Boiler Cleanup Cycle
Boiler Cleanup Cycle
Boiler Cleanup Cycle
Ranjan Kumar
NTPC Ltd
Click to edit Master
Operational Focustitle style
• Boiler Startup
• Boiler Loading
• Load Reduction
• Shutdown and Boiler cooling
• Lay up
Boiler Startup
• ASLD availability
• FEGT Monitoring by
• FTP
• HVT - water cooled HVT probe above 538 deg C
• Acoustic Pyrometer
Advantages:
Strategies to be adopted:
1. Review of startup curve provided by OEM to incorporate new learnings and best practices
2. Post startup analysis to over come potential barriers
3. Extensive use of PI Process Book.
4. Dynamic startup curve in DCS
5. Control loop tuning for automated startup.
6. Experienced Senior Operator during startup in each shift.
7. Availability of maintenance technician during startup
8. Simulator training to shift operators
9. Conducting pre-startup activities
20%
0%
0 50 100 150 200 250 300 350
Time in min
iv. Water from Boiler drain recovery tank will over flow to atmosphere until Fe level
comes below 500 ppb at its discharge.
v. Cold cleanup is complete now.
5. Hot cleanup:
Light up the boiler
Separator pressure is to be maintained around 5 to 10 Ksc.
Feed water temperature should not go beyond 2000C.
Separator pressure ramp rate will be 0.05 Ksc/min.
SH dry out process will take around 100 minute.
SH drains and vents (except startup vents) are closed at 5 Ksc of separator pr.
5. Hot cleanup:
Now create temperature swing between 1500C and 2000C by controlling oil
burners maintaining separator pressure between 5 to 10 Ksc.
2000C
1500C
Process continues until feed water quality at eco inlet achieves following
limits:
Fe < 30 ppb
SiO2 < 50 ppb
ACC < 0.35 µs/cm
If outage duration is more than 3 days, boiler may be preserved preferably under
dry layup. If not, wet preservation may be carried out with Nitrogen blanketing.
Boiler should always be filled with DM water having DO < 100 ppb.
SH circuit should be filled preferably with attemperator water to avoid impurities
carry over from feed water circuit to SH circuit.
If outage duration is more than 4 weeks, cold and hot cleanup cycle operation should
be carried out to prepare the unit for load operation within next 4 weeks without any
significant time consumption in cleanup cycle.