Professional Documents
Culture Documents
Project Planning 3 Cost Estimating & Budgeting: Heru Andraiko
Project Planning 3 Cost Estimating & Budgeting: Heru Andraiko
Time
Cost
Quality
Human Resource
Communication
Risk
Procurement
Integration
MENGAPA PERLU PROJECT
COST BUDGETING DALAM
COST PLANNING ?
Untuk memastikan bahwa perencanaan proyek sudah
mencakup :
•Estimasi biaya untuk setiap resource
•Pengalokasian estimasi biaya setiap resource yang
dibutuhkan oleh setiap work item
RZH 2008
PLANNING FOR COST BUDGETING
• Cost Estimating
• Cost Budgeting
RZH 2008
Klasifikasi Resources
RZH 2008
Contoh Project : Pembuatan Parit
Activity Resource Estimating
Tipe Resource Quantity
Indirect labour 6 orang
Direct labour 50 orang
Selokan precast dan tutupnya 300 m
Semen 100 kantong
Pasir & kerikil 60 m3
Alat gali tanah (manual) 16 set
Alat setting selokan precast 2 set
Alat angkut tanah (manual) 10 set
Alat angkut dan aduk concrete 3 set
RZH 2008
Cost Estimating
INPUTS TOOLS & OUTPUTS
TECHNIQUES
1. Analogous Estimating
1. WBS 1. Activity cost
2. Parametric Estimating
estimates
2. Enterprise 3. Bottom-up Estimating
environmental 2. Activity cost
4. Determine resource
factors cost rates
estimate
supporting detail
3. Organizational 5. Project management
process assets software 3. Requested
6. Vendor bid analysis changes
4. Project scope
statement 7. Reserve analysis 4. Cost Management
8. Cost of quality Plan
5. WBS dictionary
6. Project
management plan
RZH 2005
Contoh Project : Pembuatan Parit
Cost Estimating
20% Preliminary
10% Assembly
5% Detailed
Time
5min 1hour 1day 3 weeks
RZH 2008
Estimation Accuracy vs. Time
[Boehm et al., "Cost Models for Future Software Life Cycle Processes: COCOMO 2.0« , Annals of Software Engineering, 1995]
1. Preliminary Estimate
“Order of Magnitude”
• A cost prediction based solely on size and/or
capacity of a proposed project.
• Before any engineering or design is completed.
• Rely on broad data from already executed
similar project
relate cost to the main capacity/size parameter
number of beds in hospital
square feet of office space
number of students in school
• Purpose:
1. Ranking alternatives
2. Evaluate economics and financial feasibility
3. As a check on more detailed estimates
Uses
1. To update known historical costs for new estimates
2. To estimate replacement cost for specific assets
3. To provide for contract escalation
Limitations
1. They represent composite data, average of many projects.
2. They fail to recognize technological changes.
3. There is a reporting time log.
Prof Awad S. Hanna
To update old cost information to current date
Proposed Size
Size Factor = Comparison Size
Multipliers 1.0 3 6
1.0 23
1.0 11
1.153
1.0 9 3
1.0 43
0 .7
0 .8
0 .9
0 .725
0 .8 8 1
0 .9 10
0 .8 0 7
0 .8 75
0 .9 3 9
1.0 0 0 1.0 0 0 1.0 1.0 0 0 1.0 0 0
0 .9 9 1 0 .9 6 3 1.1 1.0 9 0 1.0 59
0 .9 8 2 0 .9 3 0 1.2 1.178 1.116
0 .9 74 0 .9 0 0 1.3 1.26 6 1.170
0 .9 6 7 0 .8 74 1.4 1.3 54 1.224
0 .9 6 0 0 .8 50 1.5 1.440 1.275
0 .9 54 0 .8 29 1.6 1.527 1.3 26
0 .9 48 0 .8 0 9 1.7 1.6 12 1.3 75
0 .9 43 0 .78 0 1.8 1.6 9 7 1.423
0 .9 3 8 0 .774 1.9 1.78 2 1.470
0 .9 3 3 0 .758 2.0 1.8 6 6 1.516
0 .9 28 0 .743 2.1 1.9 50 1.56 1
0 .9 24 0 .73 0 2.2 2.0 3 3 1.6 0 5
0 .9 20 0 .717 2.3 2.116 1.6 48
0 .9 16 0 .70 5 2.4 2.19 9 1.6 9 1
0 .9 12 0 .6 9 3 2.5 2.28 1 1.73 3
0 .9 0 9 0 .6 8 2 2.6 2.3 6 3 1.774
0 .9 0 5 0 .8 72 2.7 2.445 1.8 15
0 .9 0 2 0 .6 6 2 2.8 2.526 1.8 55
0 .8 9 9 0 .6 53 2.9 2.6 0 7 1.8 9 4
0 .8 9 6 0 .6 44 3 .0 2.6 8 8 1.9 3 3
0 .8 9 3 0 .6 3 6 3 .1 2.76 8 1.9 72
0 .8 9 0 0 .6 28 3 .2 2.8 49 2.0 10
0 .8 8 7 0 .6 20 3 .3 2.9 29 2.0 47
0 .8 8 5 0 .6 13 3 .4 3 .0 0 8 2.0 8 4
0 .8 8 2 0 .6 0 6 3 .5 3 .0 8 8 2.121
0 .8 8 0 0 .59 9 3 .6 3 .16 7 2.157
0 .8 77 0 .59 3 3 .7 3 .246 2.19 2
0 .8 75 0 .58 6 3 .8 3 .3 25 2.228
0 .8 73 0 .58 0 3 .9 3 .40 4 2.26 3
0 .8 71 0 .574 4.0 3 .48 2 2.29 7
2.000
Unit Price Cost Multiplier
1.500
(UCM)
1.000
0.500
0.000
0.1 1.0 10.0
Size Factor
4.000
3.500
3.000
2.500
(TCM)
2.000
1.500
1.000
0.500
0.000
0.1 1.0 10.0
Size Factor
Bldg B
Bldg A
Area =1500ft2
30’
40’
Area = 15ooft2
Perimeter = 150ft
Perimeter = 160ft
10’
15’ 15’
Wall height = $10 x 160 x 10 = $16,000
= $10.00 of floor area
Bldg. A
Wall cost = $10 x 160 x 10 = $16,000
= $10.00 of floor area
Bldg B
Wall cost = $10 x 180 x 10 = $18,000
= $11.25 of floor area
5. "Learning Effect"
• COCOMO: E = a + bNc
– When C < 1, we get an economy of scale
» Common for factories
– For software, C is usually > 1…
Principles of Effective Cost
Estimation
•Principle 4: Be sure to account for differences
when extrapolating from other projects.
– Different software developers
– Different development processes and maturity levels
– Different types of customers and users
– Different schedule demands
– Different technology
– Different technical complexity of the requirements
– Different domains
– Different levels of requirement stability
Principles of Effective Cost
Estimation
•Principle 5: Anticipate the worst case and plan
for contingencies.
RZH 2008
Contoh Project : Pembuatan Parit
Cost Budgeting
Rupiah
30.000.000
15.000.000
0 8 15
RZH 2008
Waktu (hari)
Group Discussion
• Menggunakan data Proyek Pembuatan Parit
yang ada di dalam bahan presentasi
Schedule Development dan Cost Estimating
& Budgeting ini, buatlah cost baseline
proyek tersebut. Diskusikan dan tulislah:
1. Asumsi-asumsi yang perlu diambil agar cost
baseline dapat dibentuk.
2. Langkah-langkah kerja untuk menghasilkan
cost baseline
RZH 2008
Inter-korelasi dalam Cost Management
Planning Phase
Resource Schedule
Estimating Development
OPA, EEF,
PMP
RZH 2008
WRAP UP
RZH 2008
Charter PLANNING STAGE Scope Mgt
Activity
Activity Schedule
Resource Project
Definition Development
Estimating Plan
Activity
Duration
OPA, EEF, Estimating Cost
PMP Budgeting
Resource
Estimating
Schedule
Development
Cost Mgt
Scope Scope
definition Create WBS
planning
Scope Mgt
Time Mgt
Activity
Sequencing
Activity Project
Activity Schedule Plan
Resource
Definition Development
Estimating
Activity
Duration
Estimating
OPA, EEF,
PMP
Cost
Estimating Cost Budgeting
RZH 2008
Cost Mgt