-Jan-19
18-Jan-19
28-Jan-19
7-Feb-19
17-Feb-19
27-Feb-19
9-Mar-19
19-Mar-19
29-Mar-19
8-Apr-19
24-Dec-17
3-Jan-18
3-Apr-18
3-May-18
23-May-18
12-Jun-18
1-Aug-18
31-Aug-18
10-Oct-18
20-Oct-18
9-Nov-18
Date
Tun nel Excavation b y TBM (
2000
4000
6000
8000
0
10000
12000
14000
16-Oct-17
1-N ov-17
17-N ov-17
3-D ec-17
19-D ec-17
4-Ja n-18
20-Jan-18
5-Feb-18
21-Feb-18
9-M a r-18
25-M a r-18
10-Apr-18
26-Apr-18
12-M a y-18
28-M a y-18
13-Jun-18
29-Jun-18
15-Jul-18
31-Jul-18
16-Aug -18
1-Sep-18
15 Oct 2017 to 16 Apr 2019
17-Sep-18
3-O ct-18
Date
19-Oct-18
4-N ov-18
20-N ov-18
6-D ec-18
22-D ec-18
7-Ja n-19
23-Jan-19
(Target of Excavation upto 12 Nov 2019)
8-Feb-19
24-Feb-19
12-M a r-19
28-M a r-19
13-Apr-19
16-Jun-19
Daily Cumulative Tunnel Excavation Target vs Progress by TBM
Segment Stacking
(Total 34550)
10000
12000
14000
0
2000
4000
6000
8000
16-Oct-17
1-Nov-17
17-Nov-17
3-Dec-17
19-Dec-17
4-Jan-18
20-Jan-18
5-Feb-18
21-Feb-18
9-Mar-18
25-Mar-18
10-Apr-18
(Upto 16 Apr, 2019)
26-Apr-18
12-May-18
Tunnel Segment Length
28-May-18
13-Jun-18
29-Jun-18
Date
15-Jul-18
31-Jul-18
16-Aug-18
1-Sep-18
17-Sep-18
3-Oct-18
Tunnel Segment Length vs Tunnel Length
19-Oct-18
4-Nov-18
Tunnel Length
20-Nov-18
6-Dec-18
22-Dec-18
7-Jan-19
23-Jan-19
[Tunnel Segment Length=(No. of segment/4) X1.404m]
8-Feb-19
24-Feb-19
12-Mar-19
28-Mar-19
13-Apr-19
Breakthrough Ceremony by Prime Minister in
presence of Ambassadors of USA & China
After Breakthrough (Intake Site Bheri)
2019 Apr 16 (2076 Baisakh 3)
End Tunnel (Intake site, Bheri)
from outside & inside of Tunnel
Factors contributing to early completion of Tunnel
• Implementation by Planning team
• Positive working attitude of Contractor & nature of work
• Better geology condition than anticipated
(not necessary probe drilling, ground engineering works, etc.)
• Smoothly crossed the Bheri Thrust Zone
• Contractor’s ownership of the TBM
• Negligible effect of Strikes (due to labour, local & general)
No payment is made for entry portal in the contract document. Once the segment
is placed inside the tunnel by TBM, the machine cannot get back and the only exit
route is the other end of the tunnel reached after completion. Hence chance of
contractor leaving without completion of tunnel due to any reason is scarce.
Head Works model from upstream
Head Works model from downstream
Powerhouse
Powerhouse
Brief Description on Quality of Works
Co m p . S t re n g th (M P a )
35
0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400
Concrete Sample Id.
Performance based on Average & Multiplication
Concrete Quality If students had got
Cement Quality 100% 95% such marks, their
× × result would have
Aggregate Quality 100% 95% been distinction
× ×
Batching & Mixing 100% 95%
× × But, this principle
Transportation & Pouring 100% 95% does not apply
× × here!
Compaction 100% 95%
× ×
Finishing 100% 95%
× × “It shows clearly that
why quality control is
Curing 100% 95%
important and sensitive
from the level of each
Concrete Structure 100% 70% constituents to the level
=
70
Comp. Strength (MPa)
65
60
55
50
45
40
Average 7day=53.52MPa; Average 28day=67.70MPa
35
30
0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400
Concrete :167,810m3
Cube Crushed:20,178no.
Rebar used : 8,011 MT
NTC Building, Sundhara
Concrete :42,348m3
Cube Crushed:5,580no.
Rebar used :3,524 MT