Presentation on WPS (welding procedure

specification) and PQR (Procedure


Qualification Record)

Conducted By:
Shri Brijesh Kumar, AE(NQA)
WPS (welding procedure
specification)

2
WPS (welding procedure specification)

 Written qualified welding procedure

 To provide direction for making


production welds

 Code – requirements.

3
Contents of WPS

 All the basic details or parameters,


ranges and values

 Required for sound welding.

 These parameters are:

 Details of joints/ base metals / filler


metal/position / pre heat / post heat /
PWHT/ gas / electric characteristics /
welding techniques. 4
 WPS contains all the parameters
pertaining to the welding.

 Parameters are known as variables.

 Categories of variables

 Essential variables

 Non Essential variables

 Supplementary Essential variables


5
Essential Variables:

 Change in Essential variable affect


mechanical properties.

 Change in Essential variable from the


WPS will change mechanical properties
of weldments.

 Change in essential variable requires


requalify WPS.
6
Non Essential variable:

 Non essential Variables are those


which can be changed without
requalifying the WPS.

 We do not need to requalify our WPS


whenever we change Non Essential
variables.
 

7
Supplementary Essential variables:

 If toughness is a criterion then we use


supplementary Essential variables

 It acts as a Essential variables.

 Change in Supplementary Essential


variables, Requires requalify WPS.

 For each welding technique, there is


separate list
8
Sl No Welding Process Table

1 Oxyfuel Gas Welding (OFW) QW-252 & QW-252.1

2 Shielded Metal Arc Welding (SMAW) QW-253 & QW-253.1

3 Submerged Arc Welding (SAW) QW-254 & QW-254.1

4 Gas Metal Arc Welding (GMAW) QW-255 & QW-255.1

5 Gas Tungsten Arc Welding (GTAW) QW-256 & QW-256.1

9
10
11
Job Requirement

Prepare PWPS- Proposed (Preliminary) WPS

Prepare a Test Coupon/ Test Piece

Welding of Test Coupon

Send the test coupon to Lab for Mechanical test of Welding

If Report is satisfactory then our WPS is qualified means


PWPS is qualified WPS.

Conduct Welder Qualification Test (WQT) and post


satisfactory completion of WQT, start the Job.
12
13
PQR
(Procedure Qualification Record)

14
Procedure Qualification Record

 Real time values of


 Essential variables,
 Non Essential variables
 Supplementary Essential variables
 Lab Test Report

 PQR is a record of variables


recorded during welding of test
coupon. It also contains the test result
of the tested specimens.
15
Contents of PQR

1. Essential variables

2. Supplementary Essential variables

3. Non Essential variables

4. Lab test Report

16
Discussion