Professional Documents
Culture Documents
Earned Value Management
Earned Value Management
1
Earned Value Management
What is it?
Where did it come from?
What’s so special about it?
How do you do it?
What is an EVMS?
2
Earned Value Management
What is it ?
A systematic approach to the integration and measurement of
cost, schedule, and technical (scope) accomplishments on a
project.
Provides the ability to examine detailed schedule information,
critical program and technical milestones, and cost data.
3
Earned Value Management
6
Earned Value Management
2500000
2000000
1500000
Actuals Budget
$1,041,000
1000000 Actuals
Budget $1,000,000
500000
0
l l
Ja
n ar ay Ju
p ov Ja
n ar ay Ju
p ov
M M Se N M M Se N
7
Earned Value Management
8
Earned Value Management
9
Earned Value
10
Earned Value
11
Earned Value Management
12
Planned Value
Data source is the Integrated Project Baseline
13
Planned Value
$2,500,000
$1,500,000
Planned Value
$1,000,000
$500,000
$0
14
Planned Value
$2,500,000
$2,000,000 $2,000,000
$1,500,000
Planned Value
$1,000,000
$500,000
PV = $1,000,000
$0
May
May
Nov
Nov
Mar
Mar
Jan
Jul
Jul
Jan
Sep
Sep
15
Actual Cost
Data source is the Earned Value Management System
16
Actual Cost
$2,500,000
AC = $1,041,000
$2,000,000
$1,500,000
Planned Value
Actual Cost
$1,000,000
$500,000
PV = $1,000,000
$0
r
r
ct
ct
n
n
l
l
Ap
Ap
Ju
Ju
Ja
Ja
O
17
Earned Value
Data source is the Earned Value Management System
18
Earned Value
$2,500,000
$2,000,000 $2,000,000
PV = $1,000,000
$1,500,000
Planned Value
Earned Value
$1,000,000
$500,000
EV = $851,000
$0
May
May
Nov
Nov
Mar
Mar
Jan
Jul
Jul
Jan
Sep
Sep
19
Integrated Performance Report
20
Integrated Performance Report
2,500,000
2,000,000
AC = $1,040,979
1,500,000 Planned Value
Actual Cost
1,000,000 Earned Value
PV = $1,000,000
500,000
EV = $851,000
0 May
May
Nov
Mar
Nov
Mar
Jan
Sep
Sep
Jul
Jul
Jan
21
Integrated Performance Report
These three data points allow us to:
22
Calculating Variances
Cost Variance
A comparison of the budgeted cost of work performed
with actual cost.
A negative variance means the project is over budget.
CV = EV – AC
CV = 851,000 – 1,041,000
CV = - $190,000
23
Calculating Variances
Schedule Variance
A comparison of amount of work performed to what was
scheduled to be performed.
A negative variance means the project is behind schedule.
SV = EV – PV
SV = 851,000 – 1,000,000
SV = - $149,000
24
Calculating Performance Indices
CPI = EV / AC
CPI = 851,000 / 1,041,000
CPI = 0.817
25
Calculating Performance Indices
SPI = EV / PV
SPI = 851,000 / 1,000,000
SPI = 0.851
26
Cost Performance
Cost Variance (EV-AC)
2,500,000 $851K - $1041K = -$190K
AC = $1,040,979 CPI (EV/AC) = 0.8175
PV = $1,000,000
2,000,000
EV = $851,000
500,000
May
May
Nov
Mar
Mar
Nov
Sep
Sep
Jul
Jan
Jan
Jul
27
Schedule Performance
Schedule Variance (EV-PV)
$851K - $1,000K = - $149K
2,500,000
PV = $1,000,000 SPI (EV/PV) = 0.851
AC = $1,040,979
2,000,000
EV = $851,000
Nov
Jan
Jan
Jul
Jul
Mar
Mar
Sep
Sep
May
May
28
Predicting Future Performance
29
Predicting Future Performance
30
Predicting Future Performance
BAC - EV
EAC = AC + CPI = $2,446,505
BAC - EV
EAC = AC + CPI * SPI = $2,691,856
31
Predicting Future Performance
1
TCPIC = CPI = 1.22
1
TCPIS = SPI = 1.17
1
TCPICS = CPI * SPI = 1.437
32
Earned Value Management
2,500,000
2,000,000 $2,000,000
1,500,000 AC = $1,000,000
PV = $1,000,000
1,000,000 EV = $1,000,000 Planned Value
Actual Cost
500,000
Earned Value
0
n p r l ct n p r l ct
Ja A Ju O Ja A Ju O
33