Civil Engineering Construction and


Graphics
Semester Project Group # 01
Group # 1
Our Group Members

 Muhammad Shoaib Rasool (2017-CE-50) Group Leader

 Zain-ul-Arifeen (2017-CE-04)

 Mohammad Hammad (2017-CE-26)

 Muhammad Rizwan (2017-CE-27)

 Nasreen Khushi Muhammad (2017-CE-47)


3
About Construction Site
 Construction Site Name
Mall Of Cantt

 Construction Site Location


SP Chowk, Abdali Colony, Multan,
Punjab

 Construction Company Name


Umair Estate Developers
4
5
About Construction Site
 Land Area
8727 Sft ( 38 marlas)

 Building Height
2 Basements , Ground Floor & 7 Suspended Floors
( 10 Storey Building)

 Unit
Single Unit (West Facing)

 Expected Completion
December 2019

 Site Engineer
Engr. Nadeem Qadri
6
PLAN
Ground Floor
Plan is consist of

13 Shops
02 Elevators
02 Escalators
01 Stair Case

7
MATERIALS

Bricks Cement Sand

Steel Mortar Timber 8


MATERIALS

Aggregates Concrete

Marble Plastic Pipes 9


Brick Ballast
MCHINERY

Concrete Mixer Tower Hoist

Vibrator Circular Saw


10
TOOLS

Plumb Bob Trowel

Line & Pins Mason Square 11


FOUNDATION
Foundation of this
structure is
Raft Foundation
(Mat Foundation)

In this Foundation
 Main & Distribution Bars are
#6@8” (T&B)
 Thickness of Raft is 36”
 Chair Height 28”
In Central Portion
 Main & Distribution Bars are
#6@4” (T&B)
12
This foundation is 27’ below Ground level and have following steps
 4” Thick PCC (1:4:8) Slab (Foundation Cover)
 36” RCC raft foundation having 3” Clear cover (All sides)
 Floor Topping

13
14
COLUMN &

BEAM SECTIONS
15
COLUMN

16
SITE PICS

17
BEAM

18
SITE PICS

19
RCC SLAB

20
21
RCC Slab is 2 way
slab and detail is
following
 Main Bars are #3@6” (S.S)
#4@6” (L.S)
 Thickness of Slab is 7”
Thickness = Shorter Span/30
 Chair Height 6”
 Top Bar length on beam is
11.5’
22
RCC Slab have Following
Bars Length

 Main Bars 64 of 15.75’ (S) each


having 8.5” Bending Allowance
 Main Bars 31 of 31.75’ (S) each
having 8.5” Bending Allowance

SECTION 23
SITE PICS

24
SITE PICS

25
26
FLOOR
27
SITE PICS
Floor of this structure is Marble Floor

Base Layer Under Layer (1:4:8)


3” Thick 3” Thick 28
29
30