Professional Documents
Culture Documents
Basic Esttmation
Basic Esttmation
PREFACE
In era globalization and monetary crisis,
competition in the market to obtain the job is very very
hard. We as a Construction Company need and have to
sharpen our Quotation in order to penetrate the market,
get the job and survive.
materials.
OBJECTIVE
The primary purpose of this training is to
enable the trainee to gain fundamental
knowledge of estimating the cost of
projects to be constructed in order they
can do estimating either for the tendering
or budgeting purpose.
3
INTRODUCTION
The purpose of estimating is to determine the forecast
costs required to complete a project in accordance with
the contract plans and specifications, with reasonable
profit and still within the owner's budget.
There are two types of estimates, approximate
estimates (preliminary, conceptual, or budgetary
estimates) and detailed estimates (final or definitive
estimates).
4
FLOW OF ESTIMATION PROCESS
MARKETING
PM or Proposal
Mgr in charge
Instruction To Bidder
- Description of the Project
- Scope of Work / Supply
INQUIRY
- Bill of Material / Quantity
DOCUMENT - Material Specification
- B/Q or MTO
- Time Schedule
- Productivity Data - General Terms & Conditions
- Material Price - Special Conditions
- Manpower rates - Codes and Procedures
ESTIMATION
- Equipment rates - Drawings
PROCESS
- Transport. rates
- Premi Insurance
- Taxes rates - Cover letter
- Summary of Price
- Others COST - Terms & Conditions
ESTIMATES/ - Scope of Works Division
QUOTATION/ - Price Breakdown
BUDGET - Construction Schedule
- Manpower Schedule
- Equipment Schedule
- Others, as per Client
requirements 6
FINISH
COST CATEGORY
DIRECT INDIRECT OVERHEAD
COST COST & PROFIT
QUOTATION PRICE
OR
TENDERING PRICE
7
COST COMPONENT
DIRECT INDIRECT OVERHEAD
COST COST & PROFIT
1. Direct Labour
1. Job Site Indirect Cost 1. Overhead & Profit
- Contractor Staff
- Temporary Facilities - Overhead
- Onsite area
- Tools - Profit
- Offsite area - Temporary Material
- Consumables
- Utility area - Insurances
2. Mob Demob /
2. Direct Material Transportation Cost
- Imported materials - Personnel
- Indirect material
- Local procured materials - Equipment & Tools
3. Head Office Cost
3. Construction Eqpt. - Engineering Cost
- Other expenses
4. Taxes and Duties 8
DIRECT COST
9
Direct Labour
This item represents costs for the labour directly engaged in the
construction of the permanent facilities of the Plant.
10
Direct Material
11
Construction Equipment
12
INDIRECT COST
13
Contractor Staff
14
Temporary Facilities
15
Tools
16
Temporary Materials
17
Consumables
18
Insurances
19
Mob Demob/Transportation
20
Head Office Cost
21
Tax and Duties
22
OVERHEAD & PROFIT
23
DATA REQUIREMENTS
- B/Q or MTO
- Productivity Data
- Material Price
- Manpower rates
- Equipment rates
- Transport. rates
- Premi Insurance
- Taxes rates
- Others
24
Bill of Quantity or Materials Take-Off
QUANTITY
No. Item Number Equipment Name Nos Unit Weight
QUANTITY
No. Ref. Drawing Item Size Specification Qty Unit
1 Utility Area
1 U-M001-1234-00 Pipe 8" PE, SCH 40, API 5L Gr.B 150 m
2 Elbow 8" BW, SCH 40, ASTM A234 WPB 18 ea
3 Gate Valve 8" 150#, RF, BB, OS&Y, STD TRIM, ASTM A216 WCB 12 ea
4 Flange 8" 150#, SO, RF, ASTM A105, SCH 40 24 ea 25
Productivity Data
26
Productivity Data (Erection Work)
A STEEL STRUCTURE
1 Light Structure 60 Mhr/T
2 Medium Structure 55 Mhr/T
3 Heavy Structure 50 Mhr/T
C PIPING
1 Carbon Steel Pipe 3.5 Mhr/DI
2 Stainless Steel Pipe 4.5 Mhr/DI
3 Alloy Steel Pipe 4.5 Mhr/DI
D EQUIPMENT
1 Vessel / Drum / Reactor 50 Mhr/T
2 Heater/Cooler/Cooling Twr. 40 Mhr/T
3 Pump/Compressor/Blower 60 Mhr/T
4 Aux. Boiler 60 Mhr/T
5 Recovery Boiler/HRSG 70 Mhr/T
6 Boiler & Accessories 80 Mhr/T
7 Steam Turbine 65 Mhr/T
8 Gas Turbine 40 Mhr/T
9 Water Turbine/Hydro Power 65 Mhr/T
10 Electrostatic Precipitator 60 Mhr/T
11 FGD 60 Mhr/T
12 Stack/Chimney 70 Mhr/T
13 Conveyor 70 Mhr/T
14 Stacker/Reclaimer 60 Mhr/T
15 Unloader 60 Mhr/T
E OTHERS
1 Refractory 175 Mhr/T
2 Insulation & lagging 9.0 Mhr/m2
3 Painting 1.6 Mhr/m2
F CIVIL WORK
1 Excavation 4.5 Mhr/m3
2 Backfill & Compaction 3.6 Mhr/m3
3 Formwork 2.8 Mhr/m2
4 Rebar work 110 Mhr/T
5 Concrete work 4.46 Mhr/m3
6 Grouting work 5.0 Mhr/m3
1 DIRECT LABOUR
2 CONTRACTOR STAFF
3 TEMPORARY FACILITY
4 CONTRACTOR EQUIPMENT
5 TEMPORARY MATERIALS
6 ERECTION TOOLS
7 CONSUMABLES
8 MOB DEMOB
9 INSURANCE
10 ANCILIARY
11 MATERIALS HANDLING
12 ASSIST. IN COMMISSIONING
TOTAL
ROUNDED
28
S UMMARY OF PRICE
A DIRECT COST
1 A0100-00 DIRECT LABOUR - 520,992.86 3.83%
2 A0400-00 PERMANENT MATERIALS 71,213.00 0.52%
3 A0500-00 TEMPORARY MATERIALS 636,916.00 4.69%
4 A0300-00 CONSUMABLES 1,457,918.56 10.73%
5 A0600-00 TOOLS 601,539.68 4.43%
6 A0700-00 EQUIPMENT 2,285,896.24 16.82%
7 A0700-01 VEHICLE 203,235.00 1.50%
8 A0800-00 SUB CONTRACTOR 2,498,468.06 18.38%
TOTAL DIRECT COST 8,276,179.39 60.89%
B INDIRECT COST
1 B0200-00 CONTRACTOR STAFF 4,160.23 2,992,336.74 22.01%
2 B1000-00 TEMPORARY FACILITY 800,000.00 5.89%
3 B1000-01 SITE OPERATIONAL COST 800,000.00 5.89%
4 B1100-00 HEAD OFFICE EXPENSES 106,320.00 0.78%
5 B1100-01 PREVENTION COST 42,588.00 0.31%
6 B1400-00 APPRAISAL COST 33,340.00 0.25%
7 B1700-00 FAILURE COST 11,112.50 0.08%
8 B0900-00 INSURANCE 209,519.78 1.54%
9 B1100-02 SAFETY 6,610.44 0.05%
10 B1300-00 MOBILIZATION & DEMOBILIZATION 315,000.00 2.32%
TOTAL INDIRECT COST 5,316,827.46 39.11%