Gem Residence Projected Schedule 02k As of August 20,2021
Gem Residence Projected Schedule 02k As of August 20,2021
PODIUM STRUCTURE
3
4 5
PODIUM STRUCTURE
1 2 6
PROJECT SCHEDULE PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021
Legend:
Ahead
Delayed
ACTUAL ACCOMPLISHMENTS PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021
TANK ROOMS
TANK ROOM
Sequence Planned Planned Start Planned Finish Actual Actual %
Duration Start Finish Complete
Tank Rooms
Tank Rooms 132 days 24-Mar-21 6-Sep-21
Sewage Treatment Plant
Sewerage Treatment Plant 132 days 24-Mar-21 6-Sep-21
1st Level (Base slab to upper level) 132 days 24-Mar-21 6-Sep-21 24-Mar-21
STP/1st lvl: base slab 6 days 24-Mar-21 29-Mar-21 24-Mar-21 29-Mar-21 100.00%
STP/1st lvl: RC wall seq. 1 12 days 30-Mar-21 15-Apr-21 30-Mar-21 15-Apr-21 100.00%
STP/1st lvl: RC wall seq. 1a 39 days 23-Apr-21 9-Jun-21 23-Apr-21 9-Jun-21 100.00%
STP/1st lvl: RC wall seq. 1b 29 days 11-May-21 15-Jun-21 11-May-21 15-Jun-21 100.00%
STP/1st lvl: RC wall seq. 3 (by others) 6 days 23-Aug-21 28-Aug-21
STP/1st lvl: RC wall seq. 4 (by others) 6 days 23-Aug-21 28-Aug-21
STP/1st lvl: beam (catwalk) (balance) 106 days 28-Apr-21 6-Sep-21 28-Apr-21 69.70%
STP/1st lvl: slab (catwalk) (balance) 89 days 20-May-21 6-Sep-21 20-May-21 27.00%
2nd Level (Upper level to ground floor) 58 days 11-Jun-21 20-Aug-21
STP/2nd lvl: beams (balance) 58 days 11-Jun-21 20-Aug-21 11-Jun-21 96.33%
STP/2nd lvl: slab (balance) 57 days 14-Jun-21 20-Aug-21 14-Jun-21 96.33%
Fire Reserve Tank
Fire Reserve Tank 105 days 6-Apr-21 12-Aug-21
1st Level (Base slab to upper level) 105 days 6-Apr-21 12-Aug-21 6-Apr-21 12-Aug-21
FR Tank 1st lvl: base slab 14 days 6-Apr-21 20-Apr-21 6-Apr-21 20-Apr-21 100.00%
FR Tank 1st lvl: RC Wall seq. 2 (1st lift) 15 days 23-Apr-21 10-May-21 23-Apr-21 10-May-21 100.00%
FR Tank 1st lvl: RC Wall seq. 2 (2nd lift) 10 days 10-Jun-21 22-Jun-21 10-Jun-21 22-Jun-21 100.00%
FR Tank 1st lvl: slab 6 days 24-Jun-21 30-Jun-21 24-Jun-21 30-Jun-21 100.00%
FR Tank 2nd lvl: RC Wall (balance) 30 days 7-Jul-21 12-Aug-21 7-Jul-21 12-Aug-21 100.00%
Cistern & Detention Tanks
Cistern & Detention Tanks 80 days 29-Mar-21 7-Jul-21
Cistern & Detention Tank: base slab 4 days 29-Mar-21 5-Apr-21 29-Mar-21 5-Apr-21 100.00%
Cistern & Detention Tank: RC wall seq. 2A 42 days 6-Apr-21 20-May-21 6-Apr-21 20-May-21 100.00%
Cistern & Detention Tank: RC wall seq. 3A 11 days 6-Apr-21 20-Apr-21 6-Apr-21 20-Apr-21 100.00%
Cistern & Detention Tank: RC wall seq. 4a 8 days 14-Apr-21 27-Apr-21 14-Apr-21 27-Apr-21 100.00%
Cistern & Detention Tank: RC wall seq. 4b 8 days 24-Apr-21 4-May-21 24-Apr-21 4-May-21 100.00%
Cistern & Detention Tank: RC wall seq. 4c (1st lift) 19 days 7-May-21 29-May-21 7-May-21 29-May-21 100.00%
Cistern & Detention Tank: RC wall seq. 4c (2nd lift) 6 days 29-May-21 4-Jun-21 29-May-21 4-Jun-21 100.00%
Cistern & Detention Tank: beams 27 days 28-May-21 7-Jul-21 28-May-21 7-Jul-21 100.00%
Cistern & Detention Tank: slab 32 days 29-May-21 7-Jul-21 29-May-21 7-Jul-21 100.00%
Elevator pit
Wall 19 days 3-Jul-21 27-Jul-21 3-Jul-21 27-Jul-21 100.00% NOTE: SEQUENCE 3 & 4 IN SEWERAGE TREATMENT PLANT– NOT BY
Beam/Slab 5 days 20-Aug-21 26-Aug-21 BBPI (VERIFY W/ SIR RAFAEL)
ACTUAL ACCOMPLISHMENTS PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021
Backfilling
B&C (ftg to FTB): seq.2 40 days 30-Mar-21 15-May-21 30-Mar-21 15-May-21 100.00%
B&C (ftg to FTB): seq.3 72 days 20-May-21 14-Aug-21 20-May-21 14-Aug-21 100.00%
B&C (ftg to FTB): seq.6 100 days 17-May-21 15-Sep-21 17-May-21 19.57%
ACTUAL ACCOMPLISHMENTS PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021
GROUND BEAM
GROUND BEAM
Planned Planned Actual Actual %
Sequence Duration Planned Start Finish Start Finish Complete
GROUND BEAM
Ground Beam 115 days 30-Apr-21 18-Sep-21
GF/ground beam: seq.1 11 days 30-Apr-21 14-May-21 30-Apr-21 14-May-21 100.00%
GF/ground beam: seq.2 39 days 19-May-21 3-Jul-21 19-May-21 3-Jul-21 100.00%
GF/ground beam: seq.3 22 days 8-Jun-21 3-Jul-21 8-Jun-21 3-Jul-21 100.00%
GF/ground beam: seq.4 3 days 28-Jun-21 31-Aug-21 28-Jun-21 23.67%
GF/ground beam: seq.5 3 days 14-Jun-21 6-Sep-21 14-Jun-21 24.00%
GF/ground beam: seq.6 3 days 16-Sep-21 18-Sep-21
PROJECT SCHEDULE PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021
B&C (ftg to FTB): seq.1 41 days 17-May-21 3-Jul-21 17-May-21 3-Jul-21 100.00%
B&C (ftg to FTB): seq.2 10 days 14-Jun-21 8-Jul-21 14-Jun-21 8-Jul-21 100.00%
B&C (ftg to FTB): seq.3 36 days 28-Jun-21 18-Aug-21 28-Jun-21 95.00%
B&C (ftg to FTB): seq.4 1 day 2-Sep-21 2-Sep-21
B&C (ftg to FTB): seq.5 1 day 28-Jun-21 8-Sep-21 28-Jun-21 5.00%
B&C (ftg to FTB): seq.6 1 day 21-Sep-21 21-Sep-21
ACTUAL ACCOMPLISHMENTS PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021
SOG/SLAB
SOG/SLAB
Slab