COKE OVEN 2

BHUSHAN STEEL, Angul

LARSEN & TOUBRO LIMITED


Major Highlights

• 11868 CUM Concreting in March’2011.

• 3 No’s EOT Erection Completed.

• Roof Sheeting Completed.

• CO Gas Under-jet Piping work Started.

LARSEN & TOUBRO LIMITED


Drg. Rel. by
Area Description UOM Scope Front Avl. Completed
BSL

Battery no 1 CUM 103645 103645 98235 98235

Battery no 2 CUM 154037 154037 72114 72114

By-Product CUM 80000 80000 63148 63148

TOTAL CUM 337682 337682 233497 233497

Presently WMM Work stopped due to non availability of workable front


Progress as on date – Concreting (CUM)

Drg. Rel. by Seq. Front Completed as


Area Description Scope Front avl.
BSL Avl on 4th Apr’11

Battery no 1 61194 51912 50488 45570 37127

By-Product 29150 13853 12601 9684 8147

Service Areas 1500 - - - -

Battery no 2 34698 8947 2630 2630 1811

TOTAL 126542 74712 65719 57884 47085


Engineering status– Civil works (CUM)
Battery-1

Area Scope Sch. Rel. Act. Rel. Balance Sch. Date

Quenching Tower 1462 1462 1462  

Coal Tower 9728 9728 4492 5236 Sep’10

End Platform-
4219 4219 3925 294  
Battery 1
Quenching track rail
5306 5306 5306  
foundation
Coke wharf &
6167 6167 4462 1705 Sep’10
De-dusting

Other Area 34312 34312 32265 2047 Sep’10

Total 61194 61194 51912 9282  


Engineering status– Civil works (CUM)
Bi-Product
Act. Sch.
Area Scope Sch. Rel. Bal.
Rel. Date
Pipe Network 1700 1700 890 810 Mar’11

Primary cooler ( 3 No.+2


680 680 641 39  
Nos. Future)

Combi Scrubber 901 901 901 Released

Electrostatic Detarrer 638 638 197 441

De-acidification and
475 475 375 100
Ammonia Stripping Plant

Exhauster building 1315 1315 1191 124  

Main control room 638 638   638 Nov'10


Engineering status– Civil works (Bi-Product)

Area Scope Sch. Rel. Act. Rel. Balance Sch. Date


Maintenance ware
2189 2189   2189 Nov'10
house utility
Sulphur recovery 638 638   638 Nov'10
Sulphur Solidification
2423 2423   2423 Feb'11
& Storage
Coal water storage 149 149   149 Nov'10

Electrical Receiving
5787 5787 5787  
Station

Settling basin 2277 2277 2277 Feb'11

Others 9340 9340 1594 7746  

Total 29150 29150 13853 15297  


Progress as on date – Structural

Area Drawing Front Fab. Erec.


UOM Scope
Description Released Avl. Comp Comp
Temp Shed for
MT 1150 782 779 761 661
Oven

Vessels MT 746 549 Nil Nil Nil

Pipe Rack
MT 1300 1057 Nil Nil Nil
Structure

Total MT 3196 2388 779 761 661


Progress as on date – Piping

Area Drg. Front Fab. Erec.


UOM Scope
Description Rel. Avl. Comp Comp

Battery Proper MT 77 40 35 32 Nil

Wet Quenching MT 59 Nil Nil Nil Nil

By Product
MT 2980 1728 Nil Nil Nil
Area

Total MT 3116 1768 35 32 Nil

Area demarcation is required on rake piping layout drawing


so that civil, strl and piping can go simultaneously.
Major Scope Of Work-Equipment
Sl Front
Description UOM Scope Drg. Rel. Comp
No Avl.
A Technological Structure & Equipment
1 Coal Tower MT 116 Nil Nil Nil
2 COB Proper MT 5989 Nil Nil Nil
3 PEC System MT 900 Nil Nil Nil
4 Wet Quenching MT 1010 Nil Nil Nil
5 By Product Plant MT 2143 Nil Nil Nil
6 Pipe & Valves MT 98 Nil Nil Nil
7 HVAC System MT 225 Nil Nil Nil
Major Scope Of Work
Sl Drg. Front
Description UOM Scope Comp
No Rel. Avl.
B Stainless Steel structures

1 COB Proper MT 0.37 Nil Nil Nil

2 Wet Quenching MT 13 Nil Nil Nil

C Oven Machines

1 COB Proper MT 6618 Nil Nil Nil


D Other Area

1 EOT MT 235 235 235 235


2 Sheeting for TOPR SQ M 13980 13980 13980 9800
Support Required From EDRC

 Drawing release schedule.

 Drawing control index & Scope.

 Balance Civil drawings of Bi-Product Area.

 GFC Drawings For Mixed gas , CO Gas Piping.

 Civil foundation Drg for pipe rack inside battery limit . In line
with structural fabrication and piping fabrication.

 Lay out Drawing & G A Drawing for mechanical.


Support Required From BU

Overall “S” Curve to be prepared along with


Engineering, supply and site service .
Schedule of Supply ordering and deliveries .
4 no’s Scrubber fabrication issue not cleared,
which is supplied by BU or fabricated at site .
P O Released for 27 no's Item
Support Required From BU

Material Related:-
BOP AREA- PIPING
 Valve & Nozzle's for COG under jet Piping .
 Valve & Nozzle's for CO gas, Mixed gas & De graphitizing
air.

BPP AREA:-
 Primary Gas Cooler with all internal parts.
 Primary gas cooler Pumps.
Progress Photographs
Progress Photographs

BI PRODUCT - MAIN ECR RAFT CONCRETING


Progress Photographs

BATTERY #1 DECK SLAB UPTO


5th SEGMENT COMPLETED

SETTLING TANK RAFT


Progress Photographs
BATTERY #1 TEMPORARY SHED-
EOT ERECTION COMPLETED

BATTERY #1 TEMPORARY SHED


Progress Photographs

COG UNDERJET PIPING


ERECTION UNDER PROGRESS
Progress Photographs

COMBI SCRUBBER

CHIMNEY- 140M high


Thank You