Professional Documents
Culture Documents
Synthesis Section: Urea Plant
Synthesis Section: Urea Plant
SYNTHESIS SECTION
.H.P
Low Pressure
Scrubber
Carbamate
condenser
Reactor
L.P UREA
NH3 Rectifying PRODUCTION
Supply column
Evaporation
CO2
Compressor H.P
Stripper
Covered
2 12/08/2021
Basic Chemical Reactions
3 12/08/2021
Optimum reaction conditions
4 12/08/2021
Synthesis Main vessels
5 12/08/2021
H.P Carbamate Condenser
DESIGN SPICIFICATION
Tube side
Tube Design press.=163 Bar.
0
Tube Design Temp.=185 C.
No of tubes = 2353 tubes.
Shell side
Shell Design press.=9.2 Bar.
0
Shell Design Temp.=165 C.
6 12/08/2021
H.P Condenser Working Principle
Ammonia from H.P. ejectors reacts with stripped gas from H.P. stripper.
The ejector serves as a pump for bringing the carbamate solution from
the HP scrubber.
The pressure in steam drum is maintained such that only about 90%
reaction take place in condense. The rest CO2 & NH3 react in rector to
provide heat for 2nd reaction.
7 12/08/2021
Reactor
DESIGN SPICIFICATION
Height = 30.4 M.
No. Of Trays = 11 Trays.
Op. Pressure = 136.3 Bar.
Design Pressure = 160 Bar.
0
Op. Temperature = 183 C
0
Design Metal temp = 198 C
8 12/08/2021
Reactor Working Principle
The reactor (301-D) is provided with 11 sieve trays. The function of the
sieve trays is to ensure proper mixing of the reactants consistent with
the specified vessel volume & residence time requirements of the reactor.
9 12/08/2021
H.P Stripper
DESIGN SPICIFICATION
Tube side
Tube Design press.=165 Bar.
0
Tube Design Temp.=225 C.
No of tubes = 2650 tubes.
Shell side
Shell Design press.=31 Bar.
0
Shell Design Temp.=225 C.
10 12/08/2021
Stripper Working Principle
The liquid from the stripper is discharged to the recirculation section via a
level control let down valve .
11 12/08/2021
H.P Scrubber
DESIGN SPICIFICATION
12 12/08/2021
H.P Scrubber Working Principle
Reactor off-gas is entering the bottom via a gas distributor and gas is
condensed in contact with recycle carbamate solution.
The off gas is discharge through inert gas control valve to maintain the
pressure of the HP system.
13 12/08/2021
Kinetics Of Urea Synthesis Reaction
Operating Variables
14 12/08/2021
Temperature
15 12/08/2021
Pressure
At constant temperature,
conversion increases with pressure
up to the critical point where all
the vapor phase is converted to
liquid phase.
16 12/08/2021
N/C Mole Ratio
Excess NH3 above the stoichemetric mole ratio of 2 increases the rate of
the reaction.
17 12/08/2021
H2O/CO2
18 12/08/2021
Stripping
High temperature.
CO2 Stripping
19 12/08/2021
Corrosion & Passivation
Absence/Low O2 Contents.
High Temperature.
20 12/08/2021
Allowable corrosion rate
21 12/08/2021
Synthesis Start-Up & S/D
22 12/08/2021
Preparation for Synthesis Section
Start sea water and fresh cooling water to coolers and condensers.
23 12/08/2021
Steam Charging
Opening the 1" bypass of main block valve of MS , PC- 9901 5~10% and
drain valves open to charge steam.
Supply condensate to 310-F from 311-F to 10~15% level via the start up
line. Supply MS/ES to 310-F and 2 BarE pressure, close start up line
and open inert vent on stripper shell side.
Open 303-C inert vent valve and start to supply MP / Steam to 303-C
shell side by pass. pressure up to 2 BarE and level up to 50 %.
Check all steam traps of HP, MP, and LP. steam system.
24 12/08/2021
Heating Up of Reactor System
Close HC-9202 and HC-9203 keep 2" drain valve crack open which is
ahead of LC-9203 raise temperature to a minimum of 1250C
25 12/08/2021
Just before start up
Stop steam supply and disconnect line to reactor down comer and close
all synthesis drain valves. Confirm there is no level in the stripper, 302-C.
Close HC-9201 and fill up down comer of reactor by HP flush water pump,
about 10 minutes. Leave drain valves of reactor down comer and line CB-
9003-10". Open (auto seal).
Open HC-9209 and open the angle valve in the suction line of 301-L.
Switch CO2 vent from HV-3001 to PV-9204 slowly, and adjust FI-9104 at
16.5~17.5 KNM3/hr. DP over 302-D never exceeds 2-Bar E.
26 12/08/2021
SYNTHESIS COLD / INITIAL START UP
Switch CO2 vent from HV-3001 to PV-9204 slowly, and adjust FI-9104 at
16.5 ~ 17.5 KNM3/H
Adjust 320-J discharge pressure at 165~170 Bar and charge S.C. to 304-
C through 307J/JA. Discharge flush point (if 320-J not available for any
reason) put 307-J/JA to 304-C maintaining discharge valve opening only
3~4 turns and maintain the speed at 40~45 rpm.
Once 304-C overflow (TR-9054) starts changing, open HV-9206 and start
304-J/JA to 303-C via. discharge 2” by pass valve. Maintain NH 3 flow at
64~65 M3/Hr. If syn pressure > 100 barE, open main discharge valve and
close by pass valve.
At same time open HV-9204 and supply CO2 to stripper via the by-pass
on CO2 supply line. Control CO2 pressure at 130-140 BarE.
27 12/08/2021
Put PC-9204 on auto at 145 BarE. Synthesis Operator make sure PV-9204
is fully closed and then close PV-9204 upstream angle valve fully. If
bypass valve opened fully and CO2 pressure increase more than 140
BarE, start to open main angle valve and close bypass valve fully.
Open inert gas discharge valve of 304-C HC-9202 fully immediately after
charging NH3 and CO2.
28 12/08/2021
About 2 hours after charging NH3 and CO2 into synthesis, slowly open HC-
9901 (310-F blow off) to 70~75 % to prepare steam for 302-C.
When level of the reactor indicates a level, Field Operator fully open 302-
C liquid exit line angle valves (upstream of LV-9203) and close drain
valve in liquid line between 303-C and 301-D (auto seal), then flush
both lines by 320-J (HP flush water pump) and put LV-9203 on auto
position at 70 ~ 90%.
When level of the reactor indicates over 80%, close HV-9901 and then
slowly open HC-9201 to 55%. Hold and check FR-9902 ES. to 302-C
is at 55-60 KKG/hr.
At this time even if 301-D level is over 100%, adjusting HC- 9201 is not
required.
29 12/08/2021
Switch 307-J/JA speed controller from local to control room.
Reduce NH3 flow to about 45 M3/hr in order to keep NH3 / CO2 ratio as
normal operation.
After reactor 301-D level become to lower than 100%, increase plant load
by steps.
30 12/08/2021
Start-Up After Blocked In
Switch CO2 vent from HV-3001 to PV-9204 slowly, and adjust FI-9104 at
16.5 ~ 17.5 KNM3/H.
Introduce NH3 into suction of 304-J/JA and prepare NH 3 pump for start
up.
Open HC-9209 and open the angle valves in the suction line of 301-L.
Open drain valves of reactor down comer and line CB-9003-10"
(BETWEEN 303-C and 301-D) in order to maintain seal preventing
"REVERSAL" of CO2.
Open HC-9901 (310-F blow off) to 70~75% to prepare steam for 302-C.
make sure enough steam is available from Utility Plant. Open inert gas
discharge valve of 304-C HC-9202 completely, Immediately after
charging NH3 and CO2.
Put Carbamate pump 307-J/JA to HP scrubber and throttle discharge
valve to 50%.
Maintain 307-J/JA speed at minimum speed (45~50 RPM) on local. After
304-C overflows, indicated by change of over flow temperature TR-
9054.
31 12/08/2021
Open HV-9206 and both 304-J/JA discharge valves fully and then start up
304- J/JA.
Supply NH3 to 303-C adjusting NH3 flow to 64~65 M3/hr by control room
operator via. pump speed.
32 12/08/2021
At this time if 301-D level is over 100%, adjusting HC-9201 is not
required.
Slowly increase 310-F pressure to 18 Bar-E by PC-9904.
Open 307-J/JA discharge valve fully and switch 307-J/JA speed controller
switch from local to control room.
Reduce NH3 flow to about 45 M3/hr in order to keep NH3 / CO2 ratio as
normal operation.
Regulate synthesis pressure by means of setting 304-C conditioned
cooling water temperature at 800C. and low pressure steam drum
pressure (302-FA / FB). After reactor 301-D level was lower than
100%, increase plant load by steps.
Regulate the inert gas temperature to 110~140 0C. by slowly closing HC-
9202.
At same time open HV-9204 and supply CO2 to stripper via the by-pass
on CO2 supply line. Control CO2 pressure at 130~140 Bar E. Put PC-
9204 on auto at 145 Bar E. Synthesis Operator make sure PV-9204 is
fully closed and then close PV-9204 upstream angle valve fully. If
bypass valve opened fully and CO2 pressure increase more than 140
Bar E, start to open main angle valve and close bypass valve fully.
33 12/08/2021
Normal S/D (Blocking In)
If the shut down is a planned one, the capacity of the plant can be
reduced to 70% (CO2 flow 16.5~17.5 KNM3/H) gradually, to obtain
minimum levels in the NH3-water tank and urea storage tank.
Stop NH3 booster pump then stop HP NH3 pump 304-J/JA and close the
control valve HV-9206 at HP ejector suction and the NH 3 discharge
angle valve before the HP ejector
Switch HP Carbamate pump 307J /JA on circulation. Control level in level
tank LP Carbamate condenser by draining to NH 3 water tank, and
switch speed controller from control room to local and adjust speed to
45~50 RPM.
Increase process water flow FC-9708 to 12~14.4 M3/hr in order to dilute
contents of LP Carbamate condenser, 307C.
Close pressure controller PC-9904 of HP steam saturator and open steam
blow-off valve HC-9901 in order to reduce pressure to about 10 Bar-E.
Close level-control valve of reactor HC-9201 and stripper LC-9203 and
increase pressure in LP steam drum to about 5 ~5.3 BarE.
34 12/08/2021
After 310F, HP steam saturator pressure drops to 10 BarE, open PC-9204
and its upstream block valve and stop CO 2 feed to synthesis by closing
HC-9204 and its angle valve.
Close first block valve in liquid outlet line of stripper.
Start HP flush water pump and flush all HP lines as per procedures.
Close TC-9901 temperature control valve and Downstream block valves
of HP scrubber cooling water circuit. Keep water temperature 120-
1250C.
Close HC-9202 inert gas discharge valve, and its downstream angle
valve, if HV-9202 is passing.
If the re-start up is possible within 24 hours the reactor can be kept
blocked in. Otherwise the reactor system has to be drained.
35 12/08/2021
Thanks
36 12/08/2021