Professional Documents
Culture Documents
Reynolds Construction Company: Submitted To: DR Indu Uprety
Reynolds Construction Company: Submitted To: DR Indu Uprety
Company
Submitted to: Submitted by:
Dr Indu Uprety Parth Saxena (17/IFT/010)
Vanshika Srivastava (17/IFT/017)
Vaishali Mavi (20/PMB/
SWOT ANALYSIS
STRENGTHS: WEAKNESSES:
In the strengths, management should
identify the following points exists in the
• Improvement that could be done.
organization: • Activities that can be avoided for
• Advantages of the organization Reynolds Construction Case Study.
• Activities of the company better than • Activities that can be determined
competitors.
as your weakness in the market.
• Unique resources and low cost resources
company have. • Factors that can reduce the sales.
• Activities and resources market sees as the • Competitor’s activities that can be
company’s strength.
seen as your weakness.
• Unique selling proposition of the company.
SWOT ANALYSIS
OPPORTUNITIES: THREATS:
• Good opportunities that can be spotted. • Following points can be identified as
• Interesting trends of industry. a threat to company:
• Opportunities for Reynolds • Company’s facing obstacles.
Construction Case Study can be • Activities of competitors.
obtained from things such as:
Change in technology and market • Product and services quality
strategies. standards
Government policy changes that is related • Threat from changing technologies
to the company’s field.
Changes in social patterns and lifestyles. • Financial/cash flow problems
Local events. • Weakness that threaten the business.
Question 1
Reduce total project duration as much as possible without unnecessary additional costs.
Indicate the new critical path or paths. Show how much slack time remains in the noncritical
paths.
Solution: This is the original network diagram of the project
F
(7)
A
(3)
D End
(5)
B G
Start
(6) (4)
B G
Start
(6) (4)
Sta En
6 3
rt G d
C 2 E
5
Using the critical path diagram for remote building project from exhibit 2, the steps to
keep the project on track are:
Increase activity C to 5 weeks, we have to reduce activity G by one week to bring the path
CEG to 10 weeks as required and reduce D by one week. Hence
. F
5
A
Sta En
5 2
rt G d
C 2 E
2
Activity Original no. of No of weeks to New weeks for Additional Cost
weeks crash by each activity
A 3 1 2 5,000
D 5 2 3 8,000
G 4 2 2 14,000
F 7 2 5 6,000
B 6 1 5 6,000
Total 8 39,000
. F
7
A
Sta En
6 3
rt G d
C 2 E
2
• Planned cost + additional cost = $61,000 + 16,000 =$77,000 Using the total number
of weeks of 9 weeks for the project, Total cost at 9 weeks = $77,000
Hence, we (after reading this case and problems given in the case) reach to
the conclusion that Option B should be considered as the solution because
it has the cheapest cost ($107,000) for executing the project.