GEM RESIDENCES

PROJECTED SCHEDULE REV 02K


AS OF AUGUST 20, 2021 (FROM GROUND. FLR.
TO 3 R D FLR. & PODIUM STRUCTURE)
ACTUAL ACCOMPLISHMENTS
PODIUM STRUCTURE (SHEARWALL)

SW1 & SW2 SW1 & SW2


SW3

PODIUM STRUCTURE

SW4 & SW5


ACTUAL ACCOMPLISHMENTS
PODIUM STRUCTURE

3
4 5
PODIUM STRUCTURE

1 2 6
PROJECT SCHEDULE PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021

KEY MILESTONE BETWEEN NOW AND MAY THAT NEED TO BE MET


CONSTRUCTION ACTUAL/REVISED
MILESTONES PLANNED DATES

Start of Excavation 23-Jun-20 A


First Concrete Pouring 21-Oct-20 D
Erection of Tower Crane 1 (MF2) 01-Feb-21D
Erection of Tower Crane 2 (MF1) 30-Nov-20 D
Start of Foundation 6-Oct-20

Tank Rooms Completion 6-Sep-21

Backfilling Completion 21-Sep-21

Ground beam/ slab Completion 30-Sep-21

Grnd Flr- 2nd Flr (2F) Completion 14-Oct-21

2nd Flr – 3rd Flr (3F) Completion 28-Oct-21

Legend:
Ahead
Delayed
ACTUAL ACCOMPLISHMENTS PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021

TANK ROOMS
TANK ROOM
Sequence Planned Planned Start Planned Finish Actual Actual %
Duration Start Finish Complete
Tank Rooms
Tank Rooms 132 days 24-Mar-21 6-Sep-21
Sewage Treatment Plant
Sewerage Treatment Plant 132 days 24-Mar-21 6-Sep-21
1st Level (Base slab to upper level) 132 days 24-Mar-21 6-Sep-21 24-Mar-21    
STP/1st lvl: base slab 6 days 24-Mar-21 29-Mar-21 24-Mar-21 29-Mar-21 100.00%
STP/1st lvl: RC wall seq. 1 12 days 30-Mar-21 15-Apr-21 30-Mar-21 15-Apr-21 100.00%
STP/1st lvl: RC wall seq. 1a 39 days 23-Apr-21 9-Jun-21 23-Apr-21 9-Jun-21 100.00%
STP/1st lvl: RC wall seq. 1b 29 days 11-May-21 15-Jun-21 11-May-21 15-Jun-21 100.00%
STP/1st lvl: RC wall seq. 3 (by others) 6 days 23-Aug-21 28-Aug-21      
STP/1st lvl: RC wall seq. 4 (by others) 6 days 23-Aug-21 28-Aug-21      
STP/1st lvl: beam (catwalk) (balance) 106 days 28-Apr-21 6-Sep-21 28-Apr-21   69.70%
STP/1st lvl: slab (catwalk) (balance) 89 days 20-May-21 6-Sep-21 20-May-21   27.00%
2nd Level (Upper level to ground floor) 58 days 11-Jun-21 20-Aug-21      
STP/2nd lvl: beams (balance) 58 days 11-Jun-21 20-Aug-21 11-Jun-21   96.33%
STP/2nd lvl: slab (balance) 57 days 14-Jun-21 20-Aug-21 14-Jun-21   96.33%
Fire Reserve Tank
Fire Reserve Tank 105 days 6-Apr-21 12-Aug-21 
1st Level (Base slab to upper level) 105 days 6-Apr-21 12-Aug-21  6-Apr-21 12-Aug-21   
FR Tank 1st lvl: base slab 14 days 6-Apr-21 20-Apr-21 6-Apr-21 20-Apr-21 100.00%
FR Tank 1st lvl: RC Wall seq. 2 (1st lift) 15 days 23-Apr-21 10-May-21 23-Apr-21 10-May-21 100.00%
FR Tank 1st lvl: RC Wall seq. 2 (2nd lift) 10 days 10-Jun-21 22-Jun-21 10-Jun-21 22-Jun-21 100.00%
FR Tank 1st lvl: slab 6 days 24-Jun-21 30-Jun-21 24-Jun-21 30-Jun-21 100.00%
FR Tank 2nd lvl: RC Wall (balance) 30 days 7-Jul-21 12-Aug-21 7-Jul-21 12-Aug-21 100.00%
Cistern & Detention Tanks
Cistern & Detention Tanks 80 days 29-Mar-21 7-Jul-21
Cistern & Detention Tank: base slab 4 days 29-Mar-21 5-Apr-21 29-Mar-21 5-Apr-21 100.00%
Cistern & Detention Tank: RC wall seq. 2A 42 days 6-Apr-21 20-May-21 6-Apr-21 20-May-21 100.00%
Cistern & Detention Tank: RC wall seq. 3A 11 days 6-Apr-21 20-Apr-21 6-Apr-21 20-Apr-21 100.00%
Cistern & Detention Tank: RC wall seq. 4a 8 days 14-Apr-21 27-Apr-21 14-Apr-21 27-Apr-21 100.00%
Cistern & Detention Tank: RC wall seq. 4b 8 days 24-Apr-21 4-May-21 24-Apr-21 4-May-21 100.00%
Cistern & Detention Tank: RC wall seq. 4c (1st lift) 19 days 7-May-21 29-May-21 7-May-21 29-May-21 100.00%
Cistern & Detention Tank: RC wall seq. 4c (2nd lift) 6 days 29-May-21 4-Jun-21 29-May-21 4-Jun-21 100.00%
Cistern & Detention Tank: beams 27 days 28-May-21 7-Jul-21 28-May-21 7-Jul-21 100.00%
Cistern & Detention Tank: slab 32 days 29-May-21 7-Jul-21 29-May-21 7-Jul-21 100.00%
Elevator pit
Wall 19 days 3-Jul-21 27-Jul-21 3-Jul-21 27-Jul-21 100.00% NOTE: SEQUENCE 3 & 4 IN SEWERAGE TREATMENT PLANT– NOT BY
Beam/Slab 5 days 20-Aug-21 26-Aug-21       BBPI (VERIFY W/ SIR RAFAEL)
ACTUAL ACCOMPLISHMENTS PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021

BACKFILLING & COMPACTION (Summary Schedule)

BACKFILLING & COMPACTION(FOOTING TO BOTTOM OF FTB)


Planned Planned Actual Actual %
Sequence Planned Start
Duration Finish Start Finish Complete

Backfilling

Backfilling & Compaction


140 days 24-Mar-21 15-Sep-21
(Footing to Bottom of FTB)
     
B&C (ftg to FTB): seq.1 37 days 24-Mar-21 5-May-21 24-Mar-21 5-May-21 100.00%

B&C (ftg to FTB): seq.2 40 days 30-Mar-21 15-May-21 30-Mar-21 15-May-21 100.00%

B&C (ftg to FTB): seq.3 72 days 20-May-21 14-Aug-21 20-May-21 14-Aug-21  100.00%

B&C (ftg to FTB): seq.4 81 days 5-May-21 26-Aug-21 5-May-21   52.00%

B&C (ftg to FTB): seq.5 95 days 8-May-21 2-Sep-21 8-May-21   39.40%

B&C (ftg to FTB): seq.6 100 days 17-May-21 15-Sep-21 17-May-21   19.57%
ACTUAL ACCOMPLISHMENTS PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021

GROUND BEAM

GROUND BEAM
Planned Planned Actual Actual %
Sequence Duration Planned Start Finish Start Finish Complete
GROUND BEAM
Ground Beam 115 days 30-Apr-21 18-Sep-21
GF/ground beam: seq.1 11 days 30-Apr-21 14-May-21 30-Apr-21 14-May-21 100.00%
GF/ground beam: seq.2 39 days 19-May-21 3-Jul-21 19-May-21 3-Jul-21 100.00%
GF/ground beam: seq.3 22 days 8-Jun-21 3-Jul-21 8-Jun-21 3-Jul-21 100.00%
GF/ground beam: seq.4 3 days 28-Jun-21 31-Aug-21 28-Jun-21   23.67%
GF/ground beam: seq.5 3 days 14-Jun-21 6-Sep-21 14-Jun-21   24.00%
GF/ground beam: seq.6 3 days 16-Sep-21 18-Sep-21      
PROJECT SCHEDULE PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021

COMPLETION OF EARTHWORKS (BACKFILLING & COMPACTION)

BACKFILLING & COMPACTION (FROM BOTTOM OF FTB UP TO BOTTOM OF SOG)


Planned Actual Actual %
Sequence Duration Planned Start Planned Finish Start Finish Complete

BACKFILLING AND COMPACTION (FROM BOTTOM OF FTB UP TO BOTTOM OF SOG)

Backfilling & Compaction (From


Bottom of FTB to bottom of SOG) 105 days 17-May-21 21-Sep-21

B&C (ftg to FTB): seq.1 41 days 17-May-21 3-Jul-21 17-May-21 3-Jul-21 100.00%

B&C (ftg to FTB): seq.2 10 days 14-Jun-21 8-Jul-21 14-Jun-21 8-Jul-21 100.00%
B&C (ftg to FTB): seq.3 36 days 28-Jun-21 18-Aug-21 28-Jun-21   95.00%
B&C (ftg to FTB): seq.4 1 day 2-Sep-21 2-Sep-21      
B&C (ftg to FTB): seq.5 1 day 28-Jun-21 8-Sep-21 28-Jun-21   5.00%
B&C (ftg to FTB): seq.6 1 day 21-Sep-21 21-Sep-21      
ACTUAL ACCOMPLISHMENTS PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021

SOG/SLAB

SOG/SLAB

Sequence Planned Planned Start Planned Actual Actual %


Duration Finish Start Finish Complete

Slab

Slab 86 days 18-Jun-21 30-Sep-21 18-Jun-21

Soil poisoning 78 days 18-Jun-21 21-Sep-21 18-Jun-21


Polyethylene sheet 82 days 19-Jun-21 27-Sep-21 19-Jun-21
laying/damp proofing
GF/SOG: seq.1 (balanced) 3 days 8-Jul-21 10-Jul-21 18-Jun-21 10-Jul-21 100.00%

rebar/embedment installation 3 days 8-Jul-21 10-Jul-21 8-Jul-21 10-Jul-21 100.00%

side form installation 3 days 8-Jul-21 10-Jul-21 8-Jul-21 10-Jul-21 100.00%

concrete 1 days 10-Jul-21 10-Jul-21 10-Jul-21 10-Jul-21 100.00%

GF/SOG: seq.2 4 days 7-Jul-21 10-Jul-21 7-Jul-21 10-Jul-21 100.00%


GF/SOG: seq.3 40 days 10-Jul-21 28-Aug-21 10-Jul-21   80.00%
GF/SOG: seq.4 3 days 1-Sep-21 3-Sep-21      
GF/SOG: seq.5 3 days 10-Jul-21 17-Sep-21 10-Jul-21   5.00%
GF/SOG: seq.6 3 days 28-Sep-21 30-Sep-21      
ACTUAL ACCOMPLISHMENTS PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021

GRND FLR.-2ND FLR. (2F)


Grnd Flr- 2nd Flr (2F)
Sequence Planned Planned Start Planned Finish Actual Actual %
Duration Start Finish Complete
Grnd Flr- 2nd Flr (2F)
Grnd Flr- 2nd Flr (2F) 134 days 5-May-21 14-Oct-21
Sequence 1 92 days 5-May-21 25-Aug-21
Column 46 days 5-May-21 29-Jun-21 05-May-21 29-Jun-21 100.00%
PC Wall Installation (balance) 35 days 2-Jul-21 24-Aug-21 02-Jul-21   57.89%
Beam (balance) 36 days 26-Jun-21 25-Aug-21 26-Jun-21   98.33%
Slab (balance) 27 days 24-Jul-21 25-Aug-21 28-Jun-21   98.33%
Sequence 2 75 days 21-May-21 19-Aug-21      
Column 58 days 21-May-21 30-Jul-21 21-May-21 30-Jul-21 100.00%
Shear wall 47 days 15-May-21 15-Jul-21 15-May-21 15-Jul-21 100.00%
Beam (balance) 29 days 15-Jul-21 19-Aug-21 15-Jul-21 19-Aug-21 100.00%
Slab (balance) 18 days 28-Jul-21 19-Aug-21 28-Jul-21 19-Aug-21 100.00%
Sequence 3 69 days 29-Jun-21 21-Sep-21      
Column (balance) 42 days 29-Jun-21 18-Aug-21 29-Jun-21   83.89%
Shear wall (balance) 35 days 14-Jun-21 10-Aug-21 14-Jun-21 10-Aug-21 100.00%
PC Wall Installation 4 days 25-Aug-21 28-Aug-21
Beam (balance) 9 days 26-Jul-21 21-Sep-21 26-Jul-21   12.67%
Slab (balance) 5 days 16-Sep-21 21-Sep-21 02-Aug-21   3.28%
Sequence 4 55 days 14-Jul-21 20-Sep-21      
Column (balance) 46 days 14-Jul-21 9-Sep-21 14-Jul-21   60.00%
Shear wall (balance) 27 days 8-Jun-21 16-Aug-21 08-Jun-21   62.33%
PC Wall Installation 4 days 4-Sep-21 8-Sep-21
Ramp 6 days 4-Sep-21 10-Sep-21 10-Aug-21 11.00%
Beam 9 days 10-Sep-21 20-Sep-21
Slab 6 days 14-Sep-21 20-Sep-21
Sequence 5 43 days 26-Jul-21 15-Sep-21      
Column (balance) 8 days 26-Jul-21 3-Aug-21 26-Jul-21 3-Aug-21  100%
Shear wall (balance) 24 days 21-Jun-21 31-Aug-21 21-Jun-21   37.33%
Beam 9 days 6-Sep-21 15-Sep-21
Slab 7 days 8-Sep-21 15-Sep-21
Sequence 6 16 days 27-Sep-21 14-Oct-21      
ACTUAL ACCOMPLISHMEN PROJECTED SCHEDULE REV 02K – AUGUST 20,
2021

2ND FLR. – 3RD FLR. (3F)


2nd Flr. – 3rd Flr. (3F)
Planned Actual Actual %
Sequence Duration Planned Start Planned Finish Start Finish Complete
2nd Flr - 3rd Flr (3F)
2nd Flr- 3rd Flr (2F) 58 days 20-Aug-21 28-Oct-21
Sequence 1 12 days 26-Aug-21 9-Sep-21
Column 6 days 26-Aug-21 2-Sep-21
PC Wall Installation 4 days 26-Aug-21 31-Aug-21
Beam 9 days 31-Aug-21 9-Sep-21
Slab 7 days 2-Sep-21 9-Sep-21
Sequence 2 12 days 20-Aug-21 4-Sep-21
Column 6 days 20-Aug-21 27-Aug-21
Shear wall 13 days 28-Jul-21 11-Aug-21 28-Jul-21   51.33%
PC Wall Installation 4 days 20-Aug-21 25-Aug-21
Ramp 9 days 20-Aug-21 1-Sep-21
Beam 9 days 25-Aug-21 4-Sep-21
Slab 7 days 27-Aug-21 4-Sep-21
Sequence 3 16 days 22-Sep-21 9-Oct-21
Column 8 days 22-Sep-21 30-Sep-21
Shear wall 10 days 31-Aug-21 10-Sep-21
PC Wall Installation 4 days 27-Sep-21 30-Sep-21
Beam 9 days 30-Sep-21 9-Oct-21
Slab 7 days 2-Oct-21 9-Oct-21
Sequence 4 12 days 21-Sep-21 4-Oct-21
Column 6 days 21-Sep-21 27-Sep-21
Shear wall 10 days 17-Aug-21 28-Aug-21
PC Wall Installation 4 days 21-Sep-21 24-Sep-21
Beam 9 days 24-Sep-21 4-Oct-21
Slab 7 days 27-Sep-21 4-Oct-21
Sequence 5 12 days 16-Sep-21 29-Sep-21
Column 6 days 16-Sep-21 22-Sep-21
Shear wall 10 days 1-Sep-21 11-Sep-21
Beam 9 days 20-Sep-21 29-Sep-21
Slab 7 days 22-Sep-21 29-Sep-21
Sequence 6 12 days 15-Oct-21 28-Oct-21      