Internship Presentation: By: Samer Sherif Kassem Electrical and Electronics Engineering Matric No: 9559
Internship Presentation: By: Samer Sherif Kassem Electrical and Electronics Engineering Matric No: 9559
ENPPI is recognized as an
international engineering,
“EPC” main contractual and
management contractor.
(Engineering, Procurement,
Construction)
1. Theoretical Studies
2. Pilot Project
3. Inspection on :
Cables
Motor Control Centre (MCC)
4. Site Visit
1. Theoretical Studies
1. Theoretical Studies
2. Pilot Project
3. Inspection on :
Cables
Motor Control Centre (MCC)
4. Site Visit
2. Pilot Project
“Fajr” project
1. Theoretical Studies
2. Pilot Project
3. Inspection on :
Cables
Motor Control Centre (MCC)
4. Site Visit
Inspection on Cables
Circuit Breaker
Terminal Strip
Transformer
Terminal Strip
Vertical bus
1. Theoretical Studies
2. Pilot Project
3. Inspection on :
Cables
Motor Control Centre (MCC)
4. Site Visit
4. Site visit to “Maa’dia” Fabrication yard,
Alexandria
Submarine Junction
Box
The Submarine
junction box (36kV)
are connected to the
utility plant through
submarine cables
Cable Tray
Figure 15 – Submarine Junction Box
Site visit to “Maa’dia” Fabrication yard,
Alexandria
Transformers
(Primary Side)
Transformers
(Secondary side)
Neutral Cable
(connected to ground resistance)
Indication lamps
Control Switches
Multi-function relays
Analog meters
Instrumentation and
weeks)
Control Dept.
• 30th August – 21st Dec (16
Instrumentation and Control System
(I & C)
Instrumentation is the branch of
engineering that deals with measurement
and control.
1. Theoretical Studies
2. Participation in projects
3. Site visit
1. Theoretical Studies
Process Measurements
Final Control Elements
Control Systems
1. Theoretical Studies
Process Measurements
Final Control Elements
Control Systems
Process Measurements
Level
Process
Measurements
on: Temperature
Flow
Pressure Measurement
Pressure Gauge
Pressure Transmitter
Level Gauge
Level Transmitter
SCADA
DCS SIS
Control
System
Distributed Control System (DCS)
Workstation Workstation
Data Highway
DCS SIS
Logic
Logic
Solver
Solver
Senso
Senso
rr
Final
FinalControl
ControlElement
Element
1. Theoretical Studies
2. Participate in projects.
3. Site visit
2. Participate in Projects
Issue Instrumentation Index for projects
1. Theoretical Studies
2. Participate in project
3. Site visit
3. GASCO site visit (1st Dec – 7thDec)
GASCO is a petroleum company in Amarya,
Alexandria.
Purpose of project is to maximize the products of C2
and C3.
Performed Activates on site
Control Room
Installation of cable trays inside Control
Room