Supply Planning Training Matls - v1.0
Supply Planning Training Matls - v1.0
Supply Planning Training Matls - v1.0
October, 2010
Table of Contents
2
IBP One Number Vision
The vision for Integrated Business Planning (IBP) is to have One Plan
drive the business
EDR -
2 Consensus
Sales
Input Demand
Marketing
Input
Planning
Historical
Demand Forecast
Unconstrained
One Plan
Forecast driving
1 PMR 4 5 MBR execution
Marketing
Marketing Portfolio Integrated Integrated Management
Consensus Sales
Plans
Management Forecast
Reconciliation Options & Business
Decisions Production
New/
Discontinued Reconciled Financial Review
Products P&L View Scenarios
CS&L
Constrained
Forecast
3 Supply
Review
Capacity
Plans
Supply
Inventory &
Planning
Supply Policies
1.0 • Portfolio Management ensures that the category plans and innovation portfolio from
Marketing align with the business strategy
Portfolio
• It also provides key inputs on new product introductions and SKU rationalization to
Management
demand and supply planning
• Process Owner1: Marketing
• Demand Planning generates a consensus shipment forecast using inputs from Sales,
2.0
Marketing and CS&L
Demand • Output is unconstrained forecast for Supply Planning and R&O’s to be analyzed in Supply
Planning Review and IR
• Process Owner1: Sales, Marketing, Product Supply, Finance
3.0 • Supply planning defines the optimal approach to meet demand and identifies any
Supply capacity gaps
Planning • Supply policies are agreed and reviewed as needed to set operational boundaries,
guide execution, drive escalation and avoid surprises
• Process Owner1: Product Supply
4.0 • Integrated Reconciliation (IR) takes the gaps from Supply Planning and analyzes the
Integrated options and financial implications of closing the gaps
Reconciliation • IR provides recommendations to the MBR along with a BU P&L and DIOH implications
• Process Owner1: BU, Finance
5.0 • Culmination of the IBP process, the MBR process reviews the recommendations from
Management
IR and makes decisions to develop an integrated plan
Business
• MBR ensures the health of the business in both the short and long term
Review
• Process Owner1: BU
4 1) Detailed process ownership addressed in the later sections
IBP One Number Design:3.0 Supply Planning
3.0 The current Supply Planning process lacks formal processes for
policy changes
Inputs
Unconstrained Demand; DFC /
Inventory Policies; Cycle Times;
Inputs / Mfg capacities & utilization
Revised
Previously Agreed Policies Production
Policies CFR policies; Pre build Strategy; Supply Scheduling
Product optimization by ABC Plan
segmentation
Un- Initial
Constrained
constrained Supply
Plan
Plan
Plan
Weekly Plan
(NPP) blown MBR / MU /
down to a daily Supply Review Ad hoc
list of other
line schedule Meeting
Review of the supply plan Issues discussions
(Finite Scheduler)
mainly to review capacity
constrained situations
6
IBP One Number Design:3.0 Supply Planning
7
IBP One Number Design: 3.0 Supply Planning
8
IBP One Number Design: 3.0 Supply Planning
3.0 In the future state, Supply Planning should enable upfront policy
setting and rigorous scenario analysis
Production
Scheduling
Future State Supply Planning Process
3.1 Initial Supply
Plan
Set / Revise
Operational
Policies Revised
3.3 3.4 3.5 Supply Plan
Issues that
require
tradeoff
3.2 Master Scheduling Supply Review analysis
Evaluate Optional Meeting
Rough Cut Scenarios
Capacity Planning
9
IBP One Number Design: 3.0 Supply Planning..3.1 Set Ops Policies
OUTPUTS
INPUTS
3.2
Recommendations on
• Current capacity by line • Re-allocation of lines
Rough Cut Capacity
/ Planning Level based on capacity and
• Planned capital Planning
demand imbalances
investments Purpose - Align capacity with • Crewing plan
• External manufacturing projected demand • Level and type of usage
constraints / options Work Steps of external mfg
• Long range demand A - Develop 0-18 mnths capacity view • Pre-build strategy
plan C - Develop scenarios • Overtime policies
• Product Portfolio plan - D - Test sensitivities / develop plan • External manufacturing
New / discontinued policy / strategy
products + products to • Planning requirement
be emphasized for promotions e.g.
Responsible Accountable
order lead times
• NPP • Director of Product Supply
• Sr. Supply Chain Manager
Consulted Informed
• Plant Managers • Sales & Marketing teams
• Plant Materials Managers
• Business Development
Directors
KEY PARAMETERS METRICS
Frequency Monthly 1. Utilization by capacity group
Horizon 0 - 18 months out 2. DIOH / DFC
3. CFR
Level of discussion Aggregate Capacity Groups 4. Manufacturing Cost per Unit
(line/location) / lbs
12
IBP One Number Design: 3.0 Supply Planning..3.2 Complete Rough Cut Capacity Planning
System (s) /
Excel Models / Capacity Charts / APS
Tools
Business Planned
investments
Development
DIOH
CFR
Cost To
Serve
% Utilization
3.3
INPUTS OUTPUTS
• Consensus forecast Master Scheduling • Weekly production plan
(planning level) (including co-man) by
• Current capacity Purpose - Develop detailed line and SKU
(including constraints) production / supply plans • Material requirements
• Utilization targets Work Steps plan
• CFR targets by SKU A - Create unconstrained plan • Predicted DIOH, DFC &
(stratified) B - Create constrained plan CFR by period
• DIOH / DFC targets • Predicted manufactured
C - Generate materials
• Run rules (light before requirements / delivered cost by
dark) period (depending on
• Cycle times / schedule maturity)
Responsible Accountable
• National Production Planner • Sr. Supply Chain Manager
Consulted Informed
• Director of Product Supply • Plant Scheduler
• Plant Managers
KEY PARAMETERS
Frequency Weekly METRICS
1. DIOH / DFC
Horizon 0-18 months with primary focus on 0- 2. Inventory Health (Act vs.
3 months (24 month long range plan Ideal)
for some BU’s like Cheese) 3. CFR
15
Level of discussion SKU / case and/or pounds 4. Schedule compliance
15 5. Mfg. cost (per unit)
IBP One Number Design: 3.0 Supply Planning..3.4 Eval. Alt Supply Options
3.4
INPUTS Alternate Supply OUTPUTS
• Consensus forecast Options • Detailed assessment of
(planning level) – SKU Purpose - Evaluate alternate supply scenarios including
level if needed options in case of exceptions impact on:
• Demand/Supply Work Steps • CFR
Imbalance A - Identify supply issues • DIOH / DFC
• Current capacity B - Develop alternate plans • Mfg. Cost
(including constraints) C - Analyze options / develop reco. • Inventory balance
• Demonstrated • Utilization
D - Present options in supply review
utilization rates • Sensitivities - based on
• CFR targets by SKU demand
(stratified)
• DIOH targets Responsible Accountable
• External mfg. options / • Sr. Supply Chain Manager • Director of Product Supply
capabilities
• Commodity Consulted Informed
commitments • NPP • Full Category team
• Ops / Category Finance • Marketing Team
• Logistics Directors • Sales Team
• Category Sales Planning Mgr.
(as needed)
• Brand Manager (as needed)
Excel Models / Capacity Excel Models / Capacity Excel Models / Capacity Recommendations
System (s) / charts / DIOH tool / IH charts / DIOH tool / IH charts / DIOH tool / IH supported by
Tools analysis analysis / CPP / APS analysis
robust analyses
• Provide input on OI
Operations implications
Finance • Provide support on analysis
17
IBP One Number Design: 3.0 Supply Planning..3.5 Conduct Supply Review Meeting
3.5
INPUTS OUTPUTS
• Constrained supply Supply Review • Revised constrained
supply plan
plan
• Projected DIOH / DFC Purpose - Review supply plan / • Documentation of R&O,
• Capacity charts discuss and resolve issues / elevate decisions and
• Supply options major issues to IR communication plan
Work Steps • Recommended policy
including risks &
A - Develop meeting materials adjustments or
opportunities for
B - Hold the meeting exceptions
escalated issues
• List of specific issues to
C - Communicate meeting outcome
to all key stakeholders be elevated to IR
• Scenarios to be
modeled for IR
Responsible Accountable
• Sr. Supply Chain Manager • Director of Product
Supply
Consulted Informed
• Business Development / Network Leads
• Ops Finance
• Sales & Marketing
METRICS
1. DIOH / DFC
KEY PARAMETERS
2. CFR
Frequency Monthly 3. Line utilization
4. Per unit manufactured /
Horizon 0 - 18 months
delivered cost
Level of discussion Aggregate Capacity Group / Resp. 5. Waste
18
Category
18
IBP One Number Design: 3.0 Supply Planning..3.5 Conduct Supply Review Meeting
19