Professional Documents
Culture Documents
Project Management Sachin Kamble
Project Management Sachin Kamble
Project Management Sachin Kamble
MANAGEMENT
Sachin Kamble
Projects
Projects are an interrelated set of activities with a definite starting
and ending point, which results in a unique outcome from a
specific allocation of resources
Projects are common in everyday life
The three main goals are to:
Complete the project on time
Not exceed the budget
Meet the specifications to the satisfactions of the customer
Projects
Project management is a systemized, phased approach to
defining, organizing, planning, monitoring, and controlling
projects
Projectsoften require resources from many different parts of the
organization
Each project is unique
Projects are temporary
A collection of projects is called a program
Defining and Organizing Projects
Define the scope, time frame, and resources of the project
Select the project manager and team
Good project managers must be
Facilitators
Communicators
Decision makers
Project team members must have
Technical competence
Sensitivity
Dedication
Planning Projects
S T U S precedes T, which
precedes U.
S S and T must be
U completed before U
can be started.
T
Figure 2
Diagramming the Network
T
T and U cannot
S begin until S has
U been completed.
Figure 2
Diagramming the Network
Figure 2
Developing the Schedule
Example 1
St. John’s Hospital Project
Activity Immediate Activity Times Responsibility
Predecessors (wks)
ST. JOHN’S HOSPITAL PROJECT
Completion Time I
START 15
ORGANIZING
Activity IP and
Time SITE PREPARATION
A A. Select
STARTadministrative
12 staff
A F K
B B. Select
STARTsite and 9 survey 12 10 6
C A 10
C. Select medical equipment
D B 10
E D. Prepare
B final24construction plans
F E. Bring
A 10to site
utilities C G
Start Finish
G C 35 10 35
F. Interview applicants for nursing and
H D
support staff40
I A 15
J PHYSICAL
E, G, H FACILITIES
4 and INFRASTRUCTURE
B D H J
K G. Purchase
F, I, J and6 deliver equipment 9 10 40 4
H. Construct hospital
I. Develop information system
J. Install medical equipment E
24
K. Figureand
Train nurses 3 support staff
FINISH
Example 1
St. John’s
Path Hospital Project
Estimated Time (weeks)
A–I–K 33
A–F–K
Activity 28 Immediate Activity Times Responsibility
Predecessors (wks)
A–C–G–J–K 67
ST. JOHN’S HOSPITAL PROJECT
Completion I
B–D–H–J–K
START 69 Time
15
B–E–J–K 43
ORGANIZING and SITE PREPARATION
A. Select administrative staff
A F K
B. Select site and survey 12 10 6
C. Select medical equipment
D. Prepare final construction plans
E. Bring utilities to site C G
Start Finish
10 35
F. Interview applicants for nursing and
support staff
PHYSICAL FACILITIES and INFRASTRUCTURE
B D H J
G. Purchase and deliver equipment 9 10 40 4
H. Construct hospital
I. Develop information system
J. Install medical equipment E
24
K. Figureand
Train nurses 3 support staff
FINISH
Example 1
St. John’s
Path Hospital Project
Estimated Time (weeks)
A–I–K 33
A–F–K
Activity 28 Immediate Activity Times Responsibility
Predecessors (wks)
A–C–G–J–K 67
ST. JOHN’S HOSPITAL PROJECT
Completion I
B–D–H–J–K
START 69 Time
15
B–E–J–K 43
ORGANIZING and SITE PREPARATION
A. Select administrative staff
A F K
B. Select site and survey 12 10 6
C. Select medical equipment
D. Prepare final construction plans
E. Bring utilities to site C G
Start Finish
10 35
F. Interview applicants for nursing and
support staff
PHYSICAL FACILITIES and INFRASTRUCTURE
B D H J
G. Purchase and deliver equipment 9 10 40 4
H. Construct hospital
I. Develop information system
J. Install medical equipment E
24
K. Train nurses and support staff
FINISH
Example 1
Application 1
Immediate
Activity Activity Time (days) Predecessor(s)
A 7 —
B 2 A
C 4 A
D 4 B, C
E 4 D
F 3 E
G 5 E
B F
2 3
A D E
Start Finish
7 4 4
C G
4 5
Project Schedule
The project schedule specifies start and finish times for each
activity
Managers can use the earliest start and finish times, the latest
start and finish times, or any time in between these extremes
Project Schedule
The earliest start time (ES) for an activity is the latest earliest finish time of
any preceding activities
The earliest finish time (EF) is the earliest start time plus its estimated
duration
EF = ES + t
The latest finish time (LF) for an activity is the latest start time of
any preceding activities
The latest start time (LS) is the latest finish time minus its
estimated duration
LS = LF – t
Activity Slack
Activity
slack is the maximum length of time an activity can be
delayed without delaying the entire project
Activities on the critical path have zero slack
Activity slack can be calculated in two ways
S = LS – ES or S = LF – EF
Illustration for identifying slack activities and critical path
F
3
Assessing Risk
a m Mean b
Time
Beta distribution
3σ 3σ
a m b
Mean
Time
Normal distribution
Figure 5
Statistical Analysis
a + 4m + b
te =
6
2
b–a
σ =
2
6
Calculating Means and Variances
EXAMPLE
Suppose that the project team has arrived at the following time estimates for activity B (site
selection and survey) of the St. John’s Hospital project:
7 + 4(8) + 15 54
te = = = 9 weeks
6 6
Note that the expected time does not equal the most likely time. These will only be
the same only when the most likely time is equidistant from the optimistic and
pessimistic times.
The variance for activity B is
2 2
15 – 7 8
σ2 = = = 1.78
6 6
Application of PERT
Bluebird University: activity for sales training seminar
Most
Immediate Optimistic Likely Pessimistic Expected Variance
Activity Predecessor(s) (a) (m) (b) Time (t) (σ)
A — 5 7 8 6.83 0.25
B — 6 8 12 8.33 1.00
C — 3 4 5 4.00 0.11
D A 11 17 25 17.33 5.44
E B 8 10 12 10.00 0.44
F C, E 3 4 5 4.00 0.11
G D 4 8 9 7.50 0.69
H F 5 7 9 7.00 0.44
I G, H 8 11 17 11.50 2.25
J G 4 4 4 4.00 0.00
TE =
Expected activity times
on the critical path =
Mean of normal
distribution
where
T – TE
z= T = due date for the project
σ 2
Calculating the Probability
Calculate the probability that Blue bird University will become operational in 50 weeks,
using the critical path.
SOLUTION
a. The critical path A- D- G- I has a length of 43.16 weeks. From the table in Example,
we obtain the variance of path A-D-G-I: σ2 = 0.25+ 5.44 + 0.69+2.25 = 2.93
b. Next, we calculate the z-value:
Z= 2.33
43.16 50
Project duration (weeks)
Calculating the Probability
Calculate the probability that St. John’s Hospital will become operational in 72 weeks, using
(a) the critical path and (b) path A–C–G–J–K.
SOLUTION
b. From the table in Example 2.4, we determine that the sum of the expected activity
times on path A–C–G–J–K is 67 weeks and that σ2 = 0.11 + 2.78 + 7.11 + 5.44 +
0.11 = 15.55. The z-value is
72 67 5
z 1.27
15.55 3.94
The probability is about 0.90 that the length of path A–C–G–J–K will be no
greater than 72 weeks.
Analyzing Cost-Time Trade-Offs
• Project Crashing
– Shortening (or expediting) some activities within a project
to reduce overall project completion time and total project
costs
• Project Costs
– Direct Costs
– Indirect Costs
– Penalty Costs
Analyzing Cost-Time Trade-Offs
• Project Costs
– Normal time (NT) is the time necessary to complete an
activity under normal conditions.
– Normal cost (NC) is the activity cost associated with the
normal time.
– Crash time (CT) is the shortest possible time to complete
an activity.
– Crash cost (CC) is the activity cost associated with the
crash time.
CC NC
Cost to crash per period
NT CT
Cost-Time Relationships
Cost–Time Relationships in Cost Analysis
Analyzing Cost-Time Trade-Offs
Determining the Minimum Cost Schedule:
1.Determine the project’s critical path(s).
2.Find the activity or activities on the critical path(s) with the
lowest cost of crashing per week.
3.Reduce the time for this activity until…
Cost of
Crashing
Normal Time (N T) Normal Cost Crash Time Crash Cost Maximum Time per Week
Activity (weeks) (NC)($) (CT)(weeks) (CC)($) Reduction (week) ($)
A 12 $12,000 11 $13,000 1 1,000
B 9 50,000 7 64,000 2 7,000
C 10 4,000 5 7,000 5 600
D 10 16,000 8 20,000 2 2,000
E 24 120,000 14 200,000 10 8,000
F 10 10,000 6 16,000 4 1,500
G 35 500,000 25 530,000 10 3,000
H 40 1,200,000 35 1,260,000 5 12,000
I 15 40,000 10 52,500 5 2,500
J 4 10,000 1 13,000 3 1,000
K 6 30,000 5 34,000 1 4,000
blank Totals $1,992,000 blank $2,209,500 blank blank
Example Project Crashing
Indirect cost $8000 per week
$20000 penalty per day if the project
Project completion time = 69 weeks
gets delayed beyond 65 weeks.
Project cost = $2,624,000
Direct = $1,992,000
Indirect = 69 $8,000 $552,000
Penalty = 69 65 $20,000 $80,000
A–I–K 33 weeks
A–F–K 28 weeks
A–C–G–J–K 67 weeks
B–D–H–J–K 69 weeks
B–E–J–K 43 weeks
Example Project Crashing
Stage 1
Step 1. The critical path is B–D–H–J–K.
Step 2. The cheapest activity to crash per week is J at $1,000, which is much
less than the savings in indirect and penalty costs of $28,000 per week.
Step 3. Crash activity J by its limit of three weeks because the critical path
remains unchanged. The new expected path times are
A–C–G–J–K: 64 weeks
B–D–H–J–K: 66 weeks
Step 3.
•Updated path times are: A–C–G–J–K: 63 weeks and B–D–H–J–K: 63 weeks
•Net savings are $8,000 − $4,000 = $4,000.
•Total project costs are $2,511,000 − $4,000 = $2,507,000.
Example Project Crashing
Example Project Crashing
Stage 4
Step 1. The critical paths are still B–D–H–J–K and A–C–G–J–K.
Step 2. Activities eligible to be crashed: (B,C) @ $7,600 per
week. This amount is still less than the savings of $8,000/week.
Step 3. Crash activities B and C by two weeks.
•Updated path times are
A–C–G–J–K: 61 weeks and B–D–H–J–K: 61 weeks
Project
Crash Total Total Total
Time Resulting Project Direct
Crash Cost Indirect Penalty Project
Stage Reductio Critical Duration Costs,
Activity Added Costs Costs Costs
n (weeks) Path(s) (weeks) Last Trial
($000) ($000) ($000) ($000)
($000)
0 — — B–D–H–J–K 69 1,992.0 — 552.0 80.0 2,624.0
1 J 3 B–D–H–J–K 66 1,992.0 3.0 528.0 20.0 2,543.0
2 D 2 B–D–H–J–K 64 1,995.0 4.0 512.0 0.0 2,511.0
A–C–G–J–K
3 K 1 B–D–H–J–K 63 1,999.0 4.0 504.0 0.0 2,507.0
A–C–G–J–K
4 B, C 2 B–D–H–J–K 61 2,003.0 15.2 488.0 0.0 2,506.2
A–C–G–J–K
Solved Example on Project Crashing
Solved Problem Project Crashing
Table Electric Motor Project Data
$1,300 $1,000
= = $300
4 days 3 days
Solved Problem Project Crashing
Crash Cost per Day Maximum Time Reduction
Activity
($) (days)
A 300 1
B 200 3
C 700 1
D 200 1
E 200 1
F 250 5
G 650 1
H 100 2
Solved Problem Project Crashing
The critical path is C–F–H at 19 days, which is the longest path in the
network.
The cheapest activity to crash is H which, when combined with reduced
penalty costs, saves $300 per day in indirect and penalty costs.
Crashing this activity for two days gives
A–D–G–H: 15 days, B–E–G–H: 15 days, and C–F–H: 17 days
Crash activity F next. This makes all activities critical and no more
crashing should be done as the cost of crashing exceeds the savings.
Solved Problem Project Crashing
Table Project Cost Analysis
A 1 4 7 —
B 2 6 7 —
C 3 3 6 B
D 6 13 14 A
E 3 6 12 A, C
F 6 8 16 B
G 1 5 6 E, F
Solved Problem PERT
SOLUTION
a. The expected time and variance for each activity are calculated as follows
a + 4m + b
te =
6
b. We need to calculate the earliest start, latest start, earliest finish, and latest finish times
for each activity. Starting with activities A and B, we proceed from the beginning of the
network and move to the end, calculating the earliest start and finish times.
Based on expected times, the earliest finish date for the project is week 20, when activity
G has been completed. Using that as a target date, we can work backward through the
network, calculating the latest start and finish times
4.0 D 16.0
Finish
8.0 12.0 20.0
C
Start 5.5 9.0
5.5 3.5 9.0
T – TE 23 – 20
z= = = 1.52
σ 2
3.88
Using the Normal Distribution Appendix, we find the probability of completing the
project in 23 weeks or less is 0.9357. Because the length of path B–F–G is close to that
of the critical path and has a large variance, it might well become the critical path
during the project