Construction of Gangapath from Digha to

Didarganj (20.5km) on EPC Mode

Revised Administrative Approval – 3390 Cr.


(HUDCO FNANACE 2000 Crs., Plan – 1390 Crs., Expenditure – 1340.38 Crs.)

Meeting on 27.05.2021
Location Map of Ganga Path from Digha to Deedarganj (20.5km)
on EPC Mode
Construction of Ganga Path from Digha to Deedarganj at Patna
in the State of Bihar (Phase-1).
• Administrative Approval : Rs.3160 Crores.
• Revised Administrative Approval : Rs.3390 Crores.
• Loan from HUDCO : Rs.2000 Crores
• Civil Agreement Amount : Rs.1777.3715 Crores
• Revised Contract price : Rs.1615.524 Crores
• Contractor : M/s Navayuga Engineering Co. Ltd.
• Agreement Date : 23.08.2013
• Appointed Date : 09.09.2013
• Completion Date : 24.12.2019 (from Digha to Ch.13.5 KM) (E.O.T Proposal
submitted upto 31.03.2023 for work upto Ch.13.5 KM) under review.
• Financial Progress : Rs. 973.78 Crore ( 60.28 %)
• Features :
• Total Length : 16.4 Km.
• Length of Elevated Structure : 7.6 km.
• Embankment length : 8.8 km.
• Service Road – 8.2 km., Vehicular Underpass – 03 Nos., Grade Separator
Interchange – 01 Nos., Underpass– 13 Nos., Toll Plaza – 02, Pedestrian
Walkways- 05 km. (river side)
• Connecting Road – 06 (Atal Path, LCT Ghat, A.N. Sinha Institute, PMCH
exclusive connectivity, Krishna Ghat & Gai Ghat)
Construction of Ganga Path from Digha to Deedarganj at Patna
in the State of Bihar (Phase-1).
Physical Progress (Work done up to to Ch. 13.500 (Main C/way Alignment)

Item No. Unit Total Executed Balance Work As On


Till 26th May, 2021 26.05.2021

Pile (727+184+76) No 987 719 268


Pile cap No 242 146 96
Pier No 225 124 101
Segment Casting No 2431 1514 917
Span Launching No 143 72 71
Earthwork Cum 56.68 47.68 9.00
(in Lac)
EMBANKMENT WORK at DIGHA ROTARY
GSB LAYING WORK
EMBANKMENT PROTECTION WORK
PILE WORK
SEGMENT LAUNCHING
JACK UP BARGE
Construction of Four Lane Elevated Road as part of Under Construction
Ganga Path (Digha to Deedarganj) From Dulli Ghat (Ch.13+525.79 Km) to
Nuruddin Ghat (Ch.16+975.79 Km), From Dharmashala Ghat (Ch.19+890
Km) to NH-30 along with Connectivity to Ashok Rajpath at Kangan
Ghat(Ch.15+700 Km) and Patna Ghat (Ch.16+600Km) with Allied Facilities
at Patna in the State of Bihar On EPC Mode
Project Cost – Rs.605.07 Cr.
Construction of Ganga Path from Digha to Deedarganj at
Patna in the State of Bihar, Phase-2
• Name of the Project : Construction of Four Lane Elevated Road as part of Under
Construction Ganga Path (Digha to Deedarganj) From Dulli Ghat (Ch.13+525.79 Km)
to Nuruddin Ghat (Ch.16+975.79 Km), From Dharmashala Ghat (Ch.19+890 Km) to
NH-30 along with Connectivity to Ashok Rajpath at Kangan Ghat(Ch.15+700 Km)
and Patna Ghat (Ch.16+600Km) with Allied Facilities at Patna in the State of Bihar On
EPC Mode

• Contractor : M/s G R Infra Projects Limited


• Agreement Date : 01.08.2020
• Appointed Date : 24.09.2020
• Completion Date : 24.03.2023
• Features :
» Total Length : 4.1 Km.
» Length of Elevated Structure : 4 km.
» Embankment length : 0.1 km.
» Connecting Road – 02 (At Kangan Ghat and Patna Ghat)
• Financial Progress: Rs. 98.57 Crores ( 16.29%) ahead scheduled milestone

• Physical Progress: (239/422) Piles,(36/104) Pile Cap & (2/104) Pier Cap Completed

• Connectivity : 2 Nos., Kangan Ghat & Patna Ghat


PILE WORK
PILE WORK
PILE CAP WORK
PIER WORK
CAMP NEAR KANGAN GHAT
CAMP AT DEEDARGANJ
Construction of Four Lane Elevated Road for an Exclusive
Connectivity from PMCH to Under Construction Ganga Path
at CH.7+400 Km at Patna in the State of Bihar on EPC Mode
Project Cost – Rs.131.00 Cr.
Construction of Four Lane Elevated Road for an Exclusive Connectivity
from PMCH to Under Construction Ganga Path, Phase-3

• Name of the Project : Construction of Four Lane Elevated Road


for an Exclusive Connectivity from PMCH to
Under Construction Ganga Path at Ch.7+400 Km at Patna in
the State of Bihar on EPC Mode
• Civil Agreement Amount : Rs. 131.00 Crores
• Contractor : M/s GAWAR Construction Limited
• Agreement Date : 31.07.2020
• Appointed Date : 13.10.2020
• Completion Date : 24.02.2022
• Features :
• Total Length : 1.112 Km.
• Length of Elevated Structure : 1.112 km.
• Embankment length : 0.00 km.
• Connecting Road – 01 (Exclusive at PMCH)

• Financial Progress: Rs. 55.02 Crore (42.00%) ahead Scheduled milestone


• Physical Progress :(107/113) Pile and (23/28) Pile Cap and (08/28) Pier Cap
executed.
PMCH CONNECTIVITY
PMCH CONNECTIVITY
PMCH CONNECTIVITY