Workflow - Drilling Project Design & Planning
Workflow - Drilling Project Design & Planning
Workflow - Drilling Project Design & Planning
Risk Management
3 RKH
Work Breakdown Structure - Project Level
ID Name Start Duration % DoneProcess Document Responsible Depends on
PROJECT Set UP Process 01 Dec '96 79d 0%
1 PREPARE PROJECT MANAGEMENT 01 Dec '96 79d 0%
2 Initialise/Edit WEMS at Project, Field (Design) and 02
Well
Dec
(Programme)
'96 1d Level0%
3 Develop Field Master Project Schedule and Interfaces01 Dec '96 0d 0%
4 Develop Works Contract for Integrated Services02 Dec '96 79d 0%
5 Develop / Agree workscope for each service provider
20 Mar '97 1d 0%
6 Agree Remuneration package for each Service02 Provider
Dec '96 1d 0%
7 Develop 3rd Party agreements to complete project20 Mar
workscope
'97 1d 0%
8 Agree Terms and Conditions 02 Dec '96 1d 0%
9 Sign Works Contract 02 Dec '96 1d 0%
10 Develop Contract / Alliance Agreement 02 Dec '96 1d 0%
11 Develop Alliance Operating Principles and Roles02 Dec '96 1d 0%
12 Review the total Project Work Scope 02 Dec '96 1d 0%
13 Review / Agree total Project Budget Cost 02 Dec '96 1d 0%
14 Agree Basis for Risk and Reward 02 Dec '96 1d 0%
15 Circulate/Review Draft 02 Dec '96 1d 0%
16 Sign Alliance Agreement 02 Dec '96 1d 0%
17 Develop Project Organization & Resources 02 Dec '96 1d 0%
18 Set up Project Steering Committee / Alliance Board
02 Dec '96 1d 0%
19 Define Project Team Positions and Required Competencies
02 Dec '96 1d 0%
20 Define Project Organigrams 02 Dec '96 1d 0% O>Org.ppt
21 Define Roles/Responsibilities across project 02 Dec '96 1d 0%
22 Define Reporting relationships 02 Dec '96 1d 0%
23 Define Personnel Positions / Competencies and 02Succession
Dec '96 Plan
1d 0% O>Persplan.mpp
24 Define / Develop Training Requirements 02 Dec '96 1d 0% O>Persplan.mpp
25 Define Ops principles / Guidance on RACI 02 Dec '96 1d 0%
26 Agree RACI Chart for running organisation 02 Dec '96 1d 0% O>Raci.xls
27 Develop Goals for teambuilding and define responsibilities
02 Dec '96 1d 0%
28 Develop Schedule for Teambuilding exercises 02 Dec '96 1d 0%
29 Develop Goals for Cross Cultural Issues and define
02 Dec responsibilities
'96 1d 0%
30 Define Communication Channels with other Project
02 DecGroups
'96 1d 0%
31 Establish Project Multidiscipline Workgroups / Goals
02 Dec and'96Responsibilities
1d 0%
32 Define Workgroups participants and communication
02 Dec / reporting
'96 1dmethods0%
33 Prepare Project QHSE Management System 01 Dec '96 1d 0%
34 Identify/Summarise Risks to Project Performance02 Dec
Contract
'96 1d 0%
35 Prepare/Maintain Project Assurance Plan 02 Dec '96 1d 0%
4 RKH 36 Agree Policies with Operator and Drilling Contractor
02 Dec '96 1d 0%
Work Breakdown Structure - Design Level
ID Name Start Duration % Done Process Document Responsible Depends on
FIELD DESIGN PROCESS 01 Dec '96 76d 0%
1 ORGANISE FIELD DESIGN PROCESS 02 Dec '96 1d 0%
2 Review Scope of Design Work 02 Dec '96 1d 0%
3 Agree and document Design Policies to be used 02 Dec '96 1d 0%
4 Update Preliminary Project Schedule, Resources 02 Dec
and'96
Responsibilities
1d 0%
5 REVIEW FIELD OBJECTIVES AND FIELD / WELL 01PROPOSAL
Dec '96 1d 0%
6 Meeting with Operator : Review Development02 Proposals
Dec '96 and Well1d Information
0%
7 Identify possible external specialist design work02 Dec '96 1d 0%
8 Identify possible R&D work from Product Lines02orDec external
'96 contractor
1d 0%
9 Develop the FIELD / Well Proposal 01 Dec '96 0d 0% PROP.MPP O>PROP.doc
10 MEETING - Project Team Review Field / Well01 Proposal
Dec '96with Operator
0d 0%
11 WELL PROPOSAL APPROVED BY OPERATOR 02 Dec '96 1d 0% O>WELPROP.DOC
12 REVIEW CONCEPTUAL WELL TEST / COMPLETION 02 Dec '96 OBJECTIVES
1d 0%
13 Meeting with PE group to Review outline Well 02 Test
Dec/ Completion
'96 1d
Objectives0%
14 Identify Interfaces between Geological / Well Test
02 Dec
/ Completion
'96 Objectives
1d 0%
15 Identify potential interfaces between Well / Test02
/ Completion
Dec '96 designs
1d 0%
16 Conceptual Well Test / Completion Approved by 02Operator
Dec '96 1d 0% O>BODCCP.doc
17 Enter Conceptual Completion document into WEMS 02 Dec '96 1d 0%
18 DEVELOP DRILLING BASIS OF DESIGN 01 Dec '96 76d 0% O>BOD Drilling.doc
19 Review Goals in Well proposal 02 Dec '96 1d 0%
20 Perform Offset Drilling Data Analysis 01 Dec '96 0d 0% BODODA.MPP O>BODODA.DOC
21 Casing / Hole size Basis of Design 01 Dec '96 0d 0% BODCSG.MPP O>BODCSG.DOC
22 Tieback Basis of design 01 Dec '96 0d 0% BODTBK.MPP O>BODTBK.doc
23 Directional Basis of Design 01 Dec '96 0d 0% BODDIR.MPP O>BODDIR.DOC
24 Drilling Fluids Basis of Design 01 Dec '96 0d 0% BODMUD.MPP O>BODMUD.DOC
25 Cementing Basis of Design 01 Dec '96 0d 0% BODCMT.MPP O>BODCMT.DOC
26 Bits/Hydraulics/Hole Cleaning Basis of Design02 Dec '96 1d 0% O>BODBIT.DOC
27 Jack Up Riser / Conductor Basis of design 01 Dec '96 0d 0% BODJUR.MPP O>BODJUR.DOC
28 Semisub Riser Basis of design 02 Dec '96 1d 0% BODSSR.MPP O>BODSSR.doc
29 Well Control Basis of Design, and Kick Detection 01 Dec
Methods
'96 0d 0% BODWCN.MPP O>BODWCN.doc
30 Wellhead (surface) Basis of Design 02 Dec '96 1d 0% BODWHD.MPP O>BODWHD.DOC
31 Mudline Suspension Basis of Design 02 Dec '96 1d 0% BODMLS.MPP O>BODMLS.doc
32 Wellhead (subsea) Basis of Design 02 Dec '96 1d 0% BODSSW.MPP O>BODSSW.doc
33 Evaluation Basis of Design 01 Dec '96 0d 0% BODEVL.MPP O>BODEVL.DOC
34 Suspension or Plug & Abandonment Basis of Design 01 Dec '96 0d 0% BODP&A.MPP O>BODP&A.DOC
35 Environmental Basis of Design 02 Dec '96 1d 0% O>BODENV.doc
36 Identify ROV requirements and equipment specifications
02 Dec '96 1d 0% O>BODROV.doc
37 Identify / document RIG Upgrade requirements02orDec Rig'96
Equipment1dSpecifications
0% O>BODRIG.doc
38 HTHP Checklist 17 Mar '97 1d 0% O>HTHPCHK.doc
39 QHSE Considerations 02 Dec '96 1d 0%
40 Risk Management 02 Dec '96 1d 0%
41 Perform High level risk assessment of design
02 Dec topics.
'96 Enter1dresults into0%
"Risk View"
42 Confirm that a detailed Risk Assessment02 has
Decbeen
'96carried1d
out on individual
0% design topics
43 Confirm that the Risk Register and Action02Plan
Decare'96complete
1d for this Design
0%
44 Confirm that any outstanding Risks are clearly
02 DecIdentified
'96 1d 0%
5 RKH
Well Construction RACI
De c isio n Ca te g o ry Onsho re
BM CPM IPM WOS RM SDE SPE OC SCR SSR
A) We ll De sig n a nd Pro g ra m m ing
1 De fine we ll o b je c tive s (We ll Pro po sa l) C C C C A/ R
2 We ll de sig n to TD A C R C C
3 Co m p le tio n De sig n A C C C R C
4 Te sting De sig n A C C C R C
5 AFE Ap pro va l A C R
6 Drilling Pro g ra m (HSE & p a rtne rs) C C C A R
7 De ta ile d o pe ra tio na l se que nc e s A C
8 Lia so n with Pa rtne rs A R
6 RKH
Typical Single Well Resources
Position Dec Jan Feb Mar Apr May June Jul Aug Sep
98 99 99 99 99 99 99 99 99 99
7 RKH
Detailed Planning
Design and Planning incorporates Quality, Time and Cost
Quality Time
Cost
8 RKH
The IPM D-E-E Cycle
Evaluate
Evaluate Design & Plan
Design
Execute
Execute
9 RKH
The WEMS* D-E-E Process
Design & Plan
Project Wellhead
Fluid
Directional
Process Maps
Design Templates
Objectives Cementing
Casing
Project Schedule
Designs
Roles & Responsibilities
Options
Policies
Policies & Procedures
Risk
Design Risk
Auditable Trail
KEY Documents:
Well Proposal
Basis of Design
Operations Programs
QHSE Plan
Permit Documents
Evaluate Execute
Well AFE
Performance Database Wellhead Wellhead
Program
Fluid Risk Register Fluid
Auditable Trail Directional Directional Policies & Procedures
End of Well Report
Process Improvement Cementing
Casing
Cementing
Casing
Guidelines
Actual vs Plan Designs Designs
Performance Curve
Benchmarking Options
Policies
Options
Policies
Auditable Trail
Continuous Risk Risk
Safety Report
Improvement Operational Risk
10 RKH Operational Learning
Project Management vs Operations Mgt.
•Operations
Project
Repetitive
Unique
Finite
Eternal
RevolutionaryChange
Evolutionary Change
Disequilibrium
Equilibrium
Unbalanced
Balanced Objectives
Objectives
Transient
Stable Resources
Resources
Flexibility
Stability
Effectiveness
Efficiency
Goals
Roles
Risk & Uncertainty
Experience
11 RKH
Well Construction Contract
Prepare Contract/Workscope
Mobilise Team
De-Mobilise Team
12 RKH
Key Design & Planning Steps &
Documents
Generate Well Objectives
• Key Well requirements
• Key Well success factors
• Starting Point for Design
Develop Design
• Options generation
• Product Line
Involvement
• Engineering Applications
•Generate
DesignProgram
consistency
• Well Specific Trajectory
• Detailed Instructions
Evaluate
• Actual vs Planned
Well Proposal
• Specifies Subsurface Environment and Well Objectives.
• Challenge Assumptions
Basis of Design ( BOD)
BOD Document for each design element
Content of each individual Design document:
– Reference to Policy or Code used in the design
– Required Design Safety Factors
– Methodology
– Source of input information
– Goals and Assumptions
– Well objectives and key success factors addressed by the design
– Design Options discussion and evaluation.
– Summary Results of simulation work performed (e.g. hydraulics, casing
wear, torque etc)
– Justification for selected design option
– Limits of applicability of the selected design over life of well
15 RKH
Features of the BOD
• Captures Reasoning
• Considers Complete Life of a Well Cycle
– Clearly States the Design envelope of the well
• Primary Design Document for similar wells in a Field
Development
• For Non-continuous Operations:
– May apply to only first phase of Well Operations
• For Field Development
– May apply to each well type
– Updated with lessons learned
– Always Current
• Sets design criteria and options for Product Line Audit Packs
16 RKH
Well Program
17 RKH
Difference Between Design and Program
Design:
• Link between Well Objectives and Program
Well Objectives
Design Well Program
(Well Proposal)
Program:
• Link between Design and Operations
18 RKH
Program and Operations Program
•Program
• Well Proposal
• High Level Operations Sequence
• Program Summary Sheet
• Operations Program
• Time Depth Plot
• Detailed Programs
• Detailed Operational Sequences
(or Guidelines)
• (Cost Information)
19 RKH
Detailed Planning
Design and Planning incorporates Quality, Time and Cost
Quality Time
Cost
20 RKH
Time vs Depth Curves
0
500
1000
1500
Depth
2000
2500
3000
3500
4000
4500
0 1 2 3 4 5 6 7
21 RKH Duration (Days)
Time vs Depth Curves
Operating Company Elf Congo Spud Date
Well Name KOBM1-06 To Date
Rig Searex-9 Planne d End Date
Fie ld (if applicable) Kombi Expected End Date
400
400 17 1/2" hole
Skidded to KOBM101 on 24 Jul y 1999
600
RD TRD)TR) T )
13 3/8" casing
800
n(Mm(M
800
inmi m
800
pethpi nth
1000
1000 12 1/4" hole
D eDpeDth
1000
1200
1200
1200
1400
1400
1400
1600
1600 Log - 9 5/8" casing 8 1/2" hole
1600 TLC/Liner/Completion
1800
1800
1800 0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00 16.00 18.00 20.00 22.00 24.00 26.00 28.00
0
0.00 22.00 4 4.00 6 6.008 10
8.00 12
10.00 14
12.00 1614.00 18 16.00
20
Days 22
18.00 24
20.00 26
22.00 28
24.00 30 26.0032 34
28.00
Days
Days
22 RKH
Detailed Planning
Design and Planning incorporates Quality, Time and Cost
Quality Time
Cost
23 RKH
Design & Planning - Well Costs
Cost Specification
• Fixed Costs
• Daily Costs
• Unit Costs
24 RKH
Fixed Costs
• Wellheads
• Site Preparation
• Casing
• Cement
• Tubing
• Packers
25 RKH
Daily Costs
• Rig Dayrate
• Tool Rentals
• Specialist Services
• Salaries & wages
• Fuel
• Lubricants
• Drilling Consumables (dope, soap & rope)
• Transport
26 RKH
Unit Costs
• Well Consumables
– e.g. price per tonnes of baryte or bentonite
27 RKH
Example Onshore Exploration Well
Fixed Items
Site Survey & Rental 72000 12%
Rig Mob/demob 46000 7%
Wellhead 26000 4%
Conductor & Casing 40000 6%
Rock Bits 17000 3%
Coreheads 13000 2%
Cementation 35000 6%
Transport/Cranes 10000 2%
Electric Logging 30000 5%
Disposal 8000 1%
Accommodation 5000 1%
Well Engineering 50000 8%
352000 57%
28 RKH
Example Onshore Exploration Well
Daily Items
Rig Dayrate 97000 16%
Mudlogging 30000 5%
Mud Engineering 10000 2%
Fuel 10000 2%
Tool Rentals 5000 1%
Water Supply 5000 1%
Wellsite Supervision 15000 2%
Wellsite geologist 8000 1%
Overheads 70000 11%
250000 41%
Unit Items
Mud Chemicals 14000 2%
14000 2%
29 RKH
Cost Planning - AFE
• AFE - Authorisation for Expenditure
• Predicts cost of proposed well
• Accuracy depends on amount of available information
• Normally broken down into circa 100 coded items
• Phases
– Preparation
– Drilling
– Testing
30 RKH
– Abandonment
Estimating
• Timing - Review Similar Wells
• Quotes from:
– Drilling Contractors
– Service Companies
– Wellhead Companies
31 RKH
IPM Project Cost Recovery
Recoverable Lost / Unidentified Recoverable Lost / Unidentified
Project Total
Management
Overhead
Project Total
Management Overhead
G&G Costs
G&G Costs “Unrecoverable” Costs
Engineering
reduced and made
Engineering Overhead
Overhead more visible
Procurement
Procurement
HQ and support costs IPM Mang, Eng & Proc
Logistics Costs Identified in
on projects not visible
IPM component
or deemed recoverable Logistics
Construction now recoverable
by Partners
Construction
Drilling Rig
Drilling Rig
Major indirect
Drilling Services
cost reduction
Drilling Services
We
ll W
el
l
D
E
S
I
GN P
r
o
gr
a
m
O
b
j
e
ct
iv
es
D
E
S
I
GN P
r
o
gr
a
m O
P
E
R
AT
I
O
NS
34 RKH
Design to Drilling Program
DESIGN PROGRAM OPS PROGRAM
SUMMARY (Full Rig info)
DETAILED
FIELD or WELL Finalised Well Programs
Proposal Specific Proposal DTLCSG.doc
prop.doc prop.doc DTLWHD.doc
WELL Finalised
PROPOSAL WELL
PROPOSAL
BASIS OF PROGRAM
DESIGN SUMMARY
HIGH LEVEL
OPS
SEQUENCE
DETAILED
PROGRAMS
OPS
SEQUENCES
36 RKH
Examples of Well Program (summary)
Compilation of individual summary documents e.g.
•Casing:
– Final casing Specification, shoe depths, Kick Tolerance, Design factors,
– Design limits, Pressure test requirements.
•Mud
– Spec by interval (MW, type, PV, YP, etc), Contingency plans (lost circ etc),
• Cement:
– Slurry specifications, excesses., planned TOC, centralisation,
37 RKH
Detailed Programs
Detailed Instructions on Implementation some aspect of the
Well Program
Liner)
39 RKH
Operations Program
• Compiled from:
• Detailed Programs
• Operational Procedures or Guidelines
• AFE (option)
• Contingency Procedures
– Environmental Plan, H2S Plan, Stuck Pipe / Fishing Plan)
40 RKH
Programme Checklist - Example
ID Name % Done Document Details
PRGCHK.mpp 0%
1 PROGRAMME CHECKLIST 0%
2 WELL NAME: 0%
6 SECTION CHECKLIST 0% To be completed by the Engineer responsible for the individual se
7 WELL PROPOSAL 0%
8 Has the Well Proposal design subprocess been completed in compiling 0%
the finalised Well Proposal?
9 Has an authorised Well Proposal been issued to the Project Team with0% clear well objectives?
10 Is the authorised Well Proposal a significant deviation from previous proposal
0% documents?
11 If yes, has this deviation been assessed as part of auditable process? 0%
12 Has the assessment of Shallow Gas risk changed for this finalised Proposal?
0%
13 Have the Well Proposal requirements been subject to an operational risk 0%assessment?
14 Have all risks been worked to as low as reasonably practical? 0%
15 Does the Well Proposal information include Design and Operational lessons0% learned from previous wells?
18 Casing Programme 0%
19 Has the Casing Basis of Design been approved? State Reference. 0%
20 Is the Casing Programme in this well a deviation from the approved Basis 0% of Design?
21 If yes, has this deviation been assessed as part of auditable process? 0%
22 Does the Programme conform with stated Policy? 0%
23 If not has a Policy dispensation procedure been followed? 0%
24 Have the design loads, design envelope, FIT, pressure test requirements 0% been included in the well programme?
25 Have operational limitations or requirements identified in the DESIGN 0% been clearly stated in the Programme?
26 Has the casing programme been subjected to an operational risk assessment0% ? State Reference.
27 Have all risks been worked to as low as reasonably practical? 0%
28 Are outstanding operational risks clearly indicated in the Programme? 0%
29 Does this programme include all relevant Design and Operational learning 0% from previous wells?
30 Directional Programme 0%
31 Has the Directional Basis of Design been approved? State Reference.0%
32 Is the Directional Programme in this well a deviation from the approved0% Basis of Design?
33 If yes, has this deviation been assessed as part of auditable process? 0%
34 Has the Well Planning Audit pack been independently verified and signed 0% off? State document Reference.
35 Does the Programme conform with stated Policy? 0%
36 If not has a Policy dispensation procedure been followed? 0%
37 Have the design limitations for the trajectory, target and well survey been
0% included in the Programme?
38 Have acceptability criteria for well surveys been clearly stated? 0%
41 RKH
Programme Approvals
||
TECHNICAL PROJECT / GOVERNMENT ||
APPROVAL PARTNER APPROVAL ||
APPROVAL ||
WELL PROPOSAL ||
+ BOD PROGRAM ||
PROGRAM
||
||
||
||
||
PROJECT || ISSUE TO RIG
APPROVAL ||
||
DETAILED || OPERATIONS
PROGRAMS || PROGRAM
+ OPS ||
SEQUENCES ||
||
||
42 RKH
Technical Integrity Assurance Programme
• What is it?
• Why have it?
• How do we do it?
• A practical example of it?
Technical Integrity Assurance Programme
A Systematic, Formal and Ongoing Procedure
to Promote & Confirm
• Objectives
• Who Should Carry out
• What needs to be Included in the Review
• What has to be Provided to Carry out
• What is done with Results
• How do we confirm success of the Review Process
Well Reviewer