Timeline for the


oneM2M Partnership Project
Timeline and Milestones

[Joachim Koss, ETSI] Contribution to CoU V1a, 20 Jan 2012


Introduction
Summary of timeline discussion at Washington meeting:
• [M2MCons02_31 Draft Meeting Report.doc]
“Mr. Foote presented a table that captures a summary of the SDO positions
along with a list of consensus items [M2MCons02_26]. There is agreement that
the launch of the consolidated group should take place no later than 1Q2012,
with the understanding that milestones will be met along the way to meet the
established threshold criteria.”
• [M2MCons02_26 - Summary of SDO proposals on M2M Consolidation 4.4.pptx]
“Launch of consolidated group no later than 1Q2012, with milestones to be met
along the way to meet the threshold criteria.”
In order to keep the envisaged date for launch of the M2M
consolidation (Q1/2012) a more detailed time schedule with
well defined milestones is necessary.
The next pages propose a timeline including milestones and
definition of milestones.

2
Timeline

2011 2012
JUL AUG SEP OCT DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT
SDO Meeting#01, SDO Meeting#03, Technical Plenary
Virtual meetings
Seoul, 21 Jul Berlin, 15-16 Dec Meeting#1
SDO Meeting#02, Steering Committee Steering Committee
Washington, Meeting#1 Meeting#2
17-18 Aug

Virtual SDO meetings


SDO Meeting#04,
Tokyo, 28-29 Mar
Reach out to verticals

M1: “Soft Launch”


M2: Final Consensus

M3: Final Draft

M4: Official Signing

M5:
TP start prepared
M6:
WG start prepared

3
Milestones (1)
 Milestone M1 – “Soft Launch”
• IPR regime agreed
• Communiqué released
• Material for communication with verticals updated to include Berlin meeting
results
• Target date: [10] 18 Jan 2012, completed

 Milestone M2 – Final Consensus


• Feedback from vertical reach outs incorporated into major principles
• Final Consensus reached and documented on all major principles (scope,
partnership and participation principles, structure, legal status, participation
rules, rights and responsibilities, level of secretariat services, funding)
• Initial Organizations identified and start work on drafting the founding
documents
• Target date: [10] 17 Feb 2012

4
Milestones (2)
 Milestone M3 – Final Draft
• Final review of feedback from vertical reach outs
• Final draft of founding documents available
(Participation rules, procedures, IPR policy and anti-trust policy, member fees,
budget plan for first year)
• Secretariat support activities identified
(online web presence, on-site meeting support, document editing, document
management, branding/publicity )
• Convenor of Steering Committee nominated
• Target date: 9 Mar 2012
 Milestone M4 – Official Signing
• Founding agreement signed
• Members of Steering Committee identified
• Preliminary list of members of the initiative identified
• Target date: 30 Mar 2012

5
Milestones (3)
 Milestone M5 – TP start prepared
• Convenor of Technical Plenary nominated
• Participants of Technical Plenary identified
• Working Procedures approved
• List of standards/specifications to be transferred into GI agreed
• Target date: 19 Jun 2012
 Milestone M6 – WG start prepared
• Initial Work Plan defined
• Initial Working Groups defined
• Convenors of Working Groups nominated
• Meeting schedule defined
• Target date: 31 Jul 2012