77th STCom - Final
77th STCom - Final
This section will define the This section will define the Key decisions required and
progress, competency and Future plans Issues and made will be defined in this
capacity of our internal team challenges and overall section.
Project strategic direction.
4
Pending Items – Withdrawn by Abacus Tentative Date for completion of all items was
15th March 2021
6
Click icon to add picture
Action Taken:
Next Steps
8
1. TORs to be Finalized
Following highlighted Deliverable points need to fix before Project Signoffs with SysTech.
9
2. Progress on Performance Management System
10
2. Cost Negotiations on SAP SuccessFactors PMGM
11
Activities “Accomplished”
12
Accomplished Items
Sr. No Task Details Status
13
Accomplished Items by Internal Team
Sr. No Description Description
Status
14
Accomplished Items by Internal Team
Sr. No Description Description
Status
15
Accomplished Items by Internal Team
16-Oct-2020 8000000926 Required Grants Fund center option with Material Type ZNVM High In Process
Workflow for PR to PO (after complete PR release, information to Under testing
procurement department) High on qas 210 In Process
16
Accomplished Items by Internal Team
Completed and
To Initiate any change in SAP reports or business processes, The FSD (Functional
i Functional Specification Specification Document) has been introduced to track the following details, Live
Document (FSD)
a) Requirements Detail
b) Expected Results
c) Test Scenarios
ABAP Control Document will serve to document the Technical Specifications which Completed and
ii ABAP Control will keep tracks of SAP Programs Coding and Naming Conventions used by Live
Documentation developer in his/her development objects.
iii Reconciliation Procedure TOT for Payroll Processing were revised and reaffirmed between Finance, HDS and Completed and
Audit Teams. Live
17
Activities “In Process”
18
In Progress by Internal Team
I. System Upgrade
S.no Issue
Category Description Priority Status
System's landscape Upgrade activity was completed in Feb. but due to High Planned to Complete Testing
1 BASIS
some issues in reports the upgrade program was reverted back and till 18th April whereas
TEAM planned to test those SLcM reports in Clone Environment as has been upgrade date will be decided
created by Basis Team. based on the results of
observations.
19
In Progress by Internal Team
III. SAP Budget Variance Report
Priorit
S.no Issue Category Description
y Status
HDS & Finance Testing with Finance and Jobs Categories Creation High Planned to Complete Testing till May
1
Teams is in Progress. 2021
20
In Progress by Internal Team
V. Fiori Login List
21
In Progress by Internal Team
VI. SAP Fiori Activations
22
In Progress by Internal Team
VII. SAP Payroll Error Rectification Plan
23
In Progress by Internal Team
VII. SAP Payroll Error Rectification Plan
24
Key Decision
25
Key Decisions Required
1. Abacus - Settlement with Abacus (Closing of Issues were expected Till 15th March)
2. PMS – Solution Finalization
3. BIAFO – Should we go with them as we have Internal Team In-placed
4. EAM - Project Kickoff