Contract No.

HY/2018/02
Central Kowloon Route – Kai Tak East
WKR TTA Sequence for Paving Works
(2020 – 07 – 15)

Contract No. HY/2018/02 1


Central Kowloon Route – Kai Tak East
TTA Sequence

Contract No. HY/2018/02 2


Central Kowloon Route – Kai Tak East
TTA – WKR SB SL

Works:
Concrete breaking
Temporary reinstatement by bituminous
Duration:
5 days
Work at 1000 - 1600
Tentative Period:
31st Aug (Mon) – 4th Sep (Fri)

Contract No. HY/2018/02 3


Central Kowloon Route – Kai Tak East
TTA – WKR SB SL

Works:
Temporary bituminous reinstatement
Concrete pavement reinstatement
Road marking
Duration:
2 weeks (24 hours TTA)
Work at 1200 noon (Sat) – 0600 (Mon)
Tentative Period:
5th Sep (Sat) – 7th Sep (Mon)
12th Sep (Sat) – 14th Sep (Mon)

Contract No. HY/2018/02 4


Central Kowloon Route – Kai Tak East
TTA – WKR SB SL

Works:
Bituminous Pavement Reinstatement
Road Marking
Duration:
1 day
Work at 2300 - 0600
Tentative Period:
14th Sep (Mon)

Contract No. HY/2018/02 5


Central Kowloon Route – Kai Tak East
TTA – WKR ISLAND

Works:
Existing kerb island removal
Relocation of temporary traffic signal
Duration:
5 days (24 hours TTA)
Work at 0800 - 1800
Tentative Period:
14th Sep (Mon) – 18th Sep (Fri)

Contract No. HY/2018/02 6


Central Kowloon Route – Kai Tak East
TTA – WKR ISLAND

Works:
Road opening and excavation
Draw pit construction
Temporary reinstatement by bituminous
Duration:
2 weeks (24 hours TTA)
Work at 1200 noon (Sat) – 0600 (Mon)
Tentative Period:
19th Sep (Sat) – 21st Sep (Mon)
26th Sep (Sat) – 28th Sep (Mon)

Contract No. HY/2018/02 7


Central Kowloon Route – Kai Tak East
TTA – LHS ISLAND

Works:
Kerb island relocation
Road opening and excavation
Draw pit construction
Tactile installation
Duration:
3 weeks (24 hours TTA)
Work at 1200 noon (Sat) – 0600 (Mon)
0800 (Thur) – 0600 (Mon) at National Day and
Mid Autumn Festival)
Tentative Period:
29th Sep (Sat) – 21st Sep (Mon)
26th Sep (Sat) – 28th Sep (Mon)
1st Oct (Thur) – 5th Oct (Mon)
(National Day and Mid Autumn Festival)

Contract No. HY/2018/02 8


Central Kowloon Route – Kai Tak East
TTA – LHS EB

Works:
Concrete breaking
Temporary reinstatement by bituminous
Duration:
5 days
Work at 1000 - 1600
Tentative Period:
5th Oct (Mon) – 9th Oct (Fri)

Contract No. HY/2018/02 9


Central Kowloon Route – Kai Tak East
TTA – LHS EB

Works:
Temporary bituminous removal
Concrete pavement reinstatement
Road marking
Duration:
3 weeks (24 hours TTA)
Work at 1200 noon (Sat) – 0600 (Mon), 1200
noon (Sat) – 0600 (Tue on Chung Yeung Festival)
Tentative Period:
10th Oct (Sat) – 12th Oct (Mon)
17th Oct (Sat) – 19th Oct (Mon)
24th Oct (Sat) – 27th Oct (Tue)
(Chung Yeung Festival)

Contract No. HY/2018/02 10


Central Kowloon Route – Kai Tak East
TTA – WKR NB SL

Works:
Concrete breaking
Temporary reinstatement by bituminous
Duration:
4 days
Work at 1000 - 1600
Tentative Period:
27th Oct (Tue) – 30th Oct (Fri)

Contract No. HY/2018/02 11


Central Kowloon Route – Kai Tak East
TTA – WKR NB SL

Works:
Temporary bituminous removal
Concrete pavement reinstatement
Road marking
Duration:
3 weeks (24 hours TTA)
Work at 1200 noon (Sat) – 0600 (Mon)
Tentative Period:
31st Oct (Sat) – 2nd Nov (Mon)
7th Nov (Sat) – 9th Nov (Mon)
14th Nov (Sat) – 16th Nov (Mon)

Contract No. HY/2018/02 12


Central Kowloon Route – Kai Tak East
TTA – WKR NB SL

Works:
Bituminous Pavement Reinstatement
Road Marking
Duration:
1 day
Work at 2300 – 0600
Tentative Period:
16th Nov (Mon)

Contract No. HY/2018/02 13


Central Kowloon Route – Kai Tak East
TTA – WKR NB SL

Works:
Concrete breaking
Temporary reinstatement by bituminous
Duration:
5 days
Work at 1000 - 1600
Tentative Period:
16th Nov (Mon) – 20th Nov (Fri)

Contract No. HY/2018/02 14


Central Kowloon Route – Kai Tak East
TTA – WKR NB SL

Works:
Temporary bituminous removal
Concrete pavement reinstatement
Road marking
Duration:
2 weeks (24 hours TTA)
Work at 1200 noon (Sat) – 0600 (Mon)
Tentative Period:
21st Nov (Sat) – 23rd Nov (Mon)
28th Nov (Sat) – 30th Nov (Mon)

Contract No. HY/2018/02 15


Central Kowloon Route – Kai Tak East
TTA – WKR NB FL

Works:
Concrete breaking
Temporary reinstatement by bituminous
Duration:
5 days
Work at 1000 - 1600
Tentative Period:
30h Nov (Mon) – 4th Dec (Fri)

Contract No. HY/2018/02 16


Central Kowloon Route – Kai Tak East
TTA – WKR NB FL

Works:
Temporary bituminous removal
Concrete pavement reinstatement
Kerb island construction
Traffic signal relocation and installation
Road marking
Duration:
3 weeks (24 hours TTA)
Work at 1200 noon (Sat) – 0600 (Mon)
Tentative Period:
5th Dec (Sat) – 7th Dec (Mon)
12th Dec (Sat) – 14th Dec (Mon)
19th Dec (Sat) – 21st Dec (Mon)

Contract No. HY/2018/02 17


Central Kowloon Route – Kai Tak East
TTA – WKR NB FL

Works:
Bituminous Pavement Reinstatement
Road Marking
Duration:
1 day
Work at 2300 – 0600
Tentative Period:
21st Dec (Mon)

Contract No. HY/2018/02 18


Central Kowloon Route – Kai Tak East
TTA – WKR NB FL

Works:
Concrete breaking
Pavement Reinstatement
Road Marking
Temporary reinstatement by bituminous
Duration:
4 days (24 hours TTA)
Work at 1000
7am-7pm
- 1600
Tentative Period:
21st Dec
Dec (Mon)
(Mon) –– 24
24thth Dec
Dec (Fri)
(Thur)

Contract No. HY/2018/02 19


Central Kowloon Route – Kai Tak East
TTA – WKR NB FL

Works:
Temporary bituminous removal
Concrete pavement reinstatement
Road marking
Duration:
2 weeks (24 hours TTA)
Work at 0800 (Fri (X’MAS)) – 0600 (Mon)
1200 noon (Sat) – 0600 (Mon)
Tentative Period:
25th Dec (Fri) – 28rd Nov (Mon)
2nd Jan (Sat) – 4th Jan (Mon)

Contract No. HY/2018/02 20


Central Kowloon Route – Kai Tak East
TTA – WKR SB FL

Works:
Concrete breaking
Temporary reinstatement by bituminous
Duration:
5 days
Work at 1000 - 1600
Tentative Period:
4th Jan (Mon) – 8th Jan (Fri)

Contract No. HY/2018/02 21


Central Kowloon Route – Kai Tak East
TTA – WKR SB FL

Works:
Temporary bituminous removal
Concrete pavement reinstatement
Road marking
Duration:
3 weeks (24 hours TTA)
Work at 1200 noon (Sat) – 0600 (Mon)
Tentative Period:
9th Jan (Sat) – 11th Jan (Mon)
16th Jan (Sat) – 18th Jan (Mon)
23th Jan (Sat) – 25th Jan (Mon)

Contract No. HY/2018/02 22


Central Kowloon Route – Kai Tak East
TTA – WKR SB FL

Works:
Bituminous Pavement Reinstatement
Road Marking
Duration:
1 day
Work at 2300 – 0600
Tentative Period:
25th Jan (Mon)

Contract No. HY/2018/02 23


Central Kowloon Route – Kai Tak East
TTA – WKR SB FL

Works:
Concrete breaking
Temporary reinstatement by bituminous
Duration:
5 days
Work at 1000 - 1600
Tentative Period:
25th Jan (Mon) – 29th Jan (Fri)

Contract No. HY/2018/02 24


Central Kowloon Route – Kai Tak East
TTA – WKR SB FL

Works:
Temporary bituminous removal
Concrete pavement reinstatement
Road marking
Duration:
2 weeks (24 hours TTA)
Work at 1200 noon (Sat) – 0600 (Mon)
Tentative Period:
30th Jan (Sat) – 1st Feb (Mon)
6th Feb (Sat) – 8th Feb (Mon)

Contract No. HY/2018/02 25


Central Kowloon Route – Kai Tak East
TTA – WKR SB SL

Works:
Concrete breaking
Temporary reinstatement by bituminous
Duration:
4 days
Work at 1000 - 1600
Tentative Period:
8th Feb (Mon) – 11th Feb (Thur)

Contract No. HY/2018/02 26


Central Kowloon Route – Kai Tak East
TTA – WKR SB SL

Works:
Temporary bituminous removal
Concrete pavement reinstatement
Road marking
Duration:
1 week (24 hours TTA)
Work at 0800 (Fri (CNY)) – 0600 (Tue)
Tentative Period:
12th Feb (Fri) – 16th Feb (Tue)

Contract No. HY/2018/02 27


Central Kowloon Route – Kai Tak East
TTA – WKR SB SL

Works:
Bituminous Pavement Reinstatement
Road Marking
Duration:
1 day
Work at 2300 – 0600
Tentative Period:
16th Feb (Tue)

Contract No. HY/2018/02 28


Central Kowloon Route – Kai Tak East
TTA – WKR SB SL

Works:
Concrete breaking
Temporary reinstatement by bituminous
Duration:
4 days
Work at 1000 - 1600
Tentative Period:
16th Feb (Tue) – 19th Feb (Fri)

Contract No. HY/2018/02 29


Central Kowloon Route – Kai Tak East
TTA – WKR SB SL

Works:
Temporary bituminous removal
Concrete pavement reinstatement
Road marking
Duration:
2 weeks (24 hours TTA)
Work at 1200 noon (Sat) – 0600 (Mon)
Tentative Period:
20th Feb (Sat) – 22nd Feb (Mon)
27th Feb (Sat) – 1st Mar (Mon)

Contract No. HY/2018/02 30


Central Kowloon Route – Kai Tak East
TTA – WKR NB SL

Works:
Concrete breaking
Temporary reinstatement by bituminous
Duration:
5 days
Work at 1000 - 1600
Tentative Period:
1st Mar (Mon) – 5th Mar (Fri)

Contract No. HY/2018/02 31


Central Kowloon Route – Kai Tak East
TTA – WKR NB SL

Works:
Temporary bituminous removal
Concrete pavement reinstatement
Road marking
Duration:
2 weeks (24 hours TTA)
Work at 1200 noon (Sat) – 0600 (Mon)
Tentative Period:
6th Mar (Sat) – 8th Mar (Mon)
13th Mar (Sat) – 15th Mar (Mon)

Contract No. HY/2018/02 32


Central Kowloon Route – Kai Tak East
TTA – WKR NB SL

Completed
Total Period = 31st Aug – 15th Mar (196 days)

Contract No. HY/2018/02 33