Professional Documents
Culture Documents
Network Tech
Network Tech
Karen J Kirkby DJ 18 01
Monitor Corrective
Corrective
Monitor
Progress Action
Action
Progress
Reviews
Targets Complete
Complete
Costs Project
Project
The Project Manager
Abilities
* Organise & plan
* People Management
* Communication skills
* Problem solving
* Technical knowledge
* Enthusiasm & ability to motivate
* Focussed
* Ability to change
Network Analysis
* Project objectives clearly defined
1 2 3 4
Network Analysis
OK that was a simple example
Now move on to a more realistic case
Same principles
Break down problem into activities
What is the activity
What has to precede that activity
How long does the activity take
Don’t panic
Network Analysis
ACTIVITY DURATION PRECURSORS
A 4 -
B 3 -
C 6 A,B
D 1 B
E 7 D
F 2 C
G 5 C,E
H 8 E
J 4 G
K 5 F,G
L 6 J,H
M 3 L,K
A F K
4 2 5
C
6 G J
START
5 4
0
B D E
3 1 7 H L M FINISH
8 6 3 0
DURATION
NETWORK ANALYSIS
Earliest Earliest Earliest Start, Earliest Finish
Start Finish
0 4 10 12 16 21
A F K
4 2 5
4 10
C 11 16 16 20
0 0
6 G J
START
5 4
0
0 3 3 4 4 11
B D E 11 19 20 26 26 29 29 29
3 1 7 H L M FINISH
8 6 3 0
NETWORK ANALYSIS
Latest Start, Latest Finish
0 4 10 12 16 21
A F K
1 4 5 19 2 21 21 5 26
4 10
C 11 16 16 20
0 0
5 6 11 G J
START
11 5 16 16 4 20
0 0 0
0 3 3 4 4 11
B D E 11 19 20 26 26 29 29 29
0 3 3 3 1 4 4 7 11 H L M FINISH
12 8 20 20 6 26 26 3 29 29 0 29
Latest Latest
Start Finish
Project Management
Karen J Kirkby DJ 18 01
4 10
C 11 16 16 20
0 0
5 6 11 G J
START
11 5 16 16 4 20
0 0 0
0 3 3 4 4 11
B D E 11 19 20 26 26 29 29 29
0 3 3 3 1 4 4 7 11 H L M FINISH
12 8 20 20 6 26 26 3 29 29 0 29
Critical Path ES =LS EF=LF
shown as a thick line
FLOAT = LF-duration-ES
If duration of activities on critical path increases then
time required for project increases
NETWORK ANALYSIS
Float 0 4 10 12 16 21
A F K
1 4 5 19 2 21 21 5 26
4 10
C 11 16 16 20
0 0
5 6 11 G J
START
11 5 16 16 4 20
0 0 0
0 3 3 4 4 11
B D E 11 19 20 26 26 29 29 29
0 3 3 3 1 4 4 7 11 H L M FINISH
12 8 20 20 6 26 26 3 29 29 0 29
FLOAT = LF-duration-ES
ACTIVITY H 20-8-11 = 1 = FLOAT
ACTIVITY A B C D E F G H J K L M
FLOAT 1 0 1 0 0 9 0 1 0 5 0 0
Critical path when float = 0
NETWORK ANALYSIS
Activity on node diagrams in which finish to start
(F-S) links have a duration will now be considered
Nature and duration of link shown on arrow
(F-S) Activity 2 cannot start until 1 week after
completion of activity 1.
Activity 3 cannot start until 2 weeks after completion of
activity 2
1 F-S (1) 2 F-S (2) 3
NETWORK ANALYSIS
Activity Duration Precursor Link L duration
A 4 -
B 24 A F-S 0
C start 6 weeks
Can 12 after the startBof B 4+6
S-S= 106
F-F 3
0 4 F-S (0) 4 28 F-F (3) Critical Path
A B
0 4 4 4 24 28
10 31
S-S (6)
C
19 12 31
Why Plan?
What Plan
Project Manager/ Leader
Network Analysis
Critical Path
Gantt charts
PERT