Professional Documents
Culture Documents
Chapter 6 - Crashing Program-3
Chapter 6 - Crashing Program-3
When we say that an activity will take a certain number of days or weeks, what we
really mean is this activity normally takes this many days or weeks. We could
make it take less time, but to do so would cost more money. Spending more
money to get something done more quickly is called “crashing.” There are various
methods of project crashing, and the decision to crash should only take place after
you’ve carefully analyzed all of the possible alternatives. The key is to attain
maximum decrease in schedule time with minimum cost.
“Project Crashing is reducing the total project time while minimizing the cost to do so”
- Multiple-shift work
- Extended workdays
- Increasing craftspeople
Actual cost
Simplistic assumption
Simplistic actual
Number of craftspeople
assumption of cost
2000 8
Activity cost (RM)
1000
10 20 1 8
As can be seen from the actual cost line (Figure 6.2), when
the number of resources is doubled, the cost is more than
doubled. This is due to the fact that:
Typically, the least expensive resources or most
productive are first applied, but any resources applied
later are increasingly expensive or less productive
1. Overtime wage rate are more than a normal rates for the same
job.
Decreased efficiency of labour due to working long hours.
Decreased efficiency of labour due to crowding.
Decreased production due to equipment breakdowns.
Higher wages due to urgency of work.
Example 6.0
Example 6.0
Solution:
Normal duration = 40 man-hours / 8 hours/day = 5days
Normal Cost = 40 hours x RM 10.00/hour = RM 400.00
In 4 days duration (Crashing by one day):
The carpenter will work 10 hours a day to finish the door in 4 days.
(8 regular hours + 2 hours overtime everyday.)
Crashed Cost = 4 days x 8 hour = 32 hours x RM10.00/hour = RM 320.00
+ 4 days x 2 hours overtime = 8 hours x RM 15.00/hour = RM120.00
= RM 440.00
The direct cost of activity A increased from RM400.00 to RM 440.00 by
decreasing activity duration (crashing) by one day.
Example 6.1
Solution 6.1
To determine the duration for installing the metal siding
with each crew, the total quantity is divided by the
estimated daily production, for example:
84400
64.9 days
1300
Table 6.2 Solution Example 6.1 – Estimated Cost with Various Crew Size
Crew Size Duration (days) Cost
Criteria for
selecting
Long activities to crash Labor
duration intensive
Cost
Slope CC NC
B ND CD
Crash Cost Crash point
(CC)
A
Normal Cost Normal point
(NC)
Duration
Crash time Normal time
(CD) (ND)
Cost
C
B Normal point
A
Duration
Example 6.2
Using the information in Example 6.1, we can graph the
duration-cost relationships and determine the cost slopes
between the points (which could be done by changing the size
of crews for increments of time while working on the
activity).
Cost (RM)
C
34,632 S2
B
33,936 S1
A
33,252
Duration (days)
37 42 51
Chapter 6 - Crashing Program
Crash Program 19
Solution 6.2
Example 6.3
8
3
12
B D
3 2
0 A 5 C 14 E 18
1 2 4 5
0 5 14 4 18
5 9
A 5 300 4 380 1 80 80 3*
B 3 240 2 340 1 100 100 4
C 9 630 7 780 2 150 75 2*
D 2 80 1 190 1 110 110 5
E 4 300 2 420 2 120 60 1*
*Critical Path : A – C - E
Solution 6.3
ACP
2110
PCP
Project Cost (RM)
1900
A (NORMAL POINT)
Duration (days)
13 18
Example 2
Normal
Duration Normal Cost Crash Duration Crash Cost
Activity (days) Predecessor (RM) (days) (RM)
A 5 - 400 3 600
B 4 - 400 3 520
C 2 A 300 1 450
Example 2
9,7
1 A 2 C 4 E 5 F 6
0 0 5 5 5 9 9 17 17
2 6 15 15 2
B D
4 4
5 5
5,4
Λ Λ
Normal Crash Slope
Normal Cost Crash Duration Cost Rank
Activity Duration Cost (RM/day)
(RM) Duration (days) (RM)
(days) (RM)
(days)
D 4 400 3 420 1 20 20 1
E 6 200 5 250 1 50 50 2
F 2 200 1 275 1 75 75 3
1 A 2 C 4 E 5 F 6
0 0 5 5 5 8 8 16 16
2 6 14 14 2
B D
4 3
5 5
1 A 2 C 4 E 5 F 6
0 0 5 5 5 8 8 15 15
2 5 13 13 2
B D
4 3
5 5
1 A 2 C 4 E 5 F 6
0 0 5 5 5 8 8 14 14
2 5 13 13 1
B D
4 3
5 5
1 A 2 C 4 E 5 F 6
0 0 3 3 4 7 7 13 13
2 5 12 12 1
B D
4 3
4 4
1 A 2 C 4 E 5 F 6
0 0 3 3 3 6 6 12 12
2 5 11 11 1
B D
3 3
3 3
1 A 2 C 4 E 5 F 6
0 0 3 3 3 6 6 12 12
1 5 11 11 1
B D
3 3
3 3
Solution 6.3
ACP
2515
PCP
2365
Project Cost (RM)
A (NORMAL POINT)
Duration (days)
12 13 17