Government of the Punjab

---11-2021
PDWP Agenda Item:----

September, 2021
PROJECT PROFILE

1. Project Title Establishment of New Small Industrial


Estate in Gujrat
2. Location Sammah-Kunjah-Dinga Road, Gujrat,
District Gujrat
Government of the Punjab

3. Sponsoring ICI&SD Department


4. Executing
PSIC
Agency
5. Estimated Cost TOTAL Capital Revenue
(In Million Rs) 1325.00 1004.63 320.37
6. Gestation Period 36 months
7. Funding ADP 2021-22
8. Allocation in ADP Rs. 400.00 million
2021-22
2
BACKGROUND & DESCRIPTION (1/2)
• Gujrat is famous for its renowned major industrial sectors
and export oriented industrial hub with a wide variety of
items ranging from fan manufacturing, furniture, ceramics,
agricultural implements, shoes manufacturing and their
Government of the Punjab

allied industries as well as forms a part of “Golden


Triangle” of industrial cities with export-oriented economy.

• PSIC established first Small Industries Estate in Gujrat in


the year 1974 over an area of Land measuring 71-Acres.
Presently, Gujrat Industrial Estate is fully colonized; hence,
significant demand in the market prevails for the
establishment of new SIE in Gujrat.

3
BACKGROUND & DESCRIPTION (2/2)
• In order to gauge market demand, a series of meeting of
PSIC’s team were held with stakeholders i.e Gujrat
Chamber of Commerce and Industry , Pakistan Electric
Fans Manufacturers Association , Furniture Manufacturers
Government of the Punjab

Association, Cutlery & Ceramic Associations and other


stakeholders as well.
• On the basis of the discussion made with stakeholders, it
has been observed that there is a dire need to establish a
new SIE in Gujrat.
• Following industries will be developed in proposed SIE:
 Fan Industry
 Furniture Industry
 Ceramic Industry
 Cutlery & Engineering Industry
4
PROJECT OBJECTIVES

To provide well organized and dedicated industrial area with


complete infrastructure facilities for promotion and
Government of the Punjab

development of industrial clusters / SMEs especially relating


to Fan, Furniture, and Ceramic but not limited to.

5
PROJECT DESIGN AND SCOPE
The Distribution of land (100 Acres) is proposed as
under:
SN Description Proportion of Land Area (K)
1 Plots/ Saleable area 65.082 % 521
2 Infrastructure & 25.926 % 207
Utilities
Government of the Punjab

3 Area under Amenities 6.106 % 49


4 Area under Green 2.884 % 23
Space
Total 100 % 800

Category Plot Size No. of Plots


A 8 Kanal 15
B 4 Kanal 34
C 2 Kanal 114
D 1 Kanal 146
  Total 309 6
Government of the Punjab

LAYOUT PLAN

7
Government of the Punjab

SITE MAP

8
Government of the Punjab

MASTER PLAN

9
SUMMARY OF COST

2021- 2022- 2023-


SN Description TOTAL
22 23 24
1 Cost of Land 300.00 300.00
2 Human Resource - 7.308 8.039 15.347
Government of the Punjab

3 IT Equipment - 0.670 0.000 0.670


4 Vehicle - 2.100 0.000 2.100
5 Furniture & Fixture - 0.590 0.000 0.590
6 Office Equipment - 1.100 0.000 1.100
7 Operational - 1.000 1.500 2.500
Expense
8 Civil Works 100.00 902.693 0.00 1002.693
  GRAND TOTAL 400.00 915.46 9.539 1325.00
10
COST OF HUMAN RESOURCE
Pay P.M
SN Name of the post No
Scale Allocation
1 Assistant Director 1 17 0.086
2 Assistant Civil Engineer 1 17 0.086
3 Office Assistant 1 16 0.054
Government of the Punjab

4 Accountant 1 16 0.054
5 Senior Clerk/ Record Keeper 1 14 0.043
6 Sub Engineer 1 14 0.043
7 Electrician 1 11 0.036
8 Tube-well Operator 1 8 0.035
9 Driver 1 5 0.034
10 Dispatch Rider 1 5 0.034
11 Naib Qasid 1 1 0.026
12 Chowkidar 2 1 0.026
13 Sweeper 1 1 0.026 11
COST OF IT EQUIPMENT

Sr.
Object Unit Total
No.   Description Qty.
Code price Cost
 
Government of the Punjab

1   Desktop Computer 2 0.150 0.300


 2 Laptop 1 0.150 0.150
 3 Scanners 1 0.050 0.050
 4 Laser jet Computer 2 0.060 0.120
A09203 Printer (Black & White)
 5 External Hard Drives 1 0.020 0.020
 6 USBs 5 0.004 0.020
 7 Internet Device 1 0.010 0.010
Total     0.670

12
COST OF VEHICLES

S Object Amount
Description Quantity
N. Code
Government of the Punjab

1000 cc Car with


1 A09105 registration and other 1 1.900
charges / accessories
Motor Cycle (70 cc)
2 A09105 2 0.200
with Registration etc.
Total 2.100

13
COST OF FURNITURE & FIXTURES
S Object
Description
N Code Total
      Qty Unit cost
1   Executive Table 2 0.100 0.200
Government of the Punjab

    with revolving


  chair, side rack
and 4 visitor
chairs
2 A09107 Office table with 3 0.050 0.150
revolving chair
and side rack
3   File cabinets 6 0.030 0.180
  Office Chairs 12 0.005 0.060
4
Total:- 0.590 14
COST OF OFFICE EQUIPMENT

Sr. Unit
Description Qty. Total
No. Price
Split Air Conditioner (1.5 2 0.150 0.300
1
Tons)
Government of the Punjab

2 Photo Copier Machine 1 0.500 0.500


3 LED 1 0.100 0.100
Ceiling / Bracket / 12 0.010 0.120
4 Pedestal fans ( As per
requirements)
5 Water Dispenser 1 0.030 0.030
6 Electric Water Cooler 1 0.050 0.050
  TOTAL 1.100
15
PROJECT STEERING COMMITTEE
Project Steering Committee shall comprise of following for
monitoring and mentoring the scheme and to take necessary
policy decisions for successful implementation of the scheme
and to remove bottlenecks if any. Steering committee will
Government of the Punjab

also review the progress of the scheme quarterly or on need


basis.
1. Secretary, ICI&SDD In Chair
2. Managing Director, PSIC Member
3. Director (Works & Development) Secretary
4. Director (Estate Management) Member
5. Representative from P&D Board Member
6. Regional Director, Gujranwala Member
7. Assistant Civil Engineer, SIE, Gujrat Member
16
EXIT STRATEGY

• On completion of the estate, Board of Management of


Estate would be formulated as per PSIC’s SIE Policy who
will run all matters / affairs of the estate as per PSIC’s
policy / regulations.
Government of the Punjab

• The services of staff hired in the scheme will stand


terminated after completion of gestation period of the
scheme.
• However, services of the staff may be retained after the
expiry of gestation period but it would be at sole
discretion of the Board of Management of the Estate as
per requirements.
• In this case, salary expense would be met from the funds
collected from the estate through maintenance charges.
17
DELIBERATIONS OF PRE-PDWP (1/2)

The PC-I of the project was considered by the Pre-PDWP in


its meeting dated 17.09.2021. Decisions of Pre-PDWP and
departmental response is as under:
Observation of Departmental Remarks
Government of the Punjab

SN
Pre-PDWP Response
Department to carry Pre-feasibility has Noted.
out a detailed in- been incorporated
1
house pre-feasibility in revised PC-I.
study of the project.
Rough cost estimates Rough Cost Noted.
of civil work to be estimates vetted.
got vetted from the Departmental
2
technical wing of response is at
P&D Board. Annex-A.
18
DELIBERATIONS OF PRE-PDWP (1/2)
S Observation of Pre- Departmental Response Remark
N PDWP s
Department to furnish a. Pre-feasibility study Business
revised PC-I of the incorporated in revised Model is
project within fortnight PC-I. missing.
incorporating the b. Pre-feasibility study
Government of the Punjab

following: covers need assessment


a. Pre-Feasibility Study c. Pre-feasibility study
b. Need Assessment covers Economic and
  c. Economic and financial Financial analysis
3 analysis d. Sound Sustainability and
d. Sound sustainability business model is in Pre-
and business model feasibility study
e. Terms and conditions e. PSIC SIE Policy, 2019 and
of the formulation of PSIC Rules of Business of
Board of Management of Board(s) of Management
Estate upon completion of SIEs are incorporated
of the estate in revised PC-I. 19
SUBMISSION

The scheme at the cost of Rs.1325.00 million is


placed before PDWP for consideration subject to the
following:
Government of the Punjab

• Department to incorporate Business Model in


the PC-I.
• Observations of Technical wing of P&D
Board to be complied with satisfactorily.

20
Government of the Punjab

THANKS