Restructuring Project Sample Docs For P2 - Pract
Restructuring Project Sample Docs For P2 - Pract
The feasibility study concluded that there was a case for restructuring the services currently
delivered by two business functions: Facilities (responsible for maintenance of buildings and
grounds) and Information Technology (IT). The recommendations were:
Restructure Facilities services and reduce the number of Facilities staff by 20%.
• Restructure IT services and replace the existing IT system with a new hardware and software
solution.
The feasibility study contained a high-level summary of the existing Facilities staffing structure
and the existing IT system, plus an outline Business Case for the required project. The external
consultants from Teamtech also made the following recommendations for the management of
the project: Use PRINCE2®.
Set up the project with 4 management stages:
• Stage 1: Standard PRINCE2 initiation activities
• Stage 2: Create a detailed design for the future Facilities staffing structure and a specification
of the new hardware and software solution. Prepare a contract for the supply and installation
of the new hardware and software solution
• Stage 3: Create request for tender and evaluate proposals. Select supplier and agree
contract
• Stage 4: Implement the new Facilities staffing structure, install new hardware and software
solution, and run a trial period.
Initial estimates indicated that the project would cost £2.5 million and take two years to
complete. There is an expected saving of £20 million over 10-years. MFH senior management
accepted the recommendations as a basis for the project. However, any event that may result in
a loss of MFH data must be escalated to them immediately.
Exercise A – Project Management Team
Additional Scenario Information
Resources who could be involved in the project:
Teamtech Account Manager: He represents Teamtech, a recruitment agency that provide
specialist resources to government departments. Teamtech provided the consultants who
carried out the feasibility study. They will not be developing any of the project’s products.
However, the same consultants will be made available for support and guidance to the
Information Technology and Facilities teams during the Restructuring project.
Director of Finance: She was transferred from Information Technology 12 months ago. She
is responsible for ensuring a cost-effective approach is adopted in all operational and
project activities across the Ministry of Food Hygiene.
Senior User 1. Director of The Senior User is responsible for specifying the
Research and needs of those who will use the project's products.
Development And she deals with Information Technology and
Facilities and can make sure the user's needs are
specified.
2. Hardware The role represents those who will use the project's
Manager products, including operations and maintenance.
This positions the Hardware Manager as a Senior
User. 'the outcome will have an impact on him', he
maintains computer hardware for all business
functions. T he Senior User specifies the
requirements and commits user resources.
Role Candidate Reason
Senior Teamtech The Senior Supplier role would need
Supplier Account representatives from the Facilities and
Manager Information Technology Departments.
And he will be providing support to the Facilities
team during the project.
(User Project
Assurance )
Role Candidate Reason
Project MFH PRINCE2- Has the skills and experience to manage the project
Manager experienced on a day to day basis on behalf of the project board.
Project
Manager
Project From IT and The role of Project Support is not optional, but the
Support facilities dept allocation of a separate individual or group to carry
out the required tasks is. Project Support defaults to
the Project Manager. In this project, given its scope
and number of stakeholders, it would be
appropriate to appoint more than one individual to
support the Project Manager.
Change Some one from Executive reporting…..
Authority IT/ facilities/
finance dept
Constraints 1. Required hardware and softwares are available and delivered timely.
and
Assumption Assumptions 2. Enough atleast 5 parties responds to the tender
s Staff will be adequately trained to work and maintain new infra.
ADD :
Outline Business Case, Project Product Description, Project Approach, Project management
team structure, Role Descriptions, and any references.
Exercise C – Business Case
The Restructuring project has completed the Starting up a Project process and is now in
the initiation stage. Because of the strategic importance of the project, the MFH Chief
Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager
has been appointed from within MFH. Staff within the business functions being
restructured will work with the external consultants who conducted the feasibility study to
define the detailed design and specification.
Using the scenario information, draft the project Business Case using the headings below
and Appendix A.2 to help you. Suggest where you would get missing information from and
check for its accuracy.
At the end of the exercise, be prepared to present your work to the rest of the group.
Information for your project Information
source and
accuracy check
Expected Dis- Lower morale in staff because of fear of loosing job. Feasibility
benefits study report,
PB
Purpose : The purpose that the projects products will fulfill, its functions,
what the overall products of the project are and who will use them.
Say In our case: each staff member to have confortable and sufficient work
space with latest HW and Software.
• Acceptance Criteria : Must be measureable
• Project level tolerances defined
• Acceptances criteria method
• Responsibilities for signing off the acceptances criteria e.g. senior user
In our case:
• Each staff has working space of 64 sq. ft (8 x8), with 3 power points, desk of 2.5
ft +-1%depth x 4 ft+-1% width at a height of 3 ft+-1%.
• PC system config….., Softwares installed…., LAN cable point with 1 meter cable,
Wifi Router of …… spec. etc…
Exercise E – Project Assurance
The MFH Project Manager is now assembling the Project Initiation Documentation at the
end of the Initiating a Project process.
You are Project Assurance. What specific items would you want to review within the
Project Initiation Documentation and why?
Item to review Reason
Lessons recalled Learn from experience
Strategy documents : all strategy Without this project delivery and quality
documents in place and risk, quality, Issue can’t be assured. Needed to check proper
registers corporate stds are adopted and tailored .
Configuration - Strategy doc and Issue Applicable standards and templates are
register used
Project Plan With proper details no. of stages, teams,
timelines, etc
Progress Controls No. of management stages, technical
stages, overlapping, etc.
Purpose This agreement specifies the MFH requirements for the supply
and installation of a hardware and software solution. It provides
measurable criteria against which the selected external supplier's
performance will be assessed.
Format and A4, Word document, printed both sides in black and white.
· Font: Arial, 12pts.
Presentation·
Quality Criteria (To what spec the product is to be produced, how will you check this
products (what quality measurem,ent will be applied) and to what
this specs this product to meet)
· Contains all composition items listed above.
· Not more than 60 pages.
· Complies with MFH corporate branding standards.
· No typographical errors.
Introduction
This document defines the approach to be taken to achieve the required quality levels during
the project. The Project Board will have overall responsibility for the Quality Management
Strategy. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
Industry quality standards for delivering hardware and software solutions.
MFH document standards.
Records
A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
Configuration Item Records will be maintained for each product to describe its status, version
and variant.
Quality records for products that require them will be stored in the quality database.
Roles and responsibilities
Team Managers will provide details of quality checks that have been carried out.
Team Managers will ensure that the Quality Register is updated with the names of team
members who are involved in the review process.
The Senior User will review the Product Descriptions of the products to be produced by
the selected external supplier to ensure that they can be achieved.
Product Breakdown Structure
Restructuring Project
Tender
Publicity
Proposal
assessment
Selected
contractor
Risk Register
Identify a risk to the MFH Restructuring project and create an entry in the Risk Register.