Professional Documents
Culture Documents
Materials Requirement Planning (MRP) : The Approach To Coordinated Scheduling For Dependent Demand Items
Materials Requirement Planning (MRP) : The Approach To Coordinated Scheduling For Dependent Demand Items
(MRP)
The approach to coordinated
scheduling for dependent
demand items.
Introduction to lean 1
The Responsibility of Manufacturing
activities
1. Design requirements and specifications and standards.
2. Be manufactured economically and environmentally
friendly.
3. Build-in quality at each stage.
4. Production methods must be sufficiently flexible to
respond to changing market demands, types of
products, production rates, and production quantities and
to provide on-time delivery to the customer.
5. New developments in materials, production methods,
and computer integration of both technological and
managerial activities.
6. Safety.
Introduction to lean 2
Production Planning and Control
Planning and control of the flow of materials through the
manufacturing process
1. Production planning
Production must be able to meet the demand of the
marketplace
a). Forecasting
b). Master planning
c). Material requirements planning
d). Capacity planning
2. Implementation and control
3. Inventory management
Introduction to lean 3
Production Planning System
Introduction to lean 4
Material Requirements Plan (MRP)
Introduction to lean 5
Example 1.
Amalgamated Fish Sinkers makes a product group of fresh
fish sinkers and wants to develop a production plan for
them. The expected opening inventory is 100 cases, and
they want to reduce that to 80 cases by the end of the
planning period. The number of working days is the same
for each period. There are no back orders. The expected
demand for the fish sinkers is as follows:
Introduction to lean 7
Answer
a). Total production required = 600 + 80 - 100 = 580 cases
Production each period = 580 / 5 = 116 cases
Period 1 2 3 4 5 Total
Forecast
(cases) 110 120 130 120 120 600
Production 116 116 116 116 116 580
Ending
100
Inventory
Introduction to lean 8
b). Ending inventory = opening inventory + production - demand
Ending inventory after the first period = 100 + 116 - 110 = 106 cases
+ - =
Period 1 2 3 4 5 Total
Forecast
(cases) 110 120 130 120 120 600
Production 116 116 116 116 116 580
Ending
Inventory
100 106
Introduction to lean 9
b). Ending inventory = opening inventory + production - demand
Ending inventory after the first period = 100 + 116 - 110 = 106 cases
+ - =
Period 1 2 3 4 5 Total
Forecast
(cases) 110 120 130 120 120 600
Production 116 116 116 116 116 580
Ending
Inventory
100 106
Introduction to lean 10
c). The total cost of carrying inventory would be:
(106 + 102 + 88 + 84 + 80)($5) = $2300
d). Since there were no stockouts and no changes in the level of
production, this would be the total cost of the plan.
Period 1 2 3 4 5 Total
Forecast
(cases) 110 120 130 120 120 600
Production 116 116 116 116 116 580
Ending
Inventory
100 106 102 88 84 80
Introduction to lean 11
Master Scheduling
Production plan:
Families of products
Master production schedule (MPS):
End items.
It breaks down the production plan into the requirements for
individual end items, in each family, by date and quantity.
The total of the items in the MPS should be equal to the total
shown on the production plan.
Master Scheduling 12
Master Scheduling
Master Scheduling 13
Example 1.
The Hotshot Lightning Rod Company makes a
family of two lightning rods, Models H and I. It bases
its production planning on months. For the present
month, production is leveled at 1000 units. Opening
inventory is 500 units, and the plan is to reduce that
to 300 units by the end of the month. The MPS is
made using weekly periods. There are four weeks in
this month, and production is to be leveled at 250
units per week. The forecast and projected available
for the two lightning rods follows. Calculate an MPS
for each item.
Master Scheduling 14
Answer
Production Plan:
Period 1 2 3 4 Total
Projected
500 450 350 300 300
Available
Master Scheduling 15
Forecasts for individual end items , Model H and I
Period 1 2 3 4 Total
Master Scheduling 16
Master Schedule: Model H:
Period 1 2 3 4 Total
Forecast 200 300 100 100 700
Projected
200 250 200 100 100
Available
MPS 250 250 100
Master Scheduling 19
MRP Process
Releasing orders
MRP 21
MRP Process
MRP 22
Example 2:
Using the product tree and lead times shown in
figure below, determine the planned order receipts
and releases. There are 50 As required in week 5.
Suppose there are 10 Bs available as well as the 20
As.
MRP 23
Week
Part #
1 2 3 4 5
Gross Requirements 50
Projected Available 20 20 0
A Net requirements
Planned Order Receipt
30
30
Planned Order Release 30
Gross Requirements
Projected Available 10
B Net requirements
Planned Order Receipt
Planned Order Release
Gross Requirements
Projected Available
C Net requirements
Planned Order Receipt
Planned Order Release
Gross Requirements
Projected Available
D Net requirements
Planned Order Receipt
Planned Order Release
Gross Requirements
Projected Available
E Net requirements
Planned Order Receipt
Planned Order Release
MRP 24
Week
Part #
1 2 3 4 5
Gross Requirements 50
Projected Available 20 20 0
A Net requirements
Planned Order Receipt
30
30
Planned Order Release 30
Gross Requirements 30
Projected Available 10 10 0
B Net requirements
Planned Order Receipt
20
20
Planned Order Release 20
Gross Requirements 30
Projected Available 0
C Net requirements
Planned Order Receipt
30
30
Planned Order Release 30
Gross Requirements
Projected Available
D Net requirements
Planned Order Receipt
Planned Order Release
Gross Requirements
Projected Available
E Net requirements
Planned Order Receipt
Planned Order Release
MRP 25
Week
Part #
1 2 3 4 5
Gross Requirements 50
Projected Available 20 20 0
A Net requirements
Planned Order Receipt
30
30
Planned Order Release 30
Gross Requirements 30
Projected Available 10 10 0
B Net requirements
Planned Order Receipt
20
20
Planned Order Release 20
Gross Requirements 30
Projected Available 0
C Net requirements
Planned Order Receipt
30
30
Planned Order Release 30
Gross Requirements 20
Projected Available 0
D Net requirements
Planned Order Receipt
20
20
Planned Order Release 20
Gross Requirements 20
Projected Available 0
E Net requirements
Planned Order Receipt
20
20
Planned Order Release 20
MRP 26
MRP Process
Scheduled Receipts:
Promised materials
Become available to use immediately
Open Orders:
Incomplete orders that have not been fully satisfied
Example, we completed the production of markers but do
not have packaging
Net Requirements (Modified) = gross requirements-
scheduled receipts – available inventory
MRP 27
Example 3:
Week 1 2 3 4
Gross Requirements 50 250 100 50
Scheduled Receipts 200
Projected Available 150
Net requirements
Planned Order Receipt
Planned Order Release
MRP 28
Answer
Week 1 2 3 4
Gross Requirements 50 250 100 50
Scheduled Receipts 200
Projected Available 150 100
Net requirements
Planned Order Receipt
Planned Order Release
Week 1 2 3 4
Gross Requirements 50 250 100 50
Scheduled Receipts 200
Projected Available 150 100 50
Net requirements
Planned Order Receipt
Planned Order Release
MRP 29
Answer Week 1 2 3 4
Gross Requirements 50 250 100 50
Scheduled Receipts 200
Projected Available 150 100 50
Net requirements 50
Planned Order Receipt 50?
X
Planned Order Release
Week 1 2 3 4
Gross Requirements 50 250 100 50
Scheduled Receipts 200
Projected Available 150 100 50 150
Net requirements 50
Planned Order Receipt 200
Planned Order Release 200
MRP 30
Example 1 of MRP
Introduction to lean 31
Example 2 of MRP
Introduction to lean 32
Example 3 of MRP
Introduction to lean 33
References
Introduction to lean 34