TECHNOLOGICAL AND PROFESSIONAL

SKILLS DEVELOPMENT SECTOR PROJECT


(TPSDP)
ADB LOAN NO: 1792-INO

SUB-PROJECT PROPOSAL
BATCH III
TECHNOLOGICAL AND PROFESSIONAL
SKILLS DEVELOPMENT SECTOR PROJECT
(TPSDP)

SUB PROJECT
PROPOSAL BATCH III
(Name of University)
(Name of SPMU)

Directorate General of Higher Education


Ministry of National Education
2003
PREPARATION AND IMPLEMENTATION SCHEDULE
TECHNOLOGICAL AND PROFESSIONAL SKILLS DEVELOPMENT PROJECT
BATCH III

2003
No. Activities
April May June July August September October November December
I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV

1 Invitation for self-evaluation & Proposal 8 4


2 Workshop for SE and Proposal
Group I Makassar 20-22
Group II Yogyakarta 24-26
Group III Padang 27-29
Gorup IV Bandung 01-03
3 Nurturing Programs 21 9
Nurturing Preparation Meeting 16-17
4 Reviewer Meeting
5 Desk evaluation
6 Final desk evaluation
7 Announcement
8 Site visit preparation
9 Site Visit
10 Site visit report submission
11 Reviewer Meeting
12 ADB and DGHE Approval
13 Announcement
14 PIP development
15 Negotiation
16 ADB Approval
17 Award
INVITATION TO SUBMIT TPSDP SUB-PROJECT
PROPOSAL BATCH III

ELIGIBLE INSTITUTIONS
ELIGIBLE INSTITUTIONS
PUBLIC AND PRIVATE UNIVERSITIES
PUBLIC AND PRIVATE UNIVERSITIES

SUBPROJECT PROPOSAL BATCH III

Strengthening New S-1 Programs Institutional Support

SP A SP A Program A
SPB A
SP SP A Program A
SPCB SP B Program B
SP SP B Program B
SP…C SP … Program …
SP SP … Program …
SPn … SP n Program n
SP SP n Program n
SP n

No
STOP DESK
DESK
EVALUATION
EVALUATION
Yes

SORT-LISTED PROGRAMS BY INSTITUTION


Strengthening New S-1 Programs Institutional Support

SP A SP A Program A
SP B Failed Program B
SP C Failed Failed
Failed
Failed Failed
Failed
Failed

A
A

Short List
Study Programs and
Institutional Support

RANKED BY RANKED BY
PUBLIC UNIVERSITY PRIVATE UNIVERSITY

REGION REGION REGION REGION REGION REGION


I II III I II III
40 % 20 % 40 % 35 % 30 % 35 %

No
SITE STOP
SITE
VISIT
VISIT
Yes
No

REVINING STOP
REVINING

Yes

CONTRACT
60-70
GRANTS
Recapitulation of Batch I + II By Type of Institution and Field

Type of InstitutionProgram Region I Region II Region III Total


Public Institution Engineering 5 3 4 12
Basic Science 5 2 1 8
Agriculture 2 6 8
Economics 5 2 6 13
Law 2 1 3
Sub Total 19 8 17 44
Private Institution Engineering 3 12 3 18
Basic Science 0
Sub Total 3 12 3 18
Polytechnic and D3Engineering 11 7 4 22
Commerce 1 2 3 6
Economics 4 4
Agriculture 0
Sub Total 12 9 11 32
Total 34 29 31 94

Recapitulation of Batch I + II By Type of Institution and Field

Type of InstitutionProgram Region I Region II Region III Total


Public Institution ISS 2 3 2 7
Private Institution ISS 7 7
Polytechnic and D3ISS 2 1 3
Total 4 11 2 17
PERBEDAAN DENGAN BATCH SEBELUMNYA
PADA PENGGABUNGAN SE DAN SPP SERTA WAKTU 3,5 TAHUN

SE
RT
REPO

TECHNOLOGICAL AND PROFESSIONAL


SKILLS DEVELOPMENT SECTOR
PROJECT (TPSDP)

SUB PROJECT
PROPOSAL BATCH III
(Name of University)
(Name of SPMU)

SPP
Directorate General of Higher Education
Ministry of National Education
2003
SUBPROJECT IMPLEMENTATION AND DISBURSEMENT SCHEDULE
TECHNOLOGICAL AND PROFESSIONAL SKILLS DEVELOPMENT SECTOR PROJECT
SUBPROJECT BATCH III

Y1 Y2 Y3 Y4
No. IMPLEMENTATION 2004 2005 2006 2007
I II III IV I II III IV I II III IV I II
                               
1 Contract Duration                            
                               
2 Implementation (SIP)                            
  Year I                            
  Year 2                            
  Year 3                            
  Year 4                            
                               
                               
3 Disbursement Plan 32% 36% 22% 10%
                               
4 Payments                            
  First Payment 75%     50%     50%     100%
  Second Payment     25%     50%     50%    
Figure A.2.4. A Common Logic For Self-Evaluation

External Environment
(Local, National, Global) STRATEGIC Problem Alternative Activities of SOURCES No Resource
DIKS/
ISSUES Identification For Solution SP Dev. Plan TPSDP DUE-Like Semi-Que DIP Pemda … Others Needed
Yayasan
Trend Stake-holders Job Market (1).1 (1).1.1 R1 ….
Ideology Students Industry (1).2 … …
politics Academic Staff Community (1) R
(1).1.n ….
Culture Users Government (1).n (1).n.n Rn ….
Sciene Government Others (2).1 (2).1.1 A1 ….
Education System (2).1.n …
(2) A …
… ….
(2).n (2).n.n An
Opportunity & Threat (3).1 (3).1.1 I1 ….
… … …
(3) I (3).1.n ….
(3).n (3).n.n In ….
Tasks Study Program (4).1 (4).1.1
Evaluation Strategic Alternative
Objective Problem … (4).1.2 …
Mission
Analysis Issues Identification For Solution
Development Plan
(4) S (4).1.n
Interpretation
Vision (4).n (4).n.n
(5).1 (5).1.1
… … ….
Strength & Weaknesses
(5) E …
(5).n (5).n.n
Organization Resources Process & Output & (6).1 (6).1.1
Human … …
Culture Services Outcome (6) L … …
Financial
Physical (6).n (6).n.n
Information (7).1 (7).1.n Ac 1 ….
… …
Flow of Cooperation (7) Ac …
(7).n (7).n.n Ac n ….
Internal Environment
External Environment (Local, National, Global)
Trend Stake-holders Job Market
Idiology Students Industry
Politics Academic Staff Community
Culture Users Government
Science Government Others
Education System

Opportunity & Threat

Development
Objectives
Evaluation

Plan
Mission Strategic Problem’s Alternatif for
Analysis
Vision Issues Identification Solution
Interpretation
Mandate

Strength & Weaknesses


Stake holder Resources Process & Output &
Culture Human Services Outcome
Financial
Physical
Information
Flow of Cooperation

Internal Environment
Table A.2.4. Identified Problem and Strategic Issues

Strategic Issues
No Identified Problem Remark
R A I S E L Ac
1 xx x xxx
2 xxx x
. Etc.
.

Back
Table A.2.5. Alternative Solution

Strategic
Identified Problems Alternative Solutions
Issues
(1) R (1).1: (1).1.1:
(1).2: (1).1.2:
(1).1.n:

(1).2.1:
(1).2.n:
(2) A (2).1: (2).1.1:
etc. (2).n.n:

(3) I etc etc


(4) S etc etc
(5) E etc etc

(6) L etc etc


(7) Ac etc etc

Back
Table A.2.6. Development Plan

Resources Required
No
Strategic Identified Alternative
Activities DIKS/ Resources
Issues Problems Solutions TPSDP Pemda Others
Yayasan Needed

(1) R (1).1 (1).1.1 R1 ####### ##########


..........  #######
(1).2.1 ......
......... NP #########

R2
R3
.
.....
RN

(2) A A1
.....
.
.
(7) Ac
Back
Background Describe the problems identified in the Self-evaluation pertinent to the planned activity. This may include
also analysis regarding why the problems had occurred and what possible solutions to them. The link
between the planned activities and the problem analysis (SWOT analysis and other conclusion) presented
in Self-evaluation report should be explicitly mentioned, by making explicit references to the relevant
parts, sections of Self-evaluation report (Chapter 2), and page of reference number.

Rationale Discuss in sufficient detail how this activity would possibly resolve the problems referred in the
background section. Empirical or theoretical facts can be used as a ground to support the argument.
Objective State clearly the objective of this activity, including the intended outcomes. Description should clearly
present all direct as well as indirect benefits to the respective S1 or D3 study programs
Mechanism and Explain how the activity, including its sub-activity if any, will be set up and how it will be implemented
design in a narative way.

Resources Explain additional resources needed from the TPSDP investment to implement the activity. If there are
any additional investments required in addition to TPSDP to implement the plan, describe clearly all-past
required
and future investment from sources outside of this project. Explain the plan to prevent double funding of
ACTIVITIES

the same activities by TPSDP and non-TPSDP resources.


Development

(In US $)
Activity Sub-activity Cost Components Source Funding
1 2 3 4 5 6
Plan

R1 <Name of R1.1 TPSDP or Others


activity>
R1.2
etc
Implementation Activities/Sub-activities Yr 1 Yr 2 Yr 3 Yr 4
Schedule (By  Detailed Sub-activity a
Quarter)  Detailed Sub-activity b
 Detailed Sub-activity m
Performance Indicators Baseline Mid Final
indicators of  indicator 1
Activity  indicator 2
 indicator n
Sustainability Describe how this activity will be maintained after the period of this project. Aspects described should
include its financial implication, allocation of resources to support this activity, and management
commitment.
Person in charge Name of staff who will be responsible for this activity.
Schematic Structure of The Sub-Project Proposal.

BOOK I BOOK II BOOK III

General Information General Informatio General Information


Chapter I
SE
RT
REPO

Chapter II Self Evaluation Self Evaluation Self Evaluation


Report Report Report

Chapter III
Proposed Proposed Proposed
Development Development Development
SPP Plan Plan Plan

Appendix Chapter I Appendix Chapter I Appendix Chapter I


Appendices Appendix Chapter II Appendix Chapter II Appendix Chapter II
Appendix Chapter III Appendix Chapter III Appendix Chapter III

-- - - - -- - - - -- - - -
Book I –– 11I-K
I-K
of
of K
K I-K
Book II – 1 of L
I-K
Book III – 1 of M

Book I – 2 of K Book III - 2 of M


Book
Book II
II –
–22 of
of L
L
Book I – K of K Book II – L of L Book
Book III
III –– M
M of
of M
M
The Content and Structure of The Sub-Project Proposal.
Book I Book II Book III
Strengthening Study Program New Study Program Institutional Support System
Abstract BERBEDA
Chapter I :General Information SETIAP PROGRAM STUDI/ISS
Section 1.1 Introduction
Section 1.2 Five Years University Development Plan
Section 1.3 Study Program/ISS Development Plan
Section 1.4 SPMU Organization
Section 1.5 Summary of Univ./Polytechnic Proposed Budget

Chapter II: Self Evaluation Report Chapter II: Feasibility Study Chapter II: Self Evaluation
Conclusion Conclusions Report/Feasibility Study
Section 2.1. Background Section 2.1. Background Conclusions
TECHNOLOGICAL AND Section 2.2. Environmental Setting Section 2.2. External Environmental Section 2.1. Background
PROFESSIONAL SKILLS
DEVELOPMENT SECTOR PROJECT Section 2.3. Graduate Setting Section 2.2. Environmental Setting
(TPSDP) Section 2.4. Educational Process Section 2.3. Curriculum Section 2.3. Services/Products
SUB PROJECT
PROPOSAL BATCH III Section 2.5. Students Section 2.4. Students Section 2.4. Implementation Processes
(Name of University)
Section 2.6. Management and Organization Section 2.5. Graduates Section 2.5. Management and Organization
(Name of SPMU)
Section 2.7. Staff; Academic and Supporting Section 2.6. Physical Facilities Section 2.6. Staff
Section 2.8. Physical Facilities Section 2.7. Staff Section 2.7. Supporting Facilities
Directorate General of Higher Education Section 2.9. Laboratories Section 2.8. Funding Section 2.8. Funding
Ministry of National Education Section 2.10. Library Section 2.9. Administration & Section 2.9. Performance Indicators
2003
Section 2.11. Curriculum Organization Section 2.10. Identified Problems
Section 2.12.Funding Section 2.10. Time Frame Section 2.11. Alternative Solutions
Section 2.13. Performance Indicators Section 2.11. Target Performance Section 2.12. Development Plan
Section 2.14. Identified Problems Indicators
Section 2.15. Alternative Solutions Section 2.12. Identified Problems
Section 2.16. Development Plan Section 2.13. Alternative Solutions
Section 2.14. Development Plan and
Deployment Approach

Chapter III : Proposed Chapter III : Proposed Chapter III : Proposed


Development Plan Development Plan Development Plan
Section 3.1. Background Section 3.1. Background Section 3.1. Background
Section 3.2. Objective and Strategy Section 3.2. Objective and Strategy Section 3.2. Objective and Strategy
Section 3.3. Improving RAISE ++ Section 3.3. Improving RAISE ++ Section 3.3. Improving RAISE ++
Section 3.4. Performance Target Section 3.4. Performance Target Section 3.4. Performance Target
Section 3.5. Implementation Plan Section 3.5. Implementation Plan Section 3.5. Implementation Plan
Section 3.6. Summary of Proposed Budget Section 3.6. Summary of Proposed Section 3.6. Summary of Proposed
Section 3.7. Project Benefit and Economic Budget Budget
Analysis Section 3.7. Project Benefit and Section 3.7. Project Benefit and
Appendices Economic Analysis Economic Analysis
Appendices Appendices
STRUCTURE OF SUB PROJECT PROPOSAL
ABSTRACT CHAPTER III Proposed Development Plan
Sect 3.1 Background
CHAPTER I General Information Sect 3.2 Objective and Strategy
Sect 1.1 Introduction Sect 3.3 Improving RAISE ++
Sect 1.2 University Development Plan Sect 3.4 Performance Target
Sect 1.4 Study Program Development Plan Sect 3.5 Implementation Plan
Sect 3.6 Summary of Proposed Budget
Sect 1.4 SPMU Organization Sect 3.7 Project Benefit and Economic Analysis
Sect 1.5 Summary of Univ./Poly. Proposed Budget Appendices

CHAPTER II Self Evaluation Report


Conclusion
Sect 2.1 Background
Sect 2.2 Environmental Setting
I
Sect 2.3 Graduate Book
Sect 2.4 Educational Process
Sect 2.5 Students
Sect 2.6 Management and Organization
Sect 2.7 Staff; Academic and Supporting
Sect 2.8 Physical Facilities
Sect 2.9 Laboratories
Sect 2.10 Library
Sect 2.11 Curriculum
Sect 2.12 Funding
Sect 2.13 Performance Indicators BOOK I
Sect 2.14 Identified Problems STRENGTHENING STUDY PROGRAM
Sect 2.15 Alternative Solutions
Sect 2.16 Development Plan
STRUCTURE OF SUB PROJECT PROPOSAL
ABSTRACT CHAPTER III Proposed Development Plan
Sect 3.1 Background
CHAPTER I General Information Sect 3.2 Objective and Strategy
Sect 1.1 Introduction Sect 3.3 Improving RAISE ++
Sect 1.2 University Development Plan Sect 3.4 Performance Target
Sect 1.4 Study Program Development Plan Sect 3.5 Implementation Plan
Sect 3.6 Summary of Proposed Budget
Sect 1.4 SPMU Organization Sect 3.7 Project Benefit and Economic Analysis
Sect 1.5 Summary of Univ./Poly. Proposed Budget Appendices

CHAPTER II Feasibility Study


Conclusion
Sect 2.1 Background
Sect 2.2 External Environmental Setting
I
Sect 2.3 Curriculum Book I
Sect 2.4 Students
Sect 2.5 Graduate
Sect 2.6 Physical Facilities
Sect 2.7 Staff
Sect 2.8 Funding
Sect 2.9 Administration and Organization
Sect 2.10 Time Frame
Sect 2.11 Target Performance Indicators
Sect 2.12 Identified Problems
Sect 2.13 Alternative Solutions BOOK II
Sect 2.14 Development Plan and Deployment Approach NEW STUDY PROGRAM
STRUCTURE OF SUB PROJECT PROPOSAL
ABSTRACT CHAPTER III Proposed Development Plan
Sect 3.1 Background
CHAPTER I General Information Sect 3.2 Objective and Strategy
Sect 1.1 Introduction Sect 3.3 Improving RAISE ++
Sect 1.2 University Development Plan Sect 3.4 Performance Target
Sect 3.5 Implementation Plan
Sect 1.4 ISS Development Plan
Sect 3.6 Summary of Proposed Budget
Sect 1.4 SPMU Organization Sect 3.7 Project Benefit and Economic Analysis
Sect 1.5 Summary of Univ./Poly. Proposed Budget
Appendices

CHAPTER II Self Evaluation Report/


Feasibility Study
Conclusion
Sect 2.1 Background
II
Sect 2.2 Environmental Setting B o ok I
Sect 2.3 Services/Products
Sect 2.4 Implementation Process
Sect 2.5 Management and Organization
Sect 2.6 Staff
Sect 2.7 Supporting Facilities
Sect 2.8 Funding
Sect 2.9 Performance Indicators
Sect 2.10 Identified Problems
Sect 2.11 Alternative Solutions BOOK III
Sect 2.12 Development Plan
INSTITUTIONAL SUPPORT SYSTEM
STRUCTURE OF SUB PROJECT PROPOSAL (NUMBER OF PAGES)
ABSTRACT CHAPTER III Proposed Development Plan
Sect 3.1 Background
CHAPTER I General Information Sect 3.2 Objective and Strategy
Sect 1.1 Introduction Sect 3.3 Improving RAISE ++
Sect 1.2 University Development Plan Sect 3.4 Performance Target
Sect 1.4 Study Program Development Plan Sect 3.5 Implementation Plan
Sect 3.6 Summary of Proposed Budget
Sect 1.4 SPMU Organization Sect 3.7 Project Benefit and Economic Analysis
Sect 1.5 Summary of Univ./Poly. Proposed Budget Appendices

CHAPTER II Self Evaluation Report


Conclusion
Sect 2.1 Background
Sect 2.2 Environmental Setting Total pages :
Sect 2.3 Graduate Abstract
Sect 2.4 Educational Process
Sect 2.5 Students
Chapter I (10 pages)
Sect 2.6 Management and Organization Chapter II (Max 90 pages)
Sect 2.7 Staff; Academic and Supporting Chapter III
Sect 2.8 Physical Facilities
Sect 2.9 Laboratories
Including Appendices
Sect 2.10 Library
Sect 2.11 Curriculum PRINTED ON

!
Sect 2.12 Funding
BOTH
Sect 2.13 Performance Indicators
SIDE OF PAPER
Sect 2.14 Identified Problems
Sect 2.15 Alternative Solutions
Max 250 Pages
Sect 2.16 Development Plan
OTHER CONSIDERATION IN SELECTION PROCESSES

 5 Study Programs Sub project


 US$ 8 Million Proposals
(for 3 Batches) Sub-Project
Proposal
Selection
NSP SSP
Criteria
ISS
ISS Evaluation
SSP NSP
Integrated
pass
New Study Program:
 No Student Enrolled
Site  No DGHE Decree
Visit  No Accreditation Mark

Revenue Capacity VS
Proposed Investment
ELIGIBLE COST COMPONENT

BUDGET PLAFOND
Program Description Max (US$)
Strengthening the S1 Program 1.300.000
existing study
D3 Program 1.300.000
program
D3 Program as RRP 1.600.000
Establishing new S1 1.500.000
study program
D3 1.500.000
Institutional Support Each Program 100.000
ELIGIBLE COST COMPONENT

STAFF DEVELOPMENT

DEGREE NON DEGREE

DOMESTIC

OVERSEAS
Staff Development
Degree Program

1. Waktu pemberian beasiswa maksimum sbb :

S2 domestic 2,5 tahun,


S3 domestic 3,5 tahun (Setelah S2)
S2 overseas 2 tahun,
S3 overseas 3,5 tahun (Setelah S2)
Staff Development
Degree Program
2.  Unit Cost Maksimum:

Overseas:
S2/S3 degree: US$ 27000/orang-tahun termasuk tiket pp 1x.

Domestic:
S2 degree Rp 19,56 juta/orang-tahun
S3 degree Rp. 21,12 juta/orang-tahun
belum termasuk tiket pp 1x.

Biaya tiket: at cost.


Staff Development
Non-Degree Program

 Seminar internasional ke luar negeri membawakan


makalah dengan maksimum US$ 3000/makalah,
termasuk tiket pp.
 Overseas short-term training minimum 1 bulan,
maksimum 3 bulan dengan dana maksimum US$ 4000/
orang-bulan termasuk tiket pp 1x. (untuk satu bulan
diluar tiket pp)
 Domestic training/magang industri maksimum 3 bulan,
minimum 1 bulan dengan dana maksimum Rp. 7 juta/
orang-bulan belum termasuk tiket pp 1x (at cost)
 Domestic Degree Training tidak dilakukan di
perguruan tingginya sendiri.
Contoh Komponen Biaya Overseas Degree
UK(GBP) USA (US$)
No. Description
UNIT-COST MAN-YEAR UNIT-COST MAN-YEAR
A. Master (S-2) Program (2 years)
I. Direct Cost
1 Stipends/living allowance/Month 560 600 6,960 875 1,100 11,850
2 Book allowance/Year 160 250 205 500 750 625
3 Arrival and clothing allowance *) 600 700 325 875 1,100 494
4 Postage & Shipping allowance *) - 150 75
5 Tuition and fee - at cost/year 10000 13,000 11,500 8,500 15,000 11,750
6 International airfare - return (at cost)*) 1300 1,500 700 2,500 3,000 1,375
7 Special program *) 500 500 250 650 850 375
8 Thesis/research allowance *) 175 250 106 250 600 213
9 Medical insurance/year - 400 500 450
10 Departure & excess baggage *) 250 250 125 -
11 Home office registration *) 40 50 23 -
12 Visa application/immigration fee *)
13 Special course, tutoring - at cost *)
14 Pre-accademic program -at cost *)
15 University application fee-at cost *)
Total 20,194 27,206
Equivalent to USD 32,027 27,206
Contoh Komponen Biaya Overseas Degree

Australia (AUD) Canada (CAD)


No. Description
UNIT-COST MAN-YEAR UNIT-COST MAN-YEAR
A. Master (S-2) Program (2 years)
I. Direct Cost
1 Stipends/living allowance/Month 1,230 1,400 15,780 1,000 1,100 12,600
2 Book allowance/Year 720 800 760 1,200 1,300 1,250
3 Arrival and clothing allowance *) 1,230 1,400 658 1,000 1,100 525
4 Postage & Shipping allowance *) - 250 250 250
5 Tuition and fee - at cost/year 15,000 25,000 20,000 6,500 15,000 10,750
6 International airfare - return (at cost)*) 2,500 3,000 1,375 3,000 4,000 1,750
7 Special program *) 1,300 1,500 700 750 860 403
8 Thesis/research allowance *) 400 600 250 1,500 1,500 750
9 Medical insurance/year 274 350 312 960 1,000 980
10 Departure & excess baggage *) 200 200 100 -
11 Home office registration *) - -
12 Visa application/immigration fee *) 450 450 225 125 125 63
13 Special course, tutoring - at cost *)
14 Pre-accademic program -at cost *)
15 University application fee-at cost *)
Total 40,160 29,321

Equivalent to USD 21,144 19,222


Contoh Komponen Biaya Overseas Degree
Netherland(NLG) Japan (Y)
No. Description
UNIT-COST MAN-YEAR UNIT-COST MAN-YEAR
A. Master (S-2) Program (2 years)
I. Direct Cost
1 Stipends/living allowance/Month 1,700 1,900 21,600 200,000 250,000 2,700,000
2 Book allowance/Year 1,200 1,200 1,200 90,000 90,000 90,000
3 Arrival and clothing allowance *) 425 425 213 200,000 250,000 112,500
4 Postage & Shipping allowance *)
5 Tuition and fee - at cost/year 14,500 20,000 17,250 800,000 1,200,000 1,000,000
6 International airfare - return (at cost)*) 3,750 3,750 1,875 150,000 150,000 75,000
7 Special program *) 960 960 480
8 Thesis/research allowance *) 50,000 50,000 25,000
9 Medical insurance/year 1,020 1,020 1,020 102,000 102,000 102,000
10 Departure & excess baggage *) 250 250 125 25,000 25,000 12,500
11 Home office registration *) - -
12 Visa application/immigration fee *) 125 125 63
13 Special course, tutoring - at cost *)
14 Pre-accademic program -at cost *)
15 University application fee-at cost *)
Total 43,826 4,117,000

Equivalent to USD 18,217 35,491


ELIGIBLE COST COMPONENT
Program Development

 Program development is aimed to strengthen management capacity and


priority disciplines.
 To strengthen management capacity will be limited to workshop
and laboratory management, maintenance logistics, quality
assurance system, and educational technology.
 To strengthen priority disciplines will be limited to curriculum
review/revision/development, industrial liaison process,
entrepreneurship development, and skill development. This
component is aimed to facilitate sustainability of project gains at
institutional level and to promote the quality of teaching learning
process.

 Program development should strongly relate to the designed activities and


support expected contribution on the improvement of RAISE ++.
 The frequency and the proposed budget should be rationale and sound
justifiable.
ELIGIBLE COST COMPONENT

CIVIL WORKS

SSP NSP

Renovation-
Upgrading

Limited
Construction

With strong judgements


CIVIL WORK

1.  Renovasi major : perbaikan bangunan yang


termasuk berat tapi tidak merubah
volume dan tidak merobohkan
bangunan lama.
2.  Renovasi minor : perbaikan-perbaikan ringan pada
bangunan yang ada.
3. Pembangunan Baru: Program Studi Baru dapat
membangun gedung baru dengan
catatan: 60% dibiayai oleh PT
sendiri atau sumber lain.
4.  Dana Civil work sebagian harus berasal dari DRK
dalam bentuk cash atau in kind
5.  Pelaksanaan Civil work hanya dilakukan pada tahun
I dan II
CIVIL WORK

UNIT COST

New Building is Rp. 1.450.000, - per square meter


Major renovation is Rp. 750.000, - per square meter
Minor renovation is Rp. 500.000, - per square meter

Unit cost riil dapat disesuaikan dengan harga didaerah


masing-masing dengan maksimum seperti petunjuk
sbb:
Major renovation = 65% X New Building Cost
Minor renovation= 45% X New Building Cost
ELIGIBLE COST COMPONENT

EQUIPMENT

Teaching Class Class


Lab Room Utilities

Repair-
Upgrade

Limited
Procurement

Improve Teaching Learning Process


EQUIPMENT

1.  Teaching dan laboratory equipment untuk S1, bukan


untuk research
2. Alat yang diusulkan pada tahun I harus dilengkapi
dengan spesifikasi yang jelas
3. Unit cost yang diajukan sudah harus termasuk biaya
pengiriman, pemasangan, training penggunaan dan
jaminan/servis satu tahun.
4. Unit cost yang diajukan sudah harus termasuk biaya
pengiriman, pemasangan, training penggunaan, pajak
dan jaminan/servis satu tahun.
5. Pemaketan tidak boleh di-pecah pecah dan harus
dipahami sistem pengadaannya
6. Pengadaan harus memperhatikan program lain yang
terkait. Contoh Gedung, kurikulum dll.
7. Dilaksanakan hanya pada tahun pertama dan kedua

Maksimum kebutuhan ± 40 % dari total budget.


Appendix-3.15
List of Proposed Equipment (Year1 to Year2)

           
Name of Laboratory/ Name of equipment Qty Unit Estimated Remark
Workshop/Units Cost Cost
I. ……….. 1……….        
2………
3………..
II………….. 1……….        
2……….
3………..
           
 
 
 
           
 
 
 
ELIGIBLE COST COMPONENT

FURNITURE

Class Room

Laboratory

Office

Institutional
Support

Limited Furniture
FURNITURE

Eligible Furniture
to be proposed are limited to classroom and
laboratory purposes.
Office furniture’s, including furniture for multi-
function halls, are not eligible to be proposed to
TPSDP.

Limited furniture for the institutional supports unit


may be proposed in this competition.
ELIGIBLE COST COMPONENT

TECHNICAL ASSISTANCE

Planning & Development

Curriculum Development
International
Research Activities
Domestic
Networking- Revenue Generating

Others Academic Act.


Technical Assistance
International & National Consultant

Definisi
 
Program technical assistance adalah suatu bantuan
tenaga ahli baik internasional maupun nasional untuk
membantu program studi dalam meningkatkan atau
memperbaiki RAISE++.
(International and domestic consulting services can be
proposed to improve the proposed program management,
assist planning and strategy development, curriculum
development, as external examiners, and other academic
activities that directly benefit undergraduate (S-1)
education program.)
Prioritas kepakaran menurut menurut Loan Agreement

No Prioritas kepakaran International National

1 Competency based curriculum √ √

2 Engineering relevancy specialist √ √

3 Laboratory teaching methodology √ √

4 Instructional resource development √ √

5 Basic science specialist - √

6 Agriculture curriculum & instruction √ √


Approach development specialist
7 Business/Management studies specialis √ √

8 Law specialist √ √

9 Accounting specialist √ √

10 Environmental Eng. Consultant √ √


11 Computer system engineering √ √

12 Computer science consultant √ √

13 Specialist training consultant/ √ √


visiting professor

14 Entrepreneurship technical - √
consultant
15 Woman in development √ √
specialist
16 Employer Liaison consultant √ √
Syarat-syarat
 
     Konsultan tidak ditugaskan untuk mengajar, seperti untuk
menggantikan staf pengajar yang mendapat tugas belajar,
atau hanya sebagai pembicara dalam suatu seminar.

      Lama penugasaan minimal satu bulan dan maksimal 3 bulan.

      Konsultan harus bekerja penuh (bukan paruh waktu)

      Konsultan tidak boleh dari institusi internal.

      Beban kerja dan waktu yang rational.

      Konsultan internasional hanya diperbolehkan dari negara


anggota ADB.
Syarat-syarat
TA tahun pertama harus ada kerangka acuannya (TOR) yang
setidak-tidaknya terdiri dari judul kegiatan, latar belakang, tujuan,
lingkup kerja, hasil yang diharapkan, pelaporan, beban dan jadwal
kerja. Nama, asal negara, institusi dan lama penugasan.

Unit Cost
 
International Consultant
Billing Rate Max:US$ 15,500 per person-month (including
International travel, economic class).

National Consultant
Billing Rate Max Rp. 15.000.000, - per person-month (excluding
Domestic travel)
Besaran biaya harus sudah mencakup:
honorarium (remunerasi)
transportasi udara (kelas ekonomi),
kelebihan bagasi,
perjalanan domestik
bagasi yang tidak dibawa sendiri
tempat tinggal sementara
biaya komunikasi
dokumen perjalanan
transport ke bandara
tunjangan harian
biaya pelaporan
ELIGIBLE COST
COMPONENT
INSTRUCTIONAL MATERIALS

Books

Related
Materials

Selected
Journal

With strong argument on its


benefit to the proposed programs
ELIGIBLE COST COMPONENT

TEACHING & RESEARCH GRANT


Target
Grant Objectives Person Procedure

Improve
Teaching Staff Competition
Teaching Method

Support Supervision Staff +


Research Competition
Student Final Project Student

Student Support limited number


Student Competition
project student Project

Topics should be in line with Research Agenda


TEACHING GRANT

Definisi
Teaching grant merupakan dana hibah yang
diberikan kepada staf pengajar program studi untuk
memperbaiki kinerja mengajar dan meningkatkan
efisiensi dan efektivitas pengajaran.

Tujuan
Untuk memberikan dorongan kepada staf pengajar
dalam upayanya untuk memperbaiki metodologi
belajar-mengajar mata kuliah yang diasuhnya
Implementasi dan Persyaratan

 Periode pelaksanaan: satu tahun (satu semester


perancangan, satu semester implementasi)
 Biaya: maksimum Rp 20.000.000,- per grant/tahun
 Metode: kompetisi murni
 Cakupan: maksimal 25% dari jumlah staf pengajar
yang eligible selama periode proyek (3,5 tahun)  
 Staf pengajar yang eligible merupakan pengajar
mata kuliah pada Program Studi
 Seorang staf pengajar hanya mendapat satu grant
selama periode proyek
RESEARCH GRANT
Definisi
Research grant merupakan dana hibah yang diberikan
untuk memperbaiki kualitas riset staf pengajar program
studi dikaitkan dengan pembimbingan skripsi
mahasiswa.

Tujuan
Hibah ini bertujuan untuk memberikan dorongan kepada
staf pengajar/ pembimbing skripsi untuk meningkatkan
kualitas riset, mempercepat kelulusan mahasiswa, dan
sekaligus mengembangkan budaya meneliti.
Implementasi dan Persyaratan
 Periode pelaksanaan: satu tahun
 Biaya: maksimum Rp 30.000.000,- per grant/tahun
 Metode: kompetisi murni
 Cakupan: maksimal 30% dari jumlah staf pengajar
program studi selama periode proyek (3,5 tahun)  
 Pengajuan proposal dapat secara tim dengan jumlah
anggota maksimal 3 orang termasuk ketua tim
 Setiap grant harus melibatkan minimal 3 mahasiswa
 Staf pengajar boleh mendapatkan lebih dari satu grant
selama proyek
Student Grant

Definisi
Student grant merupakan dana hibah yang diberikan
kepada mahasiswa dalam upaya meningkatkan kualitas
riset dan mempercepat kelulusan mahasiswa.

Tujuan
Hibah ini bertujuan untuk menumbuhkan inisiatif dan
budaya meneliti pada mahasiswa yang berhubungan
dengan pelaksanaan tugas akhir/skripsi
Implementasi dan Persyaratan

 Periode pelaksanaan: satu semester


 Biaya: maksimum Rp 5.000.000,- per grant
 Metode: kompetisi murni
 Cakupan: 10% dari total mahasiswa yang memenuhi
syarat melaksanakan skripsi atau 10 grant per tahun. 
 Setiap proposal diajukan dengan persetujuan
pembimbing skripsi
 Setiap mahasiswa hanya boleh mendapatkan satu grant
selama periode proyek
ELIGIBLE COST COMPONENT

PROJECT MANAGEMENT

Provide incentive for limited


Aim
Number of SPMU

 5% of Total Proposed
Amount Investment
DRK COMMITMENT

DRK
Institution’s commitment to sustain the
Aim
development

Supporting Demonstrated by formal statement from


Authority Rector
Level of funding at least adequate for
Amount of Fund Maintenance and Operational cost
( >  of total proposed investment)
Matching-fund allocated from Self Revenue
Source of fund
Generated fund (DRK)
Subproject Management Unit
STRUCTURE OF SUB-PROJECT MANAGEMENT UNIT

RECTOR
Executive Board

Vice Rector Vice Rector Vice Rector


Academic Administration Development

SPMU
Director
Quality Assurance

Ass.Dir for Academic/ Ass.Dir for Finance/


Program Affair Administrative Affairs

Strengthening the
existing study New study Institutional
program program

Quality Quality
Secretary Secretary
Assurance Assurance

PIC PIC PIC PIC PIC PIC


Source and Proposed Budget Composition

Source of Budget Proposed Budget Composition

ADB 80%

Investment Min. 95 %
GOI 12%

Institution (DRK) Min. 8 %


Project Max. 5 %
Management
Total 100% Total 100%
Taxes – PPN 10%
- PPh 22 1.5%
Total Contract 111.5%
DRK COMMITMENT

INCENTIVES Maintenance and Operational Cost

Lab Teach. Office Others


Target Personal involve in managing equip. Equip. Equip.
Person project
Maintenance

30% of total 3,5 years


Amount DRK Operational

DRK
FUND

IN KIND CIVIL WORKS

Office’s Staff Salary SSP NSP


Renovation-
Office operational Cost Upgrading
Limited
Office Space and Equip. Construction

With strong judgements


Project Management

This component aims to provide incentives for a limited number of Sub-


project Management Unit (SPMU) officers and activities such as
meetings, office consumables, and coverage of communication costs
to maintain Internet connections.

Domestic travel is needed for periodic workshops on implementation


conducted between grantees.

Eligible Implementing officers are


1 Executive director,
2 Assistant directors for academic/program affair and
administrative/finance affair, and
Key person from each study program and institutional support
system, and additional support staffs as needed.

The Proposed Budget for this component should not exceed 5%


of the total proposed investment.
Implementasi dan Persyaratan

Cost Breakdown
Staff Remuneration (per man-month) (Maximum)
Director of SPMU : Rp. 1000,000 -
Assistant director for academic affairs : Rp. 750,000 -
Assistant director for financial affairs : Rp. 750,000 -
Representative from awarded programs : Rp. 750,000.-
Supporting staff : Rp. 450,000 - Rp 600.000
 
Consumables (per month) : Rp. 2,000,000.-
 
Tender committee expenses :Rp.6,000,000.-per program
 
Travel allowance (per trip)
Inside Pulau Jawa : Rp. 1,500,000.-
Outside Pulau Jawa : Rp. 2,500,000.-
 
Other Expenditures (max. cost)
Telephone & internet connection : Rp. 1,500,000.-per month
Courier services : Rp. 500,000.- per month
Copying, printing, etc : Rp. 1,000,000.- per month
Regular internal meeting : Rp. 1,500,000.- per meeting
Tender committee expenses : Rp. 6,000,000.- per contract.
Table A.1.1. Summary of 3.5 Years Proposed Budget from All Programs

First Year Second Year Third Year Forth Year Total SP


Program
TPSDP DRK TPSDP DRK TPSDP DRK TPSDP DRK TPSDP DRK

Strengthening SP 1
……… SP n
Establishing New SP 1
……… SP n
Institutional Support 1
……… SP n
Annual DRK
Total Proposed Budget

in US $
Table A.1.2. Summary of 3.5 Years Budget by Component for all Programs*)
Strengthening New Inst. Support
Total
No. Program SP 1 to n SP 1 to n 1 to n
(US $)
(US $) (US $) (US $)
1 Staff Development Staff DevelopmentStaff Development
2 Civil Work Civil Work Civil Work Civil Work
3 Equipment Equipment Equipment Equipment
4 Furniture Furniture Furniture Furniture Furniture
... ... ... ... ...
Total (US $) Total (US $) Total (US $) Total (US $)
DRK (US $) DRK (US $) DRK (US $) DRK (US $)
DRK (%) DRK (%) DRK (%) DRK (%) DRK (%)

*)
This table is only for Batch III Programs
C. Proposed Budget
C. Proposed Budget
Table A.1.3. First Year University Proposed Budget*)
Unit Cost Total Cost Total DRK
No. Program Unit Quantity
(US $) (US $) (US $)
Strengthening Study Program 1 to n
1 Staff Development Staff Development
Staff Development
2 Civil Work Civil Work Civil Work Civil Work
3 Equipment Equipment Equipment Equipment
Etc Furniture Furniture Furniture Furniture Furniture
Sub-Total SSP ... ... ... ... ...
New Study Program 1 to n
1 Staff Development Staff Development
Staff Development
2 Civil Work Civil Work Civil Work Civil Work
Etc Furniture Furniture Furniture Furniture Furniture
Sub-Total NSP ... ... ... ... ...
Institutional Support 1 to n
1 Staff Development Staff Development
Staff Development
2 Civil Work Civil Work Civil Work Civil Work
Etc Furniture Furniture Furniture Furniture Furniture
Sub-Total ISP ... ... ... ... ...
Total Furniture Furniture Furniture Furniture Furniture
*)
This table is only for Batch III Programs
Table A.3.4a. Schedule of Activities

Strategic Activiti-
No. Year 1 Year 2 Year 3 Y4
Issues es
                           
R1
1 R                            
R2
                           
...Etc
                           
A1
2 A                            
A2
                           
…Etc
                           
I1
3 I                            
I2
                           
…etc
                           
etc
Etc …                              
                             
Table A.3.4b. Project Cost by Activities and Components

(US$)
Procurement Technical
Staff Development Research and Study
equipment Assistance
Degree Non Degree Civil Instructional Program
No. Strategic Issue Activities Works Material Development Teaching Research Student Other
Total
Equipment Furniture Domestic Overseas
Grant Grant Grant
Overseas Domestic Overseas Domestic

1 Relevance Activity 1
Activity 2
...
Activity n
2 Academic Activity 1
Atmosphere Activity 2
...
Activity n
3 Internal Activity 1
Efficiency Activity 2
...
Activity n
4 Sustainability Activity 1
Activity 2
...
Activity n
5 Efficiency and Activity 1
Productity Activity 2
...
Activity n
6 Leader Ship Activity 1
Activity 2
...
Activity n
7 Access and Activity 1
Equity Activity 2
...
Activity n

Total
Table A.3.4c. Summary Of The Total Proposed Budget

YEAR-1 YEAR-2 YEAR-3 YEAR-4 TOTAL


Eligible Cost Components ADB GOI (Rp) ADB GOI (Rp) ADB GOI (Rp) ADB GOI (Rp) ADB GOI (Rp)
%
US$ Rp TPSDP DRK US$ Rp TPSDP DRK US$ Rp TPSDP DRK US$ Rp TPSDP DRK US$ Rp TPSDP DRK
1. Staff Development
Domestic degree training
Domestic non degree training
Overseas degree training
Overseas non degree training
2. Civil Works
3. Furniture and Equipment
Furniture
Equipment
4. Program Development
5. Instructional Materials
6. Consultant Services
International
Domestic
7. Research and Studies
8. Project Management
Operational support
O&M of Facilities
Sub-PIU Operation
TOTAL
NOTE 80,00% 12,00% 8,00% 80,00% 12,00% 8,00% 80,00% 12,00% 8,00% 80,00% 12,00% 8,00% 80,00% 12,00% 8,00% 100

The budget proposed from TPSDP consists of Government counterpart budget and ADB Loan
Sekian
Terima Kasih
KAMI TUNGGU PROPOSALNYA TANGGAL 4 JULI 2003
PALING LAMBAT JAM 24.00 WIB

The End

Batch III