Genesis Energy Offices, Hamilton: Weekly Progress Update Construction Phase
Genesis Energy Offices, Hamilton: Weekly Progress Update Construction Phase
Construction Phase
August, 2020
480 160
31 Elpsed Time
Remaining
August
52%
43% Time
320 Total Delay
2020
Project Commencement date: 11 July 2019
Kickoff Meeting: 15 July 2019 820 D 425 D
Release of the AP: 16 July 2019 TOTAL DURATION ELAPSED DURATION
Mobilization completion: 15 Aug 2019
Commencement of Site Work: 01 Sep 2019
Completion of Piles Works: 22 Nov 19
planned Completion Date: 01 June 2021 350 D 45 D
Expected Completion Date: 15 July 2021 REMAINING DURATION TOTAL DELAY
Time Schedule Update
Construction Phase
Time Schedule
Items Finish Delay 30 Sep 19 30 Dec 19 31 Mar 20 30 June
20
30 Sep 20 30 Dec 20 30 Mar 21 30 Jun 21
Delay Analysis
Total 30 June 21 -66 Over all delay recorded up to 31 Aug 2020
10 Jul 19 30 Jun 19
Waterproofing 25 Nov 20 -60 60 days delay impact from the structure package
01 Oct 19 25 Nov 21
45 days delay from the structure package + 21
Mechanical 31 Mar 21 -66
16 Mar 20 31 Mar 21 from the package delay.
Electrical 31 Mar 21 -66 45 days delay from the structure package + 21
16 Mar 20 31 Mar 21 from the package delay.
Internal Finish 16 May 21 -66 66 days delay impact from the structure package
01 May 20 16 May 21
External Finish 10 May 21 -45 66 days delay impact from the structure package
10 Sep 20 10 May 21
Conveying Sys. 28 Feb 21 -66 45 days delay impact from the structure package
10 Aug 20 28 Feb 21
Landscape 31 May 21 -45 45 days delay impact from the structure package
15 Jul 20 30 May 21
Testing 30 June 21 -66 45 days delay impact from the structure package
15 Oct 21 30 Jun 21
2895
66 Total Activities
789
Completed Activities
372
Critical Activities
Days Delay
100,000,000.00
Performance 89,352,17
0.47
SPI = 0.92 81,843,20
8.67
10,000,000.00
90,000,000.00
The Project is behind 89.3% 80,000,000.00
Earned Value
the schedule according Planned
8,000,000.00 80,000,000.00
Acc. PV to the comparison
Acc. EV
7,000,000.00 70,000,000.00
made to the 60,000,000.00
6,000,000.00 60,000,000.00
accumulative planned 89,352,170.4
5,000,000.00 50,000,000.00 value against the Planned Value
4,000,000.00 40,000,000.00 accumulative earned
3,000,000.00 30,000,000.00 value from the project 40,000,000.00
2,000,000.00 20,000,000.00 start up to this update.
1,000,000.00
-
10,000,000.00
-
However, the
performance line is
81.8%
Completed 20,000,000.00
showing that there
was a trend for a good
1.00 performance during
1.00 Schedule Performance Line
the last 4 months 81,842,008.4
-
0.97 0.97 Earned Value PV EV
0.94 0.94
0.93
0.92 Time 90%
0.91
0.91 0.91
0.90 0.89 0.89 0.89 0.89
0.88
0.87 Progress 81.8%
0.85
Packages Tracking
Structural Package Finishing Package Elec. Package Mech. Package W.P Package Ex. Fin Package
81.5% 35,000,000.00
30,000,000.00
30,570,730,570,7
83.80 83.80
16,000,000.00
13,676,801
14,000,000.00 .13
16,000,000.00
13,785,504. 2,500,000.00
Completed 23,878,738 12,646,192 81 12,934,653. 2,022,812. 6,000,000.00 5,417,53
30,000,000.00 25,000,000.00 .04 .78 14,000,000.00 87 0.00
69
12,000,000.00
19,794,706 2,000,000.00 1,786,474.
12,000,000.00 10 5,000,000.00
25,000,000.00 .96
20,000,000.00 3,874,05
10,000,000.00 10,000,000.00
4,000,000.00 8.56
20,000,000.00 1,500,000.00
15,000,000.00 8,000,000.00 8,000,000.00
15,000,000.00 3,000,000.00
Structural 37% 30,570,783.8 10,000,000.00
6,000,000.00 6,000,000.00 1,000,000.00
10,000,000.00 2,000,000.00
Finishing 24% 19,794,706.9 4,000,000.00 4,000,000.00
5,000,000.00 500,000.00
5,000,000.00 2,000,000.00 2,000,000.00 1,000,000.00
Electrical 16% 12,646,192.7
- - - - - -
Mechanical 15% 12,934,653.8 ACC. PV ACC. EV ACC. PV ACC. EV ACC. PV ACC. EV ACC. PV ACC. EV ACC. PV ACC. EV ACC. PV ACC. EV
RC columns for the Annex Building Metal Duct Material Delivered Block Works is under progress for the
100%, and the fabrication is under Building #01 with progress reached to
have ben casted with 68%
Completed , and the curing process progress with 33% Completed 45%
is under progress
Ahmed Abdelfattah – Project Control Manager