Professional Documents
Culture Documents
Tutorial 5 - : Cost Management
Tutorial 5 - : Cost Management
Cost Management
Total Budgeted Cost (TBC)
Cumulative Budgeted Cost (CBC)
Cumulative Actual Cost (CAC)
Cumulative Earned Value (CEV)
The TBC of each work package will be the sum of the costs of all activities
that make up that work package.
Weeks
TBC 1 2 3 4 5 6 7 8 9 10 11 12
Design 24 4 4 8 8
Build 60 8 8 12 12 10 10
Install &
Test 16 8 8
Total 100 4 4 8 8 8 8 12 12 10 10 8 8
Total
budget Cumulative 4 8 16 24 32 40 52 64 74 84 92 100
cost
Cumulative Budget cost
)In $ thousands(
2.Cumulative Budgeted Cost (CBC)
Cumulative Budget cost
)In $ thousands(
100
90
80
TBC 1 2 3 4 5 6 7 8 9 10 11 12
70
Design 24 4 4 8 8
Total budget cost
Build 60 8 8 12 12 10 10
60
Install &
50
Test 16 8 8
Total 100 4 4 8 8 8 8 12 12 10 10 8 8
Cumulative 4 8 16 24 32 40 52 64 74 84 92 100 40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12
Weeks
WEEK
TBC 1 2 3 4 5 6 7 8 9 10 11 12
Design 24 4 4 8 8
Build 60 8 8 12 12 10 10
Install &
Test 16 8 8
Total 100 4 4 8 8 8 8 12 12 10 10 8 8
Cumulative 4 8 16 24 32 40 52 64 74 84 92 100
At the end of week 8 , $ 68000 has actually been expended on this project
Earned value = the total budgeted cost X the percentage of the work
performed.
WEEK
1 2 3 4 5 6 7 8
Design 10 25 80 90 100 100 100 100
Build 0 0 0 5 15 25 40 50
Install &
Test 0 0 0 0 0 0 0 0
WEEK
TBC 1 2 3 4 5 6 7 8
Design 24 2.4 6 19.2 21.6 24 24 24 24
Build 60 3 9 15 24 30
Install &
Test 16
Cumulative 100 2.4 6 19.2 24.6 33 39 48 54
70
$68000
$64000
60
$54000
50
CBC
40 CAC
CEV
30
20
10
0
1 2 3 4 5 6 7 8
5. Cost Performance Index
(CPI)
Cost Performance Analysis
As a project Manger you have to analyse the
performance of your project on regular basis.
$64000 = budgeted through the end of week 8 (CBC)
$68000 = actually performed at the end of week 8 (CAC)
$54000 = earned value of the work actually performed by the end of week 8 (CEV)
CPI = $54000/$68000=0.79
This ration indicates that for every $1 actually spent, only 0.79 of earned value was
received.
CV = CEV – CAC
CV = $54000-$68000= -$14000
162
160
150
140
123.8
120
100
80
60
40
20
0
week 1 week 2 week 3 week 4 week 5 week 6 week 7 week 8 week 9