LSTK - J.Rajendra Babu
LSTK - J.Rajendra Babu
4) Hiring of Rigs
5) LSTK Contracts
2
What is LSTK Contract ?
3
What is the deciding factor for type of contract
4
What is basic difference betw een LSTK Contract and other contracts
5
Sanction Process
6
Terms and Conditions/Clauses
7
Some of the important clauses:
Change order:
Covered at Chapter 19 of Integrated MM Manual and at Para 22.3 of BDP.
Powers under change order approval
a) For Contracts with value up to ₹ 5 crore :
Functional Director : Up to 100% of original contract value
Concerned L1 : Up to 50% of original contract value
b) For Contracts with value more than ₹ 5 crore
EPC : Full Powers
Functional Director : Up to ₹ 50 crore each change order subject to sum of all change
8
Some of the important clauses:
Completion Certificate:
Completion Certificate is issued after completion of the entire Scope of work.
(Ref PMC Circular No: 42/2020) 42_2020 Completion Certificate.pdf
Warranty:
Warranty for completion project will start from date of completion certificate for the
period of 12 months.
Insurance:
Specific Insurance provisions applicable for LSTK projects issued by PMC covering
All risk policy, Cargo Transit Insurance, Third Party Liability and statutory
requirement of workmen compensation policy.
9
Some of the important clauses
Price Format :
1) Lumpsum Price format1 Annexure V Lumpsum Price Format Hot Oil .xlsx
2) Break-up of Lumsum prices – Material & Services.
2 Annexure V A Material price.xlsx, 3 Annexure V A Services price.xlsx
3) Taxes and Duties Proforma.
GST: Single GST on the works, not on the line item wise.
64_2020 Optimization of tax.pdf
10
Delay Analysis
As per para No: 18.2.5 (C) of IMMM in LSTK contracts delay analysis is carried out
on completion of delivery /work.
Joint statement (Delay analysis) to be signed by both ONGC and Contractor which
will be prepared by User at the level of TC. Concerned Level-II Officer of indenting
department shall have full powers.
TC will examine the delay analysis the quantum of LD will be approved by the CPA
on recommendation of TC. For EPC cases concerned Director can approve the TC
quantum of LD.16_2021_Joint Statement.pdf
11
Financial Criteria
Turnover of Bidders
For Goods 30% of bid value or more
12
Type of Bids allowed
Single Bidder
JV Bidder
Consortium Bids-Optional (depending of type of Scope of work)
Supporting Company (Applicable in ICB or specialized services in NCB)
57_2020 Eligibility Criteria.pdf
13
PRE-BID CONFERENCE
14
Technical comments/Technical evaluation report on offers
15(fifteen) days for LSTK days are allowed to Indentor / User to furnish the
Technical Comments/ Technical evaluation report in case of two bid system. In
case of LSTK projects by Offshore & Onshore Engineering Services,
preparation of technical evaluation report should be completed within 15 days
time and will be approved by Level II officer of design section within 3 days
and forwarded to MM section through Head Works.
15
Correspondence with bidders by indentors
16
Additional BG for Warranty period.
17