EMD-CIVIL WORKS

WEEKLY REPORT
FOR THE PERIOD OF
MARCH 16,2021-MARCH 22,2021
TABLE OF CONTENTS
CONTENT PAGE
I. SHUTDOWN ACTIVITIES 3-6
II. PROBLEM/S ENCOUNTERED DURING 7-12
SHUTDOWN
III. PLAN OF ACTIVITIES 13-39
I. SHUTDOWN ACTIVITIES

DATE AREA ACTIVITY MANPOWER MATERIALS REMARKS


4 CC Net, Drill bit, 100% DONE
PMO Net Installation
(Jonie and his team) Teck Screw
5 Teck Screw, 100% DONE
DCN Replace the roofing
(Rodel and his team) Drill bit
DAY 1 (APRIL
TEMPORARILY
1, 2021) Repair the control 2
DCN Metal door jamb REPAIRED
room door (Archie and his team)  
Repair the loading 2 Angle bar
WAREHOUSE
door (Archie and his team)  
4 CC Net, Drill bit
DCN, VCO Net Installation
DAY 2 (APRIL (Jonie and his team)  
3, 2021) 5 Teck Screw,
ROOFING AREAS Replace the roofing
(Rodel and his team) Drill bit
Provision of door going 4 CHB, Cement,
VCO
DAY 3 (APRIL to VCO cake area (Jonie and his team) sand & gravel
4, 2021) 5 Teck Screw,
ROOFING AREAS Replace the roofing
(Rodel and his team) Drill bit

WAREHOUSE,

1/11/2021
3
I. SHUTDOWN ACTIVITIES
Day 1

Activity:

Net Installation

1/11/2021
4
I. SHUTDOWN ACTIVITIES
Day 1
Activity:
Replacing the old roof

1/11/2021
5
Day 2
I. SHUTDOWN ACTIVITIES
Activity:
Provision of door going to
VCO Cake area
BEFORE DURING AFTER

1/11/2021
6
I. SHUTDOWN ACTIVITIES
Day 2
Activity:
Repair of loading door

BEFORE DURING AFTER

1/11/2021
7
I. SHUTDOWN ACTIVITIES
Day 2
Activity:
Repair of Control room door

BEFORE AFTER

1/11/2021
8
II. PROBLEMS ENCOUNTERED

1/11/2021
9
PLAN OF ACTIVITIES

1/11/2021
10
I. SHUTDOWN ACTIVITIES

PROJECT
AREA ACTIVITY MANPOWER MATERIALS REMARKS
NAME
4 CC Net, Drill bit,
PMO Net Installation
(Jonie and his team) Teck Screw
5 Teck Screw,
ROOFING AREAS Replace the roofing
DAY 1 (APRIL (Rodel and his team) Drill bit
1, 2021) Repair the control 2 Metal door jamb
DCN
room door (Archie and his team)  
Repair the loading 2 Angle bar
WAREHOUSE
door (Archie and his team)  
4 CC Net, Drill bit
DCN, VCO Net Installation
DAY 2 (APRIL (Jonie and his team)  
3, 2021) 5 Teck Screw,
ROOFING AREAS Replace the roofing
(Rodel and his team) Drill bit
Provision of door going 4 CHB, Cement,
VCO
DAY 3 (APRIL to VCO cake area (Jonie and his team) sand & gravel
4, 2021) 5 Teck Screw,
ROOFING AREAS Replace the roofing
(Rodel and his team) Drill bit

WAREHOUSE,

1/11/2021
11
CONSTRUCTION OF MATERIALS RECOVERY FACILITY

1/11/2021
12
PROJECT: CONSTRUCTION OF MATERIALS RECOVERY FACILITY
Location: ORIENTAL GOLDEN COCO, SITIO BITAN-AGAN,
BRGY. DAHICAN, CITY OF MATI, DAVAO ORIENTAL
Project Cost
Project Duration: Thirty (30) Calendar Days
Manpower Requirements: 7 Manpower (1-Civil Works Supervisor, 3-Laborers and 4-Skilled
Laborers)
Subject: Gantt Chart
WORKING DAYS
%
Plan 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
ITEM OF WORK Amounts Plan End Perfecte
Start
d
Clearing and Grubbing   April 6, April 7,                                                          
2021 2021
Excavation   April 8, April 8,                                                          
2021 2021
Reinforced Concrete April 9, April 15,                                                          
Works 56,874.00 2021 2021
Structural Steel/Metal April 15, April 22,                                                        
Works 41,616.00 2021 2021
Masonry Works April 10, April 15,                                                          
45,176.00 2021 2021
Roofing works   April 23, May 5,                                                          
2021 2021
Doors   May 6, May 7,                                                          
2021 2021
TOTAL PROJECT COST      
143,666.00
TOTAL NO. OF 30
WORKING DAYS:
NUMBER OF SUNDAYS: 4
TOTAL NO. OF 34
CALENDAR DAYS:
1/11/2021
13
PROJECT NAME: CONSTRUCTION OF MATERIALS RECOVERY FACILITY
LOCATION: SITIO BITAN-AGAN, BRGY. DAHICAN, CITY OF MATI, DAVAO ORIENTAL
PROJECT DURATION: 30 Calendar days
IMPLEMENTATION SCHEME: ( ) Administration ( ) Contract
SOURCE OF FUNDS:
DIRECT COST: Labor, Equipment and Materials
SUBJECT: Program of Works (POW)

ITEM ITEM OF WORK UNIT QTY. UNIT PRICE MATERIAL COST


NO.
I REINFORCED CONCRETE WORKS        
  Concrete Pedestal Footing        
  Portland Cement bags 9.00 210.00 1,890.00
  Washed Sand cu.m 0.50 600.00 300.00
  Washed Gravel cu.m 0.50 700.00 350.00
  12mmø x 6m Deformed Bar, Grade 33 lgths 8.00 202.00 1,616.00
  No. 16 tie wire kg. 1.00 75.00 75.00
     
  Concrete Pedestal      
  Portland Cement bags 3.00 210.00 630.00
  Washed Sand cu.m 0.50 600.00 300.00
  Washed Gravel cu.m 0.50 700.00 350.00
  12mmø x 6m Deformed Bar, Grade 33 lgths 4.00 202.00 808.00
  10mmø x 6m Deformed Bar, Grade 33 lgths 16.00 137.00 2,192.00
  No. 16 tie wire kgs. 3.00 75.00 225.00
     
  Wall Footing        
  Portland Cement bags 15.00 210.00 3,150.00
  Washed Sand cu.m 1.00 600.00 600.00
  Washed Gravel cu.m 2.00 700.00 1,400.00
  10mmø x 6m Deformed Bar, Grade 33 lgths 12.00 137.00 1,644.00
  No. 16 tie wire kgs. 3.00 75.00 225.00

1/11/2021
14
PROJECT NAME: CONSTRUCTION OF MATERIALS RECOVERY FACILITY
LOCATION: SITIO BITAN-AGAN, BRGY. DAHICAN, CITY OF MATI, DAVAO ORIENTAL
PROJECT DURATION: 30 Calendar days
IMPLEMENTATION SCHEME: ( ) Administration ( ) Contract
SOURCE OF FUNDS:
DIRECT COST: Labor, Equipment and Materials
SUBJECT: Program of Works (POW)

  Slab on Fill        
  Portland Cement bags 90.00 210.00 18,900.00
  Washed Sand cu.m 5.00 600.00 3,000.00
  Washed Gravel cu.m 10.00 700.00 7,000.00
  10mmø x 6m Deformed Bar, Grade 33 lgths 87.00 137.00 11,919.00
  No. 16 tie wire kgs. 4.00 75.00 300.00
     
  SUB-TOTAL 56,874.00
II STRUCTURAL STEEL/METAL WORKS        
Cyclone Wire-Gauge # 10, 2″ x 2″, 3ft x 10 meters
  roll 6.00 3,250.00 19,500.00
B.I. (Black Iron) Tubular 100mm x 50mm x 1.2mm thick, 6m
  lgths. 12.00 893.00 10,716.00
          
  Purlins       
  CEE 50mm x 100mm x 1.2mm x 6m lgths. 20.00 500.00 10,000.00
  200mm x 250mm x 10mm THK Base Plate pcs 4.00 350.00 1,400.00
  SUB-TOTAL 41,616.00

1/11/2021
15
PROJECT NAME: CONSTRUCTION OF MATERIALS RECOVERY FACILITY
LOCATION: SITIO BITAN-AGAN, BRGY. DAHICAN, CITY OF MATI, DAVAO ORIENTAL
PROJECT DURATION: 30 Calendar days
IMPLEMENTATION SCHEME: ( ) Administration ( ) Contract
SOURCE OF FUNDS:
DIRECT COST: Labor, Equipment and Materials
SUBJECT: Program of Works (POW)

III MASONRY WORKS        


  Exterior Walls        
  100 mm thk CHB pcs. 1,130.00 10.00 11,300.00
  Portland Cement bags 82.00 268.00 21,976.00
  Washed Sand cu.m 7.00 700.00 4,900.00
  10mmø x 6m Deformed Bar, Grade 33 lgths 50.00 137.00 6,850.00
  No. 16 GI Tie Wire kgs. 2.00 75.00 150.00
  SUB-TOTAL 45,176.00
TOTAL MATERIAL COST 143,666.00

1/11/2021
16
THANK YOU
AND
GOD BLESS!

1/11/2021 17