Professional Documents
Culture Documents
PERT and CPM (Pagal, Rodriguez)
PERT and CPM (Pagal, Rodriguez)
PERT and CPM (Pagal, Rodriguez)
1 2 3
PERT/CPM –
INTRODUCTI THREE
PROJECT
ON PHASES OF
REQUIREME
PERT/CPM
NTS
What is
PERT?
PERT is a Program Evaluation and Review
Technique.
What is
CPM?
CPM is the Critical Path Method.
PERT and
CPM?
These are networks developed independently in the later part
of 1950s.
3,000 contractors
11,000 sub-contractors
Developers of
CPM
T
Project Evaluation and Review Management technique which plans
Technique is a technique used to plan and controls complex but routine
Definition
and control large scale projects. projects.
Reasonable time
Suitable for
estimate estimate
Only serves the project manager to see the whole picture of the
entire job.
1. Gathering of all the necessary input data to make the PERT/CPM works.
2. Planning phase is the main work of the contractor for being familiar and
knowledgeable of his costing methods of doing business.
3. The contractor can seek assistance for the accomplishment of his work
particularly the gathering of data, but his basic responsibility on this
matter cannot be delegated to any outsider group.
Plannin
g most important consideration which includes:
In any project construction undertakings, planning is the
Updating of the diagram is based on the number of days the project is out of
schedule.
Controlling and
Monitoring
Flexibility and updated re-computations brought about by changing
conditions is the key to a successful network programming.
Controlling and
Monitoring
1. The contractor is supplied with time status report showing the overall
status of the project in general and in particular.
3. The contractor is supplied with cost status reports showing how much
money is being disbursed for what type of expenses.
A B a b
1 2 3
Elements of Networking or Diagram
DIAGRAM DESCRIPTION
C
B
A must be completed before either B or C can
A B start
C
Elements of Networking or Diagram
DIAGRAM DESCRIPTION
A B Both A and C must be completed before either B or C
can start
C D
Both A and B must be completed before C can start. D
depends only on B and A.
X is called dummy
A C
B D
Elements of Networking or Diagram
DIAGRAM DESCRIPTION
D depends on A and B.
A C C depends on A only.
Y is a dummy.
B D
Principles in Networking or Arrow Diagram
PRINCIPLE No. 1
That everything in the network or arrow diagram must have
a meaning, Thus;
a.) Every arrow represents an item of work and is Excavation
called Activity.
b.) An Event is the starting point of an Activity
represented by a circle, square or any geometrical Excavation
form.
c.) An Activity is dependent upon and cannot Making Pour Footing
Forms Slab
begin until after the completion of all preceding 3
Activities.
Order and
Deliver Cement
Principles in Networking or Arrow Diagram
PRINCIPLE No. 1
e.) All activities that start with the same event Making Pour Footing
cannot begin until after the completion of all Forms Slab
3
activities that enter that event.
Order and
Pour Pedestal
Deliver Cement
5 Batter Boards
That an activity has a single definite starting point and a single definite
ending point.
B
A
C
Principles in Networking or Arrow Diagram
PRINCIPLE No. 4
Concreting
Clearing Excavation Foundation Works
1 2 3 4 5
Fundamental Elements of PERT/CPM
EVENT Networking
S- a point signifying the beginning or end of one or more
activities
- denotes the completion of all preceding or predecessor
activities and the beginning of one or more succeeding
activities
Concreting
Clearing Excavation Foundation Works
1 2 3 4 5
Fundamental Elements of PERT/CPM
Networking
The EVENT is indicated on the network as any form of geological
symbols with a number written for identification.
Note:
a. Numbering the events follows the construction of the network
b. No two events shall have the same identification number
c. For this reason, one or more dummy activities may be used in a network
Fundamental Elements of PERT/CPM
Activities can either be: Networking
a. By their end points, such as 1-2; 2-4; etc.
b. By letter assigned to an arrow, such as a,b,c, etc.
c
a 2 4
Start 1 dummy f
d
b
3 5 6 End
e g
Fundamental Elements of PERT/CPM
DUMMY ACTIVITY Networking
c
a 2 4
Start 1 dummy
f
d
b
3 5 6 End
e g
Fundamental Elements of PERT/CPM
a.) Path 1-2-4-6 Networking
c
a 2 4
Start 1 f
1
b
3 e
5 g 6 End
Fundamental Elements of PERT/CPM
PATH Networking
Comments:
1. The length of time of any path can be determined by adding the
expected time of the activities along the path.
2. The path ith the longest time, catches management interset because it
governs the project completion time.
3. In short, the expected duration of a project is equal to the expected
time of the longest path
Fundamental Elements of PERT/CPM
PATH Networking
4. If there are delays along the longest path, naturally there is also a
corresponding delay in project completion time.
5. Therefore any attempt to shorten the project completion time must
concentrate on the longest sequence of activities because of its relation
to the completion time.
6. The longest path is the critical path and its activities are called
critical activties.
Fundamental Elements of PERT/CPM
PATH Networking
7. Paths that are shorter than the critical path may experience some
delay but may not affect the over all project completion time as long the
ultimate path time does not exceed the length of critical path.
8. The allowable slippage for any path is called path slack or float
time. It indicates the difference between the length of given path and
the length of the critical path.
9. The critical path then has a zero slack or float.
Fundamental Elements of PERT/CPM
Networking
RULES IN NUMBERING EVENTS IN A NETWORK DIAGRAM
F H M
4 5 6 9 10
D
G
J 8 L
THE NETWORK
DIAGRAM
Network Diagram
Network Diagrams are a graphical portrayal of the activities and
events of a project.
• They show how each activity relates to others in the project, the
sequence of activities, and the need to perform some tasks before
others. (https://acqnotes.com/acqnote/tasks/network-diagram)
PLANNING
PLANNING - is where the logical sequence of the job to be performed.
Considerations:
1. Logic sequence must be correct
2. All phases of works should appear
3. Scope of work is correctly interpreted
PLANNING
Resources:
PLANNING
OBJECTIVES
1. Represent graphically and proper sequence of the job.
2. Establish medium for estimating resources necessary for
each job.
3. Available sequential arrangement of jobs, accurate
estimate of resources, and alternative plan.
SCHEDULING
- secondary to planning.
- it is the process of allocating calendar dates to
jobs based on the approved plan.
DEFINITION OF
TERMS
Critical Path - longest route in the network of activities representing
project.
i-node j-node
Early Start - not the point in time that the activity will be over, but the earliest
time that it can occur. First day after physical assumption of activity.
DEFINITION OF
TERMS
Earliest Finish - is equal to its Earliest Start plus its duration of time.
EF = ES + Duration or
EF = Early Event + Duration
Latest Event time - is the latest time event may occur without delaying
project completion.
LE = CP – longest path from project and event to event in question
DEFINITION OF
TERMS
Latest Finish - is activity cannot be later than the latest time of its j-node.
LF = LS + D
Total Float/Activity Total Slack - the span of time an activity can be delayed
after its earliest start time
LS – EF = Total Float or
LS + D = (ES + D) or
LS – ES = Total Float
DEFINITION OF
TERMS
Free Float - is the span of time activity can be delayed after its early start.
FF = ES - (ES + D)
Independent Float - is that portion of the activities Free Float that would
remain if all its preceding activities used up all their float
I.F. = ES - (LF - D)
When the result is negative, means there is no independent float.
I.F. = 0
COMPUTING THE EARLY START AND EARLY
FINISH
Algorithm - used to develop 4 types of information, they are:
ES = Early Start
EF = Early Finish of time activity
LS = Latest Start
LF = Latest Finish
COMPUTING THE EARLY START AND EARLY
FINISH
After determining the value of each activity, proceed to…
EF = ES + t
Rule No. 2 :
For nodes with one entering arrow, ES for activities at such node is equal
to EF of the entering arrow.
For nodes with multiple entering arrows, the ES for activities leaving
such node is equals the largest EF of the entering arrow.
EARLY START AND EARLY FINISH
0
10 8
1 21 41
4
6 13
31 15 61
12 2
ACTIVITY DURATION ES EF
Equation:
1-2 10
ES=i-node
1-3 6
EF=ES + D 2-4 8
2-5 13
3-5 12
4-5 4
5-6 2
EARLY START AND EARLY FINISH
10 18
10 8
1 21 41
4
6 13
23 22 25
31 15 61
12 18 2
ACTIVITY DURATION ES EF
Equation:
1-2 10 0 10
ES=i-node
1-3 6 0 6
EF=ES + D 2-4 8 10 18
2-5 13 10 23
3-5 12 6 18
4-5 4 18 22
5-6 2 23 25
LAST START AND LAST FINISH
10 8
1 21 41
4
6 13
25
31 15 61
12 2
ACTIVITY DURATION LF LS
Equation:
5-6 2 25
EF=LF 4-5 4
LF=LS+D 3-5 12
LS=LF-D 2-5 13
2-4 8
1-3 6
1-2 10
LAST START AND LAST FINISH
0 11 19
8
1 10 21 41
5 10
4
6 13
23 25
31 15 61
12 2
11
ACTIVITY DURATION LF LS
Equation:
5-6 2 25 23
EF=LF 4-5 4 23 19
LF=LS+D 3-5 12 23 11
LS=LF-D 2-5 13 23 10
2-4 8 19 11
1-3 6 11 5
1-2 10 10 0
SOLVING THE FLOAT OR SLACK TIME
Equation:
Float=LS-ES
0 Float=LF-EF
10 8 Float=Critical Path-Length in weeks
1 21 41
4
6 13
31 15 61
12 2
Solving ES and
(days)
A Excavate B 3
B Foundation C,D 4
EF C
D
E
Rough Plumbing
Frame
Finish Exterior
H
E,F,G
H
3
10
8
F Install HVAC H 4
G Rough Electric H 6
H Sheet Rock I,J 8
I Install cabinets K 5
J
C=3 K
Paint
Final Plumbing M
L 5
4
A=3 B=4 L
M
Final Electric
Install Flooring
M
End
2
4
1 2 3
E=8
I=5 7 K=4
F=4 M=4
4 5 6 9 10
D=10 H=8
J=5
8 L=2
G=6
Solving ES and
EF
C=3
0 A=3 B=4
1 2 3 7
3 E=8 38
I=5 7 K=4
25 10 46
17 F=4 33 42 M=4
4 5 6 9 10
D=10 H=8
40
J=5
8 L=2
G=6
38
Activity Duration ES EF
Solving ES and 1-2
2-3
3
4
0
3
3
7
EF 3-4
3-5
10
3
7
7
17
10
4-5 8 17 25
5-6 8 25 33
6-7 5 33 38
6-8 5 33 38
C=3 7-9 4 38 42
A=3 B=4 8-9 2 38 40
9-10 4 42 46
1 2 3 7
3 E=8 38
I=5 7 K=4
25 10 46
17 F=4 33 42 M=4
4 5 6 9 10
D=10 H=8
40
J=5
8 L=2
G=6
38
Solving LS and
LF
C=3
0 A=3 B=4 22
1 2 3
3 38
7 E=8
I=5 7 K=4
17
33 46
F=4 25 M=4
4 5 6 9 10
D=10 21 H=8 42
35
19
J=5
8 L=2
G=6
40
Activity Duration LF LS
1 2 3
3 38
7 E=8
I=5 7 K=4
17
33 46
F=4 25 M=4
4 5 6 9 10
D=10 21 H=8 42
35
19
J=5
8 L=2
G=6
40