Extraction and Recovery Crude Oil from Earthen

Pits & Construction of Evaporation Pond Project


of Arabian Gulf Oil Company

May, 2013
1. Introduction
Engineering Solution Provider

LG-TOYO Engineering Co., Ltd. was founded in October, 2010 as a Joint Venture
between LG Group and Toyo Engineering Corporation which is a major engineering
company in Japan. LG-TOYO have a lot of skilled and capable engineers who have
experience with Petrochemical, Chemical, Industrial Plant, etc. and LG-TOYO will
conduct Project utilizing GTS (Global Toyo System) in accordance with the
requirements of Bid document and its related drawings on the basis of EPC Contractor
as a Engineering Solution Provider.

[2/26]
2. LG-TOYO Organization
Engineering Solution Provider

CEO
Executive Committee

Project Management Engineering Division Management Support

Refinery/Petrochem. Process (28) Administration


Project Team (17)
Static (16) Corporate Planning
Industrial Plant
Project Team (17) Machinery (14) Account. & Finance

Construction Piping (31) Sales & Marketing


Management (5) Instrument (28) Procurement

Electrical (17) SQA

Civil / Arch. (19)


Total No. of Employees : 211 Persons
Fire Fighting (2)
(Average Work Experience : 11 Years)
Green Business (3)

[3/26]
3. Project Execution Plan
Engineering Solution Provider
3.1 Project Management Objectives

In order to complete this Project successfully, LG-TOYO will concentrate and control
the following major objectives firmly during execution of the PROJECT.

• Responsibilities for EPC Works


• Quality (Technical superiority of Plant) within Schedule (Products Delivery timely)
• Keeping of Safety, Health and Environment during Construction

3.2 Implementation Plan

LG-TOYO will be responsible for project management which will be performed in


accordance with OWNER’s requirements and LG-TOYO’s standard procedure (LTS) in
order to satisfy quality standard, time schedule and performance of the Plant.

And also LG-TOYO will assign professional engineers who is skilled and have many
experience in oversea Project (Middle East Asia ; Saudi Arabia and Africa ; Egypt,
etc.) in order to smooth communication with OWNER.

[4/26]
3. Project Execution Plan
Engineering Solution Provider
3.1 Project Management Objectives

In order to complete this Project successfully, LG-TOYO will concentrate and control
the following major objectives firmly during execution of the PROJECT.

• Responsibilities for EPC Works


• Quality (Technical superiority of Plant) within Schedule (Products Delivery timely)
• Keeping of Safety, Health and Environment during Construction

3.2 Implementation Plan

LG-TOYO will be responsible for project management which will be performed in


accordance with OWNER’s requirements and LG-TOYO’s standard procedure (LTS) in
order to satisfy quality standard, time schedule and performance of the Plant.

[5/26]
3. Project Execution Plan
Engineering Solution Provider
3.3 Project Overall Schedule (Preliminary)

Year Project Period


Description
Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1) Basic Engineering

2) Detail Engineering

3) Procurement

4) Construction

5) Operation

Please note that the proposed schedule as above is typical and it can be adjustable according to site
conditions and OWNER’s requirements.

[6/26]
3. Project Execution Plan
Engineering Solution Provider
3.5 Crude Oil Extraction & Recovery System (RB-Tech)

LG-TOYO will be bring RB-Tech Technology of Greencore Engineering &


Construction (GEC) with closed communication and cooperation which is proven and
excellent technology to Crude Oil Extraction & Recovery System.

[7/26]
3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [8/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [9/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [10/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [11/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [12/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [13/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [14/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [15/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [16/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [17/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [18/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [19/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [20/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [21/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [22/26]


3. Project Execution Plan
Engineering Solution Provider

GEC RB-Tech Technology [23/26]


4. Performed Record
Engineering Solution Provider
Petrochemical

Plant Name Client Scope of Work Project Period

Acrylic Acid Plant LG Chem E, Ps, FE Jan., 2011 to Jul., 2012

SAP (Super Absorbent Polymer) LG Chem E, Ps Jan., 2011 to Jun., 2012

CA/EDC LG Chem E, Ps, FE Jan., 2011 to Jun., 2012

Bis-Phenol A Plant LG Chem E, Ps, FE Jul., 2011 to Mar., 2013

Cumene / Phenol Plant LG Chem E, Ps, FE Jul., 2011 to Mar., 2013

Ethylene Vinyl Acetate Plant LG Chem E, Ps, FE Nov., 2011 to Aug., 2013

Solution Styrene Butadiene Rubber Plant LG Chem E, Ps, FE Dec, 2012 to Sep., 2013

BPA Product Handling System LG Chem E, P, C Jan., 2012 to Sep., 2012

LG-TOYO have a lot of skilled and capable engineers who have experience with Middle East Asia
(Ammonia Plant of SAFCO in Saudi Arabia, ), Africa (Polypropylene Plant Project of OPC in Egypt)

[24/26]
4. Performed Record
Engineering Solution Provider
Industrial Plant

Plant Name Client Scope of Work Project Period

EGKr HOT (Glass Plant) TOYO-K Cs Dec., 2012 to Nov., 2013

Oksan New Plant LG Hausys PM, E, Cs May, 2012 to Jul., 2013

Photovoltaic System LG Chem E Jul, 2011 to Mar., 2013

HIB/FSH Plant LG Life PM, E, Cs Jul, 2011 to Mar., 2013

D-Project LG Display Ec Jul, 2012 to Dec., 2012

Animal Laboratory LG Life E Jun, 2012 to Sep., 2012

Built-up HVAC LG CNS Ts Jun., 2012 to Aug., 2012

TechnoPark LG Chem Ts Jan., 2012 to Jul., 2012

Busan IT Center LG CNS E Nov, 2011 to Jan., 2012

Solar 3 LG Electric E Aug, 2011 to Oct., 2011

[25/26]
5. Information of Price
Engineering Solution Provider

The estimated costs for ISBL portion of the Crude Oil Extraction & Recovery System
(Basis of Capacity : 20 Ton/hr) is US$ 4.4 MM based on EPC Lump Sum basis and this
costs can be adjusted and verified in accordance with OWNER’s requirements and site
survey to be conduit after receipt of ITB.