Professional Documents
Culture Documents
Processing Station Screw Press: Ir. Amin Buhari MD Zain Sime Darby Plantation SDN BHD
Processing Station Screw Press: Ir. Amin Buhari MD Zain Sime Darby Plantation SDN BHD
SCREW PRESS
PART II
• Maintenance
– Press design is very simple and complete overhaul of
the major wear items can be completed within one day
(provided all spares are available)
– Maintenance cost between 30 – 50 cents/ton ffb
– Lifespan of screws between 600hrs – 1200hrs depend
to the trash inclusion in the fruits
– Lifespan of press cage between 600hrs – 1500hrs
– Clearance between new screw and new press cage is
not more than 5mm and should not be allowed to
exceed 12mm to minimize oil loss and nut breakage.
P15 Screw Press
• BASIC SPECIFICATIONS
– Electric motor 37kw / 760rpm / 3 phase
– Worm Screw 305mm dia x 1200mm L, feed section pitch
270mm , Extraction section pitch 190 root 100mm dia
shaft
– Capacity 14 – 16 tons ffb per hour (32-40amps load)
– Screw speed 10.6 rpm (200mm dia pulley) 12
rpm(170mm dia pulley)
– Oil loss in fibre of less than 7% oil in NOS (dry basis)
– Broken nuts less than 7% on sample or 12% broken nuts
to total nuts
Operation of The Screw Press
• Ensure that digester is not left full overnight
• Start digester arm when the digester is empty
• The digester steam jacket should always be on
steam
• Live steam should be added to bring mash
temprature to above 90 deg C
• Excessive drainage at bottom of digester should be
necessary (in most cases it is undesirable)
Operation of Screw Press
• When the digester is over half full, it is in order to
start the screw press
• Start the press motor and open fully digester chute
• The hydraulically controlled cones should be
manually controlled until the press cake is of
satisfactory condition. This initial manual operation
is to prevent the passage of any oily cake into CBC
as well as to avoid jamming over dried cake in the
press.
• The automatic control to follow
Screw Press Operations
• Operator should close the cone to start the
pressing process and open them to allow full cake
flow
• The cones should then be closed slowly to obtain
the required balance of dry fibre without too high
a broken nut content
– (Note: Broken nuts in themselves are not important
when the nut recovery system has a facility for their
recovery but crushed kernels are always to be avoided)
Screw Press Operations
• It is necessary to have a supply of hot water
(say 95 deg C) opened as this water will
passes over the outside of the cage carrying
with the crude oil. The supply of water
should be in the order of 1800litres or
400gallons per hour for throughput 10 ton
per hour. The correct adjustment will have
to be made to correspond with the proper
operation of the clarification plant.
Upkeep Screw Press
• It is a normal practices by the some mills to
rebuild their worm screw
• For new screw, first time rebuild only necessary on
the first flight of the screw
• Build up by welding to original thickness of
approximately 30 mm
• When the other flights have been worn by 6mm to
10mm, then its should be build up by welding on
both sides
• Before machining to the outside diameter of
305mm, the welds should be ground smooth as it
will reduce nut breakage and promote an even
wear.
Upkeep Screw Press
• It is a good practice to have a spare cage and set of
screws.
• It is recommended that the two sets be
interchanged over every 600 hours. Few users find
it necessary to make more frequent change but
some prefer to extend the change to every 1000
hours.
• A set of screws and a cage with proper upkeep
will last for between 4000 to 6000 hours (that is to
say for 40,000 ton ffb to 60,000 ton ffb)
THANK YOU