Start Up Report

Initial Condition
• Unit 50 shutdown
• Level Hotwell = +- 1800
• Level FWT = +- 2750
• Level SD = +-120
• WTP available, Demin Tank +- 95% – 99%
• FO Day Tank Level Ok
• CCWP B running , CWP A running
Preparation
23/2/2021
Morning
21:00 Priming Condensate Line, then Start CEP A + treatment line condensate

24/2/2021
Night
02:23 Proses Fill and Purge BWCP
02:40 Changover Disch. Blowdown Sump Pump to Seal Pit
02:55 Purge and Bleed Vent Valve Open
03:10 Start Gravity Filling Boiler
03:40 Open make up chain valve condenser + butterfly valve
04:44 Drain Boiler via intermitten + emergency blowdown
05:00 Warm up aux steam intertie
05:45 Start Filling SSCC
06:07 Drain boiler complete (+- 1 Jam 23 menit)
06:08 Start Gravity Filling Boiler ke 2
06:26 Start Dosing pump 1 disch to condensate (fill and purge still inprogress)

24/2/2021
Morning
07:35 Intertite U5 and U6 aux steam open  then warm up aux steam
08:06 Start EFWP
08:07 Purge and bleed valve closed
08:15 Start CWP A
08:15 Start CWP C
08:25 Fill and Purge done, supply valve closed
08:45 SSCC Fully primed and sealed
08:45 Reset proteksi generator (CHA11/12)
09:10 Start BWCP B
09:30 Prestart Draft System (ID+FD)
09:48 Manual command on start natural purge
09:49 Start FGC Draft System
08:15 Start CWP A
08:15 Start CWP C
08:25 Fill and Purge done, supply valve closed
08:45 SSCC Fully primed and sealed
08:45 Reset proteksi generator (CHA11/12)
09:10 Start BWCP B