Professional Documents
Culture Documents
Bidding Stage
Bidding Stage
Topic Outline
1. Notice to Bidders
2. Bid Package
3. General Conditions
4. Supplementary Conditions
5. Technical Specifications
6. Addenda
Topic Outline
7. Decision to Bid
8. Prequalification
9. Subcontractor and Vendor Quotations/Contracts
10.Bid Bond
11.Performance and Payments Bonds
12.Cost and Requirements for Bonds
Notice to Bidders
This document announces to prospective bidders that design
documents are available for consideration and that the owner is
ready to receive bids.
6. Owner’s responsibilities
7. Engineer’s responsibilities
8. Changes in the work
9. Change of contract price
10.Change of contract times
General Conditions
Some topics that are typically considered in the general
conditions are listed below:
These documents establish the basis for determining the bid price
and influence the willingness of the prospective bidder to bid or
enter into a contract.
Addenda
It is important, therefore, that the bid package documents
accurately reflect the project to be constructed and the
contract administration intentions of this owner or of the
owner’s representative.
The key to this entire process is the fact that these predictions
are made based on past experiences and the ability of the
estimator to sense potential trouble spots that will affect field
cost.
Decision to Bid
The accuracy of the result is a direct function of the skill of the
estimator and the accuracy and suitability of the method by
which these past experiences were recorded.
Given that the estimate is the basis for determining the bid
price of a project, it is important that the estimate be carefully
prepared.
Decision to Bid
Studies reveal the fact that the most frequent causes of
contractor failure are incorrect and unrealistic estimating and
bidding practices.
Decision to Bid
The quantities of materials must be developed from the
drawings by an expert in quantity takeoff.
They then add to the totaled project direct costs those indirect costs that
cannot be assigned directly to a particular estimating item (project
supervising costs).
In effect, the owner asks the firm to submit its “resume” for
consideration.
The contractor does not prepare a bid and incur the inherent cost unless he
can qualify.
On the other hand, the owner does not find herself in the position of being
under pressure to accept a low bid from a firm she feels cannot perform
the work.
If the owner feels the contractor will not be able to successfully pursue the
work, the owner can fail to prequalify the contractor.
Subcontractor & Vendor Quotations/Contracts
The contractor integrates these quotations into the total bid price.