Project Crashing
Project Crashing
Normal Time : The normal time is the activity duration under normal circumstances.
Normal Cost : The direct cost associated with the normal completion time. This is the
minimum direct cost required for performing that activity .
Crash time : The minimum possible time in which an activity can be completed.
Crash cost : The direct cost associated with crash time of an activity . When an activity is
crashed , its direct cost will increase.
Crash Time < Normal Time
Crash Cost > Normal Cost
COST SLOPE
OPTIMAL COST & OPTIMAL TIME
OPTIMAL COST & OPTIMAL TIME
CRASHING PROCEDURE
CRASHING PROCEDURE
EX 1
Paths (days) Cost
crashing
A-F A-D-G B-G C-E-G Direct cost indirect total Cost
Before 11 13 10 8 713 400 1113
Crashing
crashing A by 1 10 12 10 8 743 250 993
day
crashing D by 1 10 11 10 8 793 175 968
day
crashing D by 1 10 10 10 8 843 100 943
day