Professional Documents
Culture Documents
Lecture 3 - Project Management
Lecture 3 - Project Management
Lecture 3 - Project Management
Project Management
A C F Finish
Start
B D E
Probability of 1 in 100
of a Occurring
Probability
Probability of 1 in
100 of b Occurring
Activity Time
Most Most Most
Optimistic Likely Pessimistic
Time Time Time
(a) (m) (b)
Figure 13.2
Note: Beta distribution can be understood as representing a distribution of
probabilities- that is, it represents all the possible values of a probability when we
© 2009 Prentice-Hall, Inc. 13 – 12
don't know what that probability is.
Activity Times
The formula for the expected activity time (t)
(from previous slide) is written below:
a 4m b
E( t)
6
= 1.222
A 10 C4 F5 Finish
Start
B5 D3 E6
A 10 C 4 F 5
0 10 10 14 16 21 Finish
Start
B 5 D 3
0 5 5 8 E 6
10 16
For activity A: (EF=ES + the expected activity time), ES =
0 and EF = 0 + 10 = 10; for C: ES=10 and EF= 14 (10 + 4);
Note: ES for F:choose the largest EF(16) of E rather then
smaller EF(14) of C © 2009 Prentice-Hall, Inc. 13 – 21
The latest start time and the latest
finish time by backward pass
A 10
C 4 F 5
0 10
10 14 16 21
0 10
12 16 16 21 Finish
Start
B 5 D 3
0 5 5 8 E 6
2 7 7 10 10 16
10 16
A 10
C 4 F 5
0 10
10 14 16 21
0 10
12 16 16 21 Finish
Start
B 5 D 3
0 5 5 8 E 6
2 7 7 10 10 16
10 16
The slack (or total float), s = LS(latest start time) – ES(earliest start
time) or s = LF – EF. Slack: the length of time an activity can be
delayed without affecting project completion time . © 2009 Prentice-Hall, Inc. 13 – 23
Critical path: slack=0. Since the slacks
for activities A, E and F are all zero,
these activities lie on the critical path.
These activities cannot be delayed as
any delay will affect the project
completion time.
Critical path: A-E-F
Project completion time = 21 weeks.
*Thus critical paths are determined by
identifying the activities with zero
slacks.
© 2009 Prentice-Hall, Inc. 13 – 24
Eg. 2: General Foundry Example of
PERT/CPM
General Foundry, Inc. has long been trying to
avoid the expense of installing air pollution
control equipment
The local environmental protection group has
recently given the foundry 16 weeks to install a
complex air filter system on its main smokestack
General Foundry was warned that it will be forced
to close unless the device is installed in the
allotted period
They want to make sure that installation of the
filtering system progresses smoothly and on time
A C F
Build Internal Construct Install Control
Components Collection Stack System
E H
Start Inspect Finish
Build Burner
and Test
B D G
Modify Roof Pour Concrete Install Pollution
and Floor and Install Frame Device
Figure 13.1
Table 13.2
A 2 C 2 F 3
E 4 H 2
Start Finish
B 3 D 4 G 5
Figure 13.3
A 2 C 2 F 3
0 2 2 4 4 7
E 4 H 2
Start 4 8 13 15 Finish
B 3 D 4 G 5
0 3 3 7 8 13
Figure 13.4
For activity H
LS = LF – t = 15 – 2 = 13 weeks
A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15
B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13
Figure 13.5
Note: LF=Smallest of LS for following activities
e.g. C: LF= 4 rather than 10 © 2009 Prentice-Hall, Inc. 13 – 32
How to Find the Critical Path
Once ES, LS, EF, and LF have been determined, it
is a simple matter to find the amount of slack
time that each activity has
Slack = LS – ES, or Slack = LF – EF
From Table 13.3 we see activities “A, C, E, G, and
H have no slack time”
These are called critical activities and they are
said to be on the critical path
The total project completion time is 15 weeks
A 2 C 2 F 3
0 2 2 4 4 7
0 2 2 4 10 13
E 4 H 2
Start 4 8 13 15 Finish
4 8 13 15
B 3 D 4 G 5
0 3 3 7 8 13
1 4 4 8 8 13
Figure 13.6
0 0.90
= 0.5 – 0.1841
-0.9 0
= 0.3159
0.1841 0.5
© 2009 Prentice-Hall, Inc. 13 – 40
E.g. 2: Probability of Project
Completion
The critical path analysis helped determine the
expected project completion time of 15 weeks (air
pollution filter)
But variation in activities on the critical path can
affect overall project completion, and this is a major
concern
If the project is not complete in 16 weeks, the
foundry will have to close
PERT uses the “variance of critical path activities”
to help determine the variance of the overall project
Critical path: A-C-E-G-H
ACTIVITY VARIANCE
A 4/36
B 4/36
C 4/36
D 16/36
E 36/36
F 64/36
G 64/36
H 4/36
P(T ≤ 16 Weeks)
≤ (16 – 15) / √ 3.11
0.57) = 0.5 + 0.2157
=0.71566
That means there is a 71.6% probability this
project can be completed in 16 weeks or less
A - 3 2 800 1400
B - 2 1 1200 1900
C A 5 3 2000 2400
D B 5 3 1500 2300
E C, D 6 4 2000 2800
F C, D 2 1 600 1000
G F 2 1 500 1000
A3 C5 F2 G2 Finish
Start
B2 D5 E6