Test and Commissioning

November 2, 2021
TEST AND COMMISSIONING UPDATES

2
BACKGROUND

DOE DC 2021-06-0013
“Adopting A General Framework Governing the
Test and Commissioning of Generation Facilities
for Ensuring Readiness to Deliver Energy to the
Grid or Distribution Network”

• Was because of issues on the prolonged test


and commissioning of some generation
facilities (with recorded maximum Test and
Commissioning period of 5 years)
• Provides the framework on the conduct of Test
and commissioning of generation facilities
• Became effective on 17 July 2021.

3
Test and Commissioning Comparison
2014 Revised COC Rules vs DOE DC 2021-06-0013
ITEMS 2014 Revised COC Rules DOE DC 2021-06-0013
Application to ERC/TNP prior • Application for COC shall be • Application for the conduct of
to the conduct of test and filed not later than 3 months T&C at least 3 months before
commissioning (T&C) before targeted date of T&C target date (to SO and TNP)
(to ERC)
Notification to ERC on the • Notify ERC at least 30days • None mentioned
actual T&C schedule before the actual date
Required document prior to • None mentioned • Provisional Certificate of
the conduct of T&C Approval to Connect
(PCATC)
• Genco to furnish a copy of
PCATC to MO and SO
Timeline for the conduct of • Maximum period of 2 months • Maximum period of 2 months
Test and Commissioning
Extension for the timeline • None mentioned • Maximum of 1 month
• (actual: some gen facilities extension due to (a) valid
conducted more T&C more technical or other issues with
than 2 months) the gen facility, or (b) reasons
beyond the control of gen
facility, and TNP
• Required extended PCATC
4
Test and Commissioning Comparison
2014 Revised COC Rules vs DOE DC 2021-06-0013
ITEMS 2014 Revised COC Rules DOE DC 2021-06-0013
Injection payment during • Settled at WESM prices • Settled at WESM prices
valid T&C
Injection beyond valid T&C • None mentioned • SO to cease overriding
period • (actual: prolonged T&C was constraints
paid as price takers) • Not allowed to declare BCQ
• No WESM payment
Document required after T&C • Certificate of Technical • Final CATC*
Requirements Compliance • TNP to issue final CATC 14
issued by NGCP calendar days upon
satisfactory result of T&C and
genco’s submission of
requirements
• TNP to furnish a copy of final
CATC to ERC and MO

*May be additional to the certificate of technical requirements compliance depending on the implementation of NGCP

5
Test and Commissioning Comparison
2014 Revised COC Rules vs DOE DC 2021-06-0013
ITEMS 2014 Revised COC Rules DOE DC 2021-06-0013
Required regular reporting • None mentioned • If T&C was conducted by 3rd-
during the conduct of T&C party testing entity, Genco
shall submit weekly status
update to MO, WESM
Governance Arm, ERC, and
DOE
Timeline for ERC issuance of • 60 calendar days from • 60 calendar days from
COC complete submission of submission of Final CATC
documents, including ERC and satisfaction of other
technical inspection applicable requirements
(conducted after T&C)

6
Test and Commissioning Process Flow
Start A
Genco ready to

Application for No
deliver energy
to the grid?
B
conduct of YES
Generation T&C completed
T&C before/upon PCATC Submit
Company Furnish expiration? Submit
PCATC copy complete Submit
Submit requirements to
YES req’ts for COC to
to MO and TNP for
complete req’ts COC to
SO issuance of MO
for PCATC ERC
Final CATC

Third-party
Conduct Test Evaluate
testing result and
entity and validate
Commissionin readiness
g to deliver Issue Final
Issue PCATC energy CATC to
TNP to gen Gen
Cease
company company
imposition of
and furnish
overriding
copy to ERC
constraints
and MO
Reflect registration
to Commercial
Disallow BCQ Operations
MO declaration
and no WESM Effectivity
payment for commercial
injections operations

ERC Issue End


COC
7
Test and Commissioning Process Flow (for extension)
Reason for non- External
A completion of
T&C? Genco ready to
Internal deliver energy
to the grid?
B
Secure new YES
Generation schedule of
T&C completed
before/upon PCATC Submit
Company T&C from Furnish expiration? Submit
complete Submit
TNP and extended requirement to
req’ts for COC to
apply PCATC copy TNP for
COC to MO
extension of to MO and issuance of
ERC
PCATC SO Final CATC

Third-party Evaluate
Complete the
testing Technical issue
based on? conduct of Test result and
Evaluation
entity Identified during validate
of result and readiness
conduct of T&C
Commissionin to deliver
Issue Issue Final
Available T&C g energy
schedule w/in 1 Yes extended CATC to
TNP month from expiry PCATC to Gen
of PCATC?
gen company Cease company
imposition of and furnish
overriding copy to ERC
Suspend validity
constraints and MO
of PCATC

Reflect
Disallow BCQ
registration
MO declaration
to Comm ops
and no WESM C
payment for Effectivity
injections Comm
Ops

ERC Issue End


COC 8
Test and Commissioning Process Flow (for extension)
A T&C
Expired PCATC, Yes
B including
extension?
Process End
Genco ready to
reset
C No
deliver energy
to the grid?

Generation T&C completed YES


before/upon PCATC Submit
Company expiration? Submit
complete Submit
requirement to
req’ts for COC to
TNP for
COC to MO
issuance of
ERC
Final CATC

Third-party Complete the Evaluate


testing result and
conduct of Test
validate
entity and
readiness
Commissionin to deliver
g energy Issue Final
CATC to
TNP Gen
Cease company
imposition of and furnish
overriding copy to ERC
constraints and MO

Reflect
Disallow BCQ
registration
MO declaration
to Comm ops
and no WESM
payment for Effectivity
injections Comm
Ops

ERC
Issue End 9
COC
Test and Commissioning Process Flow (for extension)
Inform MO
and SO that
T&C was not Expired PCATC,
T&C Genco ready to
Yes
C completed including
extension?
Process End deliver energy
to the grid?
w/in reset
Generation prescribed No T&C completed YES
before/upon PCATC Submit
Company period expiration? Submit
complete Submit
Apply for requirement to
req’ts for COC to
reactivation of TNP for
COC to MO
the PCATC issuance of
ERC
Final CATC

Third-party Complete the Evaluate


testing result and
conduct of Test
validate
entity and
readiness
Commissionin to deliver
g energy Issue Final
CATC to
Issue Gen
TNP
reactivated Cease company
PCATC imposition of and furnish
overriding copy to ERC
constraints and MO

Reflect
Disallow BCQ
registration
MO declaration
to Comm ops
and no WESM
payment for Effectivity
injections Comm
Ops

ERC Issue End


10
COC
Test and Commissioning Summary of Timelines

PROCEDURE RESPONSIB TIMELINE REQUIREMENT/REM


LE ENTITY ARKS
Notification to TNP of • GENCO • 3 months prior to target date • Actual schedule of Test and
target T&C date and of Test and commissioning Commissioning shall be
submission of application subject to confirmation of
for T&C the TNP.
Electromechanical • GENCO • Prior the application for
completion PCATC
Submit complete • GENCO • at least 23 days before the 1. Scheduled date of Test
requirements for PCATC conduct of Test and and Commissioning, as
coordinated with TNP
Commissioning Schedule and SO
2. Certification attesting
Electromechanical
Completion
3. Other Proof of WESM
Registration issued by
the MO
4. requirements as may
be determined by the
TNP
PCATC Issuance • TNP • within 20 calendar days from
submission of complete
requirements
Submission of PCATC to • GENCO • within 3 working days upon
MO and SO receipt of the PCATC

11
Test and Commissioning Summary of Timelines

PROCEDURE RESPONSIB TIMELINE REQUIREMENT/REM


LE ENTITY ARKS
Conduct of T&C • Testing 2 months (initial conduct) • Over-riding constraints
Entity + TNP   will be submitted by SO
1 month (extension) to MO
+ SO • Any injection during
(witness) valid PCATC is eligible
for WESM payment
Evaluation of result and • TNP and/or • Within 14 calendar days after
validation of readiness to Third party completion of the conduct of
deliver energy testing entity T&C
Submit requirements to the • Genco • N/A • As may be required by TNP
TNP for issuance of Final
CATC
Issuance of Final CATC • TNP • within 14 calendar days from
the satisfactory evaluation of
the results and GenCo's
complete submission of
requirements

12
Test and Commissioning Summary of Timelines

PROCEDURE RESPONSIB TIMELINE REQUIREMENT/REM


LE ENTITY ARKS
Submission of Final CATC • TNP • within 3 calendar days upon
to ERC and MO issuance
Submission of complete • GENCO • N/A As may be required by ERC
requirements for COC
Issuance of COC • ERC • Within 60 calendar days
Submission of COC to MO • GENCO • Within 3 working days
WESM Registration update • MO • Within 15 working days Effectivity of the new WESM
to Commercial Operations registration in the MPI shall
be within eight (8) calendar
days from approval.

13
EPI Test and Commissioning Timeline (Target March 30, 2022)
2021 2022
ACTIVITIES
DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV

Notification to NGCP target T&C date and


submission of application for T&C
Dec 30
Electromechanical completion
Dec 30
Submit complete requirements for PCATC Mar 7 PCATC Issuance
Mar 27
Submission of PCATC to MO and SO
Conduct of T&C* Mar 30
Test and
Mar 30 Commissionin May 30
MO notification of the expiration of g
PCATC*
May 15
Evaluation of result and validation of
readiness to deliver energy*
Jun 13
Submit requirements to the TNP for
issuance of Final CATC
TNP Issuance of Final CATC* (no max timeline)
Jun 30 (TNP submission
ERC issuance of COC (PAO accepted by Jun 27 Final CATC to ERC and MO
MO)*
Submission of COC to MO Aug 30
MO to reflect Commercial operations
Sept 2
registration*
MPI effectivity * Sept 17
Commercial Operations
Sept 25
Sept 25

*With external
14
dependencies
EPI Test and Commissioning Timeline (Target April 26, 2022)

ACTIVITIES 2021 2022


DEC JAN FEB MAR APR MAY JUN JUL AUG SEPT OCT NOV

Notification to NGCP target T&C date and


submission of application for T&C
Jan 30
Electromechanical completion
Jan 30
Submit complete requirements for PCATC PCATC Issuance
Apr 7
Submission of PCATC to MO and SO Apr 27

Conduct of T&C* Apr 30


Test and
MO notification of the expiration of Apr 30 Commissioning Jun 30
PCATC*
Jun 15
Evaluation of result and validation of
readiness to deliver energy*
Submit requirements to the TNP for Jul 14
issuance of Final CATC
TNP Issuance of Final CATC* (no max timeline)
Jul 31 (TNP submission Final
ERC issuance of COC (PAO accepted by Jul 28 CATC to ERC and MO
MO)*
Submission of COC to MO Sept 30

MO to reflect Commercial operations


registration* Oct 05

MPI effectivity * Oct 20


Commercial Operations
Oct 28
Oct 28

*With external dependencies


15