Professional Documents
Culture Documents
Chapter Six Activity Planning
Chapter Six Activity Planning
Chapter Six
Activity planning
Objectives of activity planning
This helps us to:
Assessthe feasibility of the planned project
completion date
Identify
when resources will need to be
deployed to activities
Calculate when costs will be incurred
This helps the co-ordination
and motivation of the project team
Project schedules
4 steps
Constructing an ideal activity plan
Risk analysis
Resource allocation
Schedule production
Project activities
A project is:
Composed of a number of activities
May start when at least one of its
activities is ready to start
Completed when all its activities are
completed
Defining activities -continued
An activity
Must have clearly defined start and end-points
Musthave resource requirements that can be
forecast: these are assumed to be constant
throughout the project
Must have a duration that can be forecast
May
be dependent on other activities being
completed first (precedence networks)
Identifying activities
The activity based approach (dia next slide)
Product-based approach
list the deliverable and intermediate products of
project – product breakdown structure (PBS)
Identify the order in which products have to be
created
Work out the activities needed to create the
products
Hybrid approach : final deliverable
ACTIVITY BASED
Sequencing and scheduling activities
Activity-on-arrow
Formulating a network model
A node has duration
Links have no duration
Precedents are the immediate preceding activities
Time moves from left to right
A network may not contain loops
A network should not contain dangle
Lag:
Lag is the delay of a successor activity and represents time
that must pass before the second activity can begin.
Earlier
diagram
Float =latest start – earliest start
Activity float : it is the amount of time that a task in project can be
delayed without causing a delay in subsequent task
It is difference between an activity’s earliest start date and its latest
start date .
Note : any activity with a float of zero is critical in the sense that any
delay in carrying our the activity will delay the completion of the
project .
Free float : how much an activity can be delayed without affecting its
successor activity
Total float is how much an activity can be delayed without affecting the
project finish date