Professional Documents
Culture Documents
EWC-301 Lec-35 & 36 PERT CL 30 Dec 21
EWC-301 Lec-35 & 36 PERT CL 30 Dec 21
• Sum of activities timing along the activity path leading to that event.
=33.5
=32.7 𝑻
𝑬 =𝟑𝟗 . 𝟗
•Formulation
of Latest Allowable time ():
• (successor event)=(predecessor event)
- (activity duration)
=1.8
=0
=21.3 =24
• network showing earliest expected time () and latest
PERT
allowable occurrence time () .
𝑻
𝑳 =𝟐𝟑
=21
=17 =19
=11
• is slack?
What
• Difference between two times ie. () and ( indicates the
range between which the occurrence time of an event
vary.
• Slack may be defined as the difference between the
latest allowable time and the earliest expected time of an
event.
• S= -
Computation of Slack
• Slack for all event, except for event 40, is zero.
• Other events do not have any slack time and hence their
occurrences are critical.
What are the information slack gives?
11.
7
Thanks