Professional Documents
Culture Documents
Chiller Control Project Ifc Ii
Chiller Control Project Ifc Ii
Chiller Control Project Ifc Ii
EVAPORATOR SIDE
2813 Kw
2813 Kw
1758 Kw
879 Kw
VARIABLE FLOW PRIMARY PARALLEL CHILLER
CONFIGURATION
EVAPORATOR SIDE
Chiller
Motorized Valve
Temperature Sensor
Pressure Sensor
Volumetric Flow Sensor
VARIABLE FLOW PRIMARY PARALLEL CHILLER
CONFIGURATION
EVAPORATOR SIDE
VARIABLE FLOW PRIMARY PARALLEL CHILLER
CONFIGURATION
Pressure Transducer
VARIABLE FLOW PRIMARY PARALLEL CHILLER
CONFIGURATION
Motorized Valve
CONDENSER SIDE
Cooling Tower
Temperature Sensor
VARIABLE FLOW PRIMARY PARALLEL CHILLER
CONFIGURATION
CONDENSER SIDE
CONCEPT
• The flow through the chillers is varied in response to the system load
PRESSURE INDEPENDENT BALANCING CONTROL VALVES
Overflow
No overflow
M M
∆p
M M
70kpa
Flow
VSD DP
MAIN PRINCIPAL
• The flow through the chillers is varied in response to the system load
• Variable Speed Drive / Inverter to minimize pumping energy
• At the same time we have to maintain the minimum flow required by
the chiller
• Each chillers must be equipped with a flow meter that is used to
measure flow through each chiller evaporator
• A bypass valve is required to maintain minimal flow equivalent to
about 30% of the flow through the largest chiller.
VARIABLE FLOW PRIMARY PARALLEL CHILLER
CONFIGURATION
Flow
Meter
EVAPORATOR SIDE
BYPASS VALVE
VARIABLE FLOW DISTRIBUTION SYSTEM
P = q x ∆T Designed to be
relatively constant
Load %
Therefore variation of flowrate is
proportional to cooling load
VARIABLE FLOW
100%
80%
60%
40%
20%
Flowrate %
20% 40% 60% 80% 100%
VARIABLE FLOW PRIMARY PARALLEL CHILLER
CONFIGURATION
4571 kw
3692 kw
2813 kw
1758 kw
879 kw
Flowrate %
33% 66% 100% 133% 166%
VARIABLE FLOW PRIMARY PARALLEL CHILLER
CONFIGURATION
EVAPORATOR SIDE
BTUH Meter
SEQUENCE OF OPERATION
START UP SEQUENCE
SEQUENCE OF OPERATION
Start/Stop Initiation
• Delay between start up sequence
60 SECONDS
(Allow for circulation)
60 SECONDS
(Operating time for most butterfly valve DN600 and below at 50Hz)
SAFETY FEATURE
Start/Stop Initiation
• Delay between start up sequence
• Using feedback from previous cycle (Example below)
HYDRONIC – COMPONENT’S CONTROL
A bypass control valve must be modulated open when the flow rate through
Built-in controller
the last
1. Opens & closes operating
compressor’s vanechiller is reduced to its minimum level, as indicated by the
2. Vary compressor’s speed chiller manufacturer
Differential pressure sensor is installed across the most distance (or 2/3)
flow circuits and a minimum pressure setpoint is determined for each
circuit.
Then as the pump speed is reduced, if the pressure falls below the required
setpoint in the circuit , further reduction of pump speed is inhibited
Δp
COOLING TOWER OPERATION
TS
TS
HEAT EXCHANGER
C C C C C
C C C C C
HEAT EXCHANGER
FLOW DIRECTION
C C C C C
C C C C C
HEAT EXCHANGER
TEMPERATURE REQUIREMENT
6°C ΔT = 1°C
7°C
C C C C C
C C C C C
12°C
13°C
HEAT EXCHANGER
CONTROL STRATEGIES
Controller
TS
C C C C C
C C C C C
ΔP
HEAT EXCHANGER
WHAT HAPPENS WHEN HYDRONIC SYSTEM IS NOT WELL
BALANCED?
C C C C C
C C C C C
HEAT EXCHANGER
Low ΔT Syndrome !
Power Output
100%
Coil Characteristic
75%
50%
example : velocity 1m/s
25%
6°C 0%
Flow
16°C
7°C 0% 25% 50% 75% 100%
C C C C C
C C C C C
ΔT = 3°C
12°C
18°C