PREPAIRED BY
ABHISHEK SINHA
TYPE OF GENERATOR COOLING
SYSTEM
TYPICALLY THERE ARE THREE TYPES OF GENERATOR COOLING SYSTEM
1. WATER & HYDROGEN COOLED
2. HTDROGEN COOLED
3. AIR COOLED
HYDROGEN/WATER 2/4 POLE STEAM H2 / WATER COOLED
COOLED TURBINE GENERATOR ABOVE 400MVA
TOTALISER
MB
FILTER
FM
FLOW METER
COOLER
DMCW
OUT
PW PUMP-1
DMCW
IN
PW PUMP-2
The Stator Cooling Water (SCW) system is used to provide a source of
de-mineralize water to generator winding for direct cooling of stator
winding and associated component.
The primary water is circulated in a closed circuit and dissipates the
absorbed heat to the secondary cooling water(DMCW) in the primary
water cooler.
Aim of primary water:
* Cooling of the stator windings
* Cooling of the phase connectors and bushings.
The water used must not contain any contaminants that might have a
harmful effect on the materials used in the primary water circuit. For this
reason, the water must have the following quality criteria :
*Conductivity : < 10 μs/cm.(Preferably 0.5 μs/cm.)
*pH : 6 – 8
*Dissolved O2 : Minimum, preferably less than 100 ppb
*Dissolved CO2 : Minimum, permissible conductivity
Primary Water Treatment System
MAKE-UP WATER
BUSHING
FROM OVER
HEAD TANK STATOR
DRAIN
TOTALISER
LOW CONDUCTIVITY
MB
FILTER
FM
FLOW METER
COOLER
DMCW
OUT
PW PUMP-1
DMCW
IN
PW PUMP-2
The direct contact between the primary water and the high-voltage
windings cause for a low conductivity of the primary water. During
operation, the electrical conductivity should be maintained below a value of
approximately 1 μ s/cm. In order to maintain such a low conductivity it is
necessary to provide for continuous water treatment.
1 3 2
MB
FILTER
FM
FLOW METER
COOLER
DMCW
OUT
PW PUMP-1
DMCW
IN
PW PUMP-2
SOP FOR PRIMARY WATER MAKE-UP :
N2 fill & purge properly before taking make-up in the system.
Lineup the source of makeup water from hotwell make-up pump.
Open the drain before the make -up line isolation valve- 1 for flushing of the make-up
line. Ensure there is no passing through the make-up isolation valve from the flow totaliser.
Take sample of drain water and check the chemical parameters from DM PLANT.
The parameters should be :
Conductivity : < 1 μ s/cm. ,Preferably( 0.5 μ s/cm)
pH : 6 - 8
Dissolved O2 : Minimum, preferably less than 100 ppb
Dissolved CO2 : Minimum, permissible conductivity
Take clearance from DM plant for taking make-up.
Now isolate the treatment system by closing valve no. 2 & ensure the flow meter
showing “0” reading.
Open valve no. 1 , slowly open valve no. 3 & N2 vent valve .Regulate the flow up to 3-
5 lpm max.
Now the make-up water will flow through the totaliser-ion exchanger-fine filter -flow
meter & then to the pump suction pipe. The totaliser will show reading in the display.
During the operation observe the conductivity of system water & always keep contact
with the control room engineer.
After taking make-up up to desired level close valve no. 1 & 3 .
Check there is no passing through the make-up isolation valve from the flow totaliser.
Check the NaOH dosing system working properly with the logic.
Fill & purge N2 to ensure a oxygen & other dissolve gas free system.
2
PG
b
4
3 a 6 PG
1
5 c
TO WAIST GAS
SYSYEM
1. Gas rake
2. Pressure gauge
FROM GAS RAKE 3. Pressure reducer
DRAIN
4. Primary water over
head tank
5. Pressure controller
N2 fill & purge procedure: