Professional Documents
Culture Documents
Lecture 27 - Execution, Enforcement and Implementation of Award
Lecture 27 - Execution, Enforcement and Implementation of Award
Lecture 27 - Execution, Enforcement and Implementation of Award
Lecture 27
–
Enforcement, Execution and Implementation
of Award
Arbitral Award
• Partial Award
• Interim Award
• Final Award
Till Now we have studied ….
AWARD
Regulation and Execution of Decree –
International Awards
Award may be questioned during the transitional period in compliance with Section 34
of the Act
AFTER THIS TIME - authenticity of the arbitral award cannot be questioned any
further
IF Section 34 Application
YES NO
LIMITATION
Limitation Act 1963 Applies
Section 14 to 17
* Objections from the parties were invited. Where no objection was filed or
was sustainable, the court would pass a judgment in terms of the award and it was
then converted into a decree for enforcement.
A court executing the award will exercise all powers under the CPC which are available
to a court at the stage of execution of a decree
Leela Hotels Ltd v Housing & Urban Developing Corpn. Ltd (2012) 1 SCC 302)
This power is not limited by any other provision in the 1996 Act. For instance, though
section 33 enables a party to correct typographical/clerical errors, it does not take away
the power of the executing court under sections 152 and 153 of the CPC to make similar
amendments.
Manmohan Exims Pvt Ltd v Sarju International, 2005 (Suppl) Arb LR 206 relying on Hemanta Kumar
Ghosh v Rajendra Mondal, AIR 1935 Cal 619.
SECTION 31
Section 31(7)(b) –
* interest at 18% is applicable (from the date of award to the date of payment ) –
substituted 2015 to 2% higher than the rate
* The executing court cannot however award interest, where this has been
rejected by the arbitrator. Coal Linker v Coal India Ltd (2009) 9 SCC 491
* The date upto which interest would accrue would be the date when the
amount was available for release to the decree holder.
• The 1940 Act does not disable the parties from terminating their dispute in a way
different from the award.
• May supersede the arbitration and leave the parties to work out their submission in
accordance with the law outside the Arbitration Act.
Allahabad High Court - distinguished earlier authorities - held that under the 1996 Act,
the parties cannot modify or vary the terms of the award by agreement. A and A Restaurant
and Hotel Pvt Ltd v Dwarikajeet Restaurant Pvt Ltd, (2005) 1 Arb LR 526
to ensure that the mere filing of an application under section 34 does not operate
as an automatic stay on the enforcement of the award.
Henceforth a separate application for stay of operation of the award would have to be
filed. The stay application would be decided keeping with the principles laid down in
the Code of Civil Procedure.
BACKGROUND –
position of law was explained thus in National Aluminium Co. Ltd v Pressteel &
Fabrications Pvt Ltd (NALCO Case) - (2004) 1 SCC 540
2. R Knutson, “The Interpretation of Arbitral Awards — When is a Final Award Not Final?” 11 (2) J
Intl Arbn. 99 (1994).
3. Hanotiau “The Res Judicata effect of Arbitral Awards”, ICC International Court of Arbitration
Bulletin, Complex Arbitrations, Special Supplement, pp. 43-51 (2003).
5. National Aluminium Co. Ltd v Pressteel & Fabrications Pvt Ltd (NALCO Case) - (2004) 1 SCC 540
8. D.R. Dhanuka, “Award under Arbitration and Conciliation Act, 1996 and Insolvency Law”, 2007
(1) MLJ 1
9. Ashutosh Salil, “Role of Courts in the Enforcement of a Domestic Arbitral Award”, (2005) 3 Arb LR
12
10. Pavit Singh & Preeti Bishnoi, “Problems with Enforcing Arbitration Awards”, 2006 (6) Kar LJ 33
11. Sarita Woolhouse, “India: Appeal from a Domestic Arbitration Award to an International
Arbitration Tribunal — Two Conflicting Awards”, 10(1) Int. ALR 8 (2007)