Professional Documents
Culture Documents
BUS1040 Lecture Week 5 SS21
BUS1040 Lecture Week 5 SS21
Additional Supplementary Resources: Watch the following video that explains and compares the 3 Project Planning Approaches (Waterfall, Sashimi, and
Agile)
Agile vs Waterfall Video
Gantt Charts
One of the oldest and most
useful methods of presenting
schedule information – still
used by many organizations
today
A None 5 days
B None 4 days
C A 6 days
D B 2 days
E B 5 days
F C,D 8 days
Step #1 –From the “Start”, identify the Tasks that do not have any Predecessor
Activities
35
Project Management: A Managerial Approach – Samuel J. Mantel, Jr. & Jack R. Meredith. Fourth Edition
Example: Constructing a
Network Diagram
Step #2 – Build on the tasks that depend on the completion of these tasks
Step #3 – Continue to build on the tasks that depend on the completion of these tasks.
When completed, make sure that the project is closed off at a single “END”
36
Project Management: A Managerial Approach – Samuel J. Mantel, Jr. & Jack R. Meredith. Fourth Edition
Example: Constructing a Network
Diagram
Step #4 – Add in the times required to complete each task.
Step #5 – Calculate Slack for activities which do not appear along the Critical Path
37
Project Management: A Managerial Approach – Samuel J. Mantel, Jr. & Jack R. Meredith. Fourth Edition
Slack / Float Time
Total float is the duration of delay allowed within the project which will
not interfere with the projected completion date
To calculate, compare the difference between the earliest start time
(EST) and latest start time (LST) for a specific task, in each path for
which it is a part. The lowest calculated slack time for a task, in each of
these paths, is the total slack time for that task
17
Approaches to Budget Estimation
1. The Top-Down Strategy
Top & middle management use their judgment & experiences to estimate an
overall total project cost
These cost estimates are then allocated to line managers for each sub-project
who allocate the budget to each of the required tasks and units
3. Parametric Estimating
Project characteristics (parameters) are expressed in a mathematical model/database
E.g (cost per square foot)
4. Analogous Estimating
Uses a previous similar project as the baseline
5. Three-Point Estimating
Manages estimate uncertainty and risk by defining most likely, optimistic, and
pessimistic scenarios (take the average of all 3…more weight to likely scenario)
People closest to the work participate and estimate within these guidelines