Professional Documents
Culture Documents
Csos Abandonment Scheme Design
Csos Abandonment Scheme Design
SCHEME DESIGN
1
Goals
Carrying out hydraulic analysis using InfoWorks software to:
CSO
2. Design CSO abandonment scheme
To avoid flooding in section A & downstream
for the 40-year return period
Identify storage solution
2
Current performance of the CSO (rainfall
data)
1. 1-year rainfall event:
3
Current performance of the CSO (critical
storm)
2. The 5-year storm was determined to be the worst:
surcharging and some insignificant flooding in section to be redesigned
4
Consequences of abandoning the CSO -rainfall
data
1. For the 1-year recorded rainfall only one manhole flooded
5
Consequences of abandoning the CSO – critical
storm
2. 40-year rain storm (M40-30) was Critical – total flood volume of 5,288m3
7
Design Alternative 1: Online Storage
Advantages
• Efficiently use the existing space - no additional land required
Disadvantages
due to the site topography, the pipes would have to be laid deep in
the ground to have and efficient storage system.
Cannot do civil works while system is functioning
The length of the section is not sufficient to store the required
amount of sewage and storm water along the line
Tank storage
Pipe storage
9
Design approach
1. Flooding to be controlled upstream of the section under redesign
10
Design approach
2. A rectangular storage tank (25x25x6m) will be used with a pump to
return the stored volume back to the main sewer line
Rectangular shape take less space compared to a shaft or circular tank
Initial flood volumes estimated at 5,288 m3
3. Storage volume was optimised to 3800 m3 because the pump is
working at the same time as the water flows into the tank
4. Orifice and pump to control flow downstream
Pump flow + orifice flow not to exceed 240l/s downstream
11
Design Layout
.
12
Simulation results
Flow in SK35393202.1 limited to 240l/s during peak flow (M30-120)
13
Simulation results
No flooding in the redesigned network section
14
Issues to consider for the design
Regular inspections for the pumps
• Pump failure might cause flooding as well as septic conditions in the storage tank
The diameter of the orifice is very small due to the 240l/s limit at the
downstream
• Orifice may cause clogging due to its sharp edges and size thus regular removal of
litter/debris is required
• Provide storage downstream to allow more flow
A screen should be installed at the weir to prevent debris from collecting into
the tank
urban creep and climate change are likely to cause an increase in flooding if
not addressed
• Additional investments will be required to accommodate the flows
15