Professional Documents
Culture Documents
Hong Kong Baptist Niversity
Hong Kong Baptist Niversity
Hong KongKong
Baptist
niversity
Baptist University
Department of Accounting
Department
and Lawof Finance
& Decision Sciences
Postgraduate Diploma
5
in
Professional Accounting
FINE3015 Net Present Value
Corporate Finance
ACCT 7650 and Other
Financial Management Investment Criteria
Chapter Outline
3
Project Example Information
5
NPV – Decision Rule
7
Payback Period
11
Discounted Payback Period
12
Computing Discounted Payback for
the Project
Assume we will accept the project if it pays
back on a discounted basis in 2 years.
Compute the PV for each cash flow and
determine the payback period using discounted
cash flows
Year 1: 165,000 – 63,120/1.121 = 108,643
Year 2: 108,643 – 70,800/1.122 = 52,202
Year 3: 52,202 – 91,080/1.123 = -12,627 project pays
back in year 3
Do we accept or reject the project?
13
Computing Discounted Payback for
the Project
Assume we will accept the project if it pays
back on a discounted basis in 2 years.
Compute the PV for each cash flow and
determine the payback period using discounted
cash flows
Year 1: 165,000 – 63,120/1.121 = 108,643
Year 2: 108,643 – 70,800/1.122 = 52,202
Year 3: 52,202 – 91,080/1.123 = -12,627 project pays
back in year 3
Do we accept or reject the project?
14
Advantages and Disadvantages of
Discounted Payback
Advantages Disadvantages
Includes time value of May reject positive
money NPV investments
Easy to understand Requires an arbitrary
Does not accept cutoff point
negative estimated Ignores cash flows
NPV investments beyond the cutoff point
when all future cash Biased against long-
flows are positive term projects, such as
Biased towards R&D and new products
liquidity
15
1. You are considering the following two mutually exclusive projects.
The required rate of return is 10.75 percent for project A and 12
percent for project B. Which project should you accept and why?
a. project A; because it has the lower required rate of return
b. project A; because its NPV is about $796 more than the NPV of
project B
c. project B; because it has the largest total cash inflow
d. project B; because it returns all its cash flows within two years
e. project B; because it is the largest sized project
16
Average Accounting Return
18
Example—ARR (continued)
$105 $30 $0
Average net profit
3
$45
19
Example—ARR (continued)
20
Advantages and Disadvantages of
AAR
Advantages Disadvantages
Easy to calculate Not a true rate of
Needed information return;
will usually be time value of money is
available ignored
Uses an arbitrary
benchmark cutoff rate
Based on accounting
net income and book
values, not cash flows
and market values
21
Internal Rate of Return ( 内部回报率 )
22
IRR – Definition and Decision
Rule
=Discount rate that equates the present
value of the future cash flows with the
initial cost.
24
NPV Profile for the Project
70,000
IRR = 16.13%
60,000
50,000
40,000
30,000
NPV
20,000
10,000
0
-10,000 0 0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18 0.2 0.22
-20,000
Discount Rate 25
Advantages of IRR
26
Summary of Decisions for the
Project
Summary
Net Present Value Accept
Payback Period Reject
Discounted Payback Period Reject
Average Accounting Return Reject
Internal Rate of Return Accept
27
2. Colin is analyzing a project and has gathered the
following data. Based on this data, what is the average
accounting rate of return? The firm depreciates it
assets using straight-line depreciation to a zero book
value over the life of the asset.
a. 6.66 percent
b. 13.31 percent
c. 20.66 percent
d. 26.62 percent
e. 31.31 percent
28
NPV vs. IRR
29
Multiple Rates of Return
Assume you are considering a project for
which the cash flows are as follows:
0 –$252
1 1431
2 –3035
3 2850
4 –1000
30
IRR and Non-conventional Cash
Flows
When the cash flows change sign more
than once, there is more than one IRR
If you have more than one IRR, which
one do you use to make your decision?
31
Multiple Rates of Return
What’s the IRR? Find the rate at which
the computed NPV = 0:
at 25.00%: NPV = 0
at 33.33%: NPV = 0
at 42.86%: NPV = 0
at 66.67%: NPV = 0
Two questions:
1. What’s going on here?
2. How many IRRs can there be?
32
Multiple Rates of Return
NPV
$0.06
$0.04
IRR = 25%
$0.02
$0.00
IRR = 42.86%
($0.04)
($0.06)
($0.08)
33
Another Example – Non-
conventional Cash Flows
Suppose an investment will cost $90,000
initially and will generate the following
cash flows:
Year 1: 132,000
Year 2: 100,000
Year 3: -150,000
The required return is 15%.
Should we accept or reject the project?
34
NPV Profile
$4,000.00
IRR = 10.11% and 42.66%
$2,000.00
$0.00
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5 0.55
($2,000.00)
NPV
($4,000.00)
($6,000.00)
($8,000.00)
($10,000.00)
Discount Rate
35
Summary of Decision Rules
37
Example With Mutually Exclusive
Projects
Period Project Project The required return
A B for both projects is
0 -500 -400 10%.
1 325 325
Which project
2 325 200 should you accept
IRR 19.43 22.17 and why?
% %
NPV 64.05 60.74
38
NPV Profiles
$160.00
$140.00 IRR for A = 19.43%
$120.00 A IRR for B = 22.17%
$100.00
$80.00 Crossover Point = 11.8%
A
NPV
$60.00
B
$40.00 B
$20.00
$0.00
($20.00) 0 0.05 0.1 0.15 0.2 0.25 0.3
($40.00)
Discount Rate
39
Conflicts Between NPV and IRR
40
Profitability Index
41
Profitability Index
PV of inflows
PVI
Initial cost
43
Example—PVI (continued)
500 1 000
NPV 1100
1.10 1.10 2
$181
181 1100
PVI
1100
1.1645
44
Example—PVI (continued)
45
Advantages and Disadvantages of
Profitability Index
Advantages Disadvantages
Closely related to May lead to incorrect
NPV, generally decisions in
leading to identical comparisons of
decisions mutually exclusive
Easy to understand investments
and communicate
May be useful when
available investment
funds are limited
46
Capital Budgeting In Practice
47
3. When the present value of the cash inflows exceeds the
initial cost of a project, then the project should be:
a. accepted because the internal rate of return is positive.
b. accepted because the profitability index is greater than 1.
c. accepted because the profitability index is negative.
d. rejected because the internal rate of return is negative.
e. rejected because the net present value is negative.
48